Inland Empire Dry Wall Supply Co. v. Western Surety Company

389 P.3d 717, 197 Wash. App. 510
CourtCourt of Appeals of Washington
DecidedJanuary 10, 2017
Docket34022-8-III
StatusPublished
Cited by2 cases

This text of 389 P.3d 717 (Inland Empire Dry Wall Supply Co. v. Western Surety Company) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Inland Empire Dry Wall Supply Co. v. Western Surety Company, 389 P.3d 717, 197 Wash. App. 510 (Wash. Ct. App. 2017).

Opinions

Pennell, J.

¶1 Washington law allows for the recording of a bond to free up property encumbered by a construction lien. When this happens, the bond is substituted for the property and a hen claimant can take legal action against the bond. The question we confront here is who must be sued when a claim is filed against a lien release bond. The [512]*512procedural statute governing lien release bonds unambiguously identifies only the bond surety as an interested party. This is consistent with general suretyship principles, which allow a claimant to seek relief directly against a surety. Because the trial court erroneously ruled that a claim against a hen release bond could not be made solely against a surety, the judgment in this matter is reversed.

FACTS1

¶2 Inland Empire Dry Wall Supply Company entered into a credit and sales agreement with Eastern Washington Dry wall & Paint (EWD&P) for a construction project. EWD&P had been subcontracted by Fowler General Construction, the project’s general contractor, to provide labor and materials for the project. Over the course of the construction project, Inland purportedly supplied $124,653.05 in drywall materials to EWD&P.

¶3 Fowler provided EWD&P with funds to pay Inland, but EWD&P never paid Inland and eventually ceased working on the project. Inland ultimately initiated a lien against the project for money owed. It filed a preclaim lien notice against the owner of the project, Western States Development Corporation, as required by RCW 60.04.031. Inland then timely recorded the lien as required by RCW 60.04.091.

¶4 In order to release the project from Inland’s lien, Fowler obtained a release of lien bond in the amount of $186,979.57 from Western Surety Company (Western). The bond identifies Fowler as the “Principal,” Western as the “Surety,” and Inland as the “Obligee.” Clerk’s Papers at 84-85.

¶5 After the hen release bond was recorded, Inland filed an action against Western in Spokane County Superior Court to recover on its lien. Fowler was not named a party [513]*513to the suit. Western answered Inland’s complaint and raised several affirmative defenses, including that by failing to name and include Fowler as a necessary and indispensable party, Inland had not satisfied the statute of limitations requirements in chapter 60.04 RCW. Both parties filed motions for summary judgment.

¶6 Relying on our decision in CalPortland Co. v. LevelOne Concrete, LLC, 180 Wn. App. 379, 321 P.3d 1261 (2014), the trial court granted summary judgment in favor of Western. The trial court reasoned that under Cal-Portland, when legal action is taken to foreclose on a lien release bond, the statute of limitations under RCW 60.04.141 for service of the lawsuit on a property owner is replaced by an analogous statute of limitations requiring service on a bond’s principal and surety. The court ruled that because Inland named only Western as a party and served it as the bond’s surety, the statute of limitations was not met and Western was discharged from liability and entitled to judgment in its favor. Inland filed a motion for reconsideration, but the motion was denied. Inland appeals.

BACKGROUND

¶7 This case concerns chapter 60.04 RCW, also known as the “mechanics’ lien” or “construction lien” statute. See id. at 385-86. This statute sets forth a lien procedure to protect the financial interests of persons contributing labor, materials, or equipment to a construction project. If construction costs are not paid, the statute allows a lien to be placed against the construction project property as a method for financial recovery. Given the burdens on property imposed by construction hens, the statute sets forth strict time limits. One asserting a claim of lien must bring an action to foreclose the lien within 8 months of recording the claim. RCW 60.04.141. The property owner must be served with notice of the suit within 90 days. Id. A hen claimant who fails to comply with these time constraints loses all rights to [514]*514recover on the lien. See Bob Pearson Constr., Inc. v. First Cmty. Bank of Wash., 111 Wn. App. 174, 178, 43 P.3d 1261 (2002).

¶8 Apart from protecting the rights of property owners by requiring strict time compliance, the statute also sets forth a bond procedure that can be used to free up construction project property from a lien prior to resolution of claims. RCW 60.04.161. Under the hen release bond statute, a variety of persons disputing the validity of a lien can obtain and record a bond, including a property owner, a contractor, or a lender. Id. While the statute allows for flexibility with respect to who can initiate a bond, it has strict requirements for bond sureties. A surety must be authorized to issue bonds in the state and must comply with federal bonding requirements. The statute also states a bond “surety shall be discharged from liability under the bond” if “no action is commenced to recover on a hen within the time specified in RCW 60.04.141.” Id. In other words, strict time frames for filing suit apply in the lien release bond context, not just the regular hen context.

¶9 The procedure for obtaining relief against a lien release bond under RCW 60.04.161 has been the source of considerable confusion. Relevant here, questions have arisen with respect to who the necessary parties are when a bond has been obtained to release property from a lien. Without a bond, the statute is fairly straightforward. The owner of the real property must be made a party to the suit, along with any person who, prior to commencement of the action, has a recorded interest in the property which the lien claimant seeks to have affected. RCW 60.04.141, .171. But who must be served when a bond releases a piece of property? This is the source of the parties’ dispute.

¶10 We attempted to resolve this confusion in Cal-Portland. In that case, like this one, a general contractor recorded a lien release bond prior to the filing of suit. Unlike this case, the hen claimant served both the general contractor as hen principal and the surety company. How[515]*515ever, the owner of the underlying real property was not sued. Initially, the trial court dismissed the hen claim, holding the real property owner was a necessary party. We reversed. As we explained, because a bond operates to release real property from being encumbered by a lien, once the bond is recorded, the real property owner is no longer an interested party.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
389 P.3d 717, 197 Wash. App. 510, Counsel Stack Legal Research, https://law.counselstack.com/opinion/inland-empire-dry-wall-supply-co-v-western-surety-company-washctapp-2017.