John Schellenberg and Lisa Schellenberg v. First State Bank Central Texas

Court of Appeals of Texas·Decided November 20, 2014·No. 13-13-00195-CV·Published

Opinion

NUMBER 13-13-00195-CV

COURT OF APPEALS

THIRTEENTH DISTRICT OF TEXAS

CORPUS CHRISTI - EDINBURG

JOHN SCHELLENBERG AND LISA SCHELLENBERG, Appellants,

v.

FIRST STATE BANK CENTRAL TEXAS, Appellee.

On appeal from the 53rd District Court of Travis County, Texas.

MEMORANDUM OPINION

Before Chief Justice Valdez and Justices Rodriguez and Benavides Memorandum Opinion by Justice Rodriguez This is a negligent misrepresentation and fraudulent inducement case brought

incident to a bankruptcy proceeding. Appellants John Schellenberg and Lisa

Schellenberg, plaintiffs in the trial court, challenge the traditional summary judgment granted in favor of appellee First State Bank Central Texas (FSB). By four issues, the

Schellenbergs argue that the trial court erred in granting summary judgment to FSB

because (1) their claims sound in tort and not contract; (2) the evidence was insufficient

to show that their causes of action had accrued at the time of the signed release; (3) the

evidence was insufficient to show that the representations made by FSB were true; and

(4) the evidence was insufficient to show that their reliance on FSB’s representations was

unreasonable. We affirm.

I. Background1

It is undisputed that in early 2006, the Schellenbergs contracted with a mortgage

broker, Roger Rheinheimer, to help them secure a construction loan. Rheinheimer

arranged a one-year interim construction loan for the Schellenbergs through FSB. The

interim loan imposed a one-year construction deadline and was conditioned on the

Schellenbergs securing permanent financing to refinance the interim loan at the

completion of construction.

The interim loan agreement was executed by the parties on August 10, 2006. In

their petition, the Schellenbergs allege that both Rheinheimer and an FSB loan officer

told them that permanent financing was "sourced and locked" at the time of the interim

loan contract. In a letter, which was attached as evidence to FSB's motion for summary

judgment, Mortgage Acceptance Corporation (MAC) committed to provide permanent

financing; the commitment letter also conditioned financing on the completion of

1 This case is before the Court on transfer from the Third Court of Appeals in Austin pursuant to a

docket equalization order issued by the Supreme Court of Texas. See TEX. GOV'T CODE ANN. § 73.001 (West, Westlaw through 2013 3d C.S.).

2 construction within one year of the interim loan agreement, or by August 10, 2007. The

parties dispute whether the Schellenbergs ever saw this commitment letter. Finally, as

part of the loan agreement, the Schellenbergs paid a $7,720 commitment fee to MAC; the

Schellenbergs allege that Rheinheimer told them that this fee was necessary to secure

the permanent financing.

It is undisputed that during the summer of 2007, the parties began to question

whether the Schellenbergs were going to meet their August 10 construction deadline.

The Schellenbergs alleged that, "knowing that the interim construction was coming due

in approximately two months," they contacted Rheinheimer in both June and July 2007 to

check on the status of the permanent financing. At these times, the Schellenbergs

alleged, Rheinheimer informed them that it was "'too early'" for him to advise them on the

terms of the permanent financing. The Schellenbergs alleged that in August 2007,

because "the interim construction loan was due but construction was not quite complete

on the Schellenberg residence," they "visited with Rheinheimer and FSB to discuss

extending the note with FSB and to discuss the terms of the permanent loan that would

be used to refinance the interim construction loan." When they asked about the

permanent financing, "Rheinheimer told [them], 'They aren't making those anymore,'" and

that they "would have to find permanent financing elsewhere because he could not make

those kinds of loans anymore." The Schellenbergs alleged, and FSB does not dispute,

that the expiration of the original interim loan "coincided with one of the worst mortgage

markets in recent history."

Rheinheimer searched for new permanent financing throughout the fall of 2007 but

near the end of September, informed the Schellenbergs that he was unable to find it and 3 suggested that the Schellenbergs list their property for sale. FSB agreed to extend its

interim loan to the Schellenbergs later in the fall. On November 9, 2007, the

Schellenbergs and FSB signed an extension of the interim construction agreement, which

extended the maturity date of the interim loan to February 6, 2008 and included a release

of any and all claims against FSB, known and unknown, that had accrued up to that date.

When they signed the extension agreement, the Schellenbergs reserved their right to

assert claims against Rheinheimer and MAC. When the Schellenbergs failed to meet

their obligations under the extended terms, FSB foreclosed on the loan. In March 2009,

the Schellenbergs filed for bankruptcy.

The Schellenbergs sued FSB, alleging claims for promissory estoppel, negligent

misrepresentation, and fraudulent inducement.2 Specifically, the Schellenbergs alleged

that FSB promised and represented to them at the time of the August 10, 2006 loan that:

a permanent loan commitment had been "sourced and locked"; FSB was "satisfied with

the Schellenbergs' permanent loan" commitment; and FSB "does not make interim

construction loans unless permanent financing is in place." The Schellenbergs also

alleged that FSB showed them a "HUD-1 settlement statement showing fees paid for its

promised permanent financing loan." The Schellenbergs claimed that these

representations were either negligent misstatements of fact or knowingly false and that

they reasonably relied on these statements to their detriment. The Schellenbergs

claimed that they suffered damages in the form of "loss of the actual land, loss of actual

2The Schellenbergs also alleged claims of common-law fraud and fraud by non-disclosure against MAC, Rheinheimer, and others not parties to this appeal; these claims were non-suited after the trial court granted summary judgment to FSB. 4 value of the land, cost of the improvements to the land, cost of third party providers that

provided services for the development of the land, loan fees, damage to credit reputation,

and loss of future earnings derived from the stables that were constructed on the property

as part of the Schellenbergs' livelihood."

FSB filed a traditional motion for summary judgment, arguing that the

Schellenbergs' claims were barred as a matter of law because: (1) they signed an

agreement releasing FSB from all claims; (2) their claims sounded in contract and not

tort; (3) FSB could conclusively disprove the promise, reasonable reliance, and falsity

elements of fraud; and (4) the statute of frauds barred the promissory estoppel claim.

FSB attached as evidence: excerpts from the Schellenbergs' depositions, which

included as exhibits the various documents involved in effectuating the interim

construction loan; the affidavit of FSB's loan officer; a series of emails between

Rheinheimer and the Schellenbergs; and the HUD statement. The Schellenbergs

responded, in relevant part, that because they were unaware of the facts giving rise to

Free access — add to your briefcase to read the full text and ask questions with AI

John Schellenberg and Lisa Schellenberg v. First State Bank Central Texas, (Tex. Ct. App. 2014).

John Schellenberg and Lisa Schellenberg v. First State Bank Central Texas (John Schellenberg and Lisa Schellenberg v. First State Bank Central Texas) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Travelers Insurance Co. v. Joachim
315 S.W.3d 860 (Texas Supreme Court, 2010)
Alba v. Nueces County Sheriff's Department
89 S.W.3d 132 (Court of Appeals of Texas, 2002)
FM Properties Operating Co. v. City of Austin
22 S.W.3d 868 (Texas Supreme Court, 2000)
Seureau v. ExxonMobil Corp.
274 S.W.3d 206 (Court of Appeals of Texas, 2008)
Alejandro v. Bell
84 S.W.3d 383 (Court of Appeals of Texas, 2002)
Woods v. William M. Mercer, Inc.
769 S.W.2d 515 (Texas Supreme Court, 1988)
Moreno v. Sterling Drug, Inc.
787 S.W.2d 348 (Texas Supreme Court, 1990)
ABC, INC. v. Shanks
1 S.W.3d 230 (Court of Appeals of Texas, 1999)
Provident Life & Accident Insurance Co. v. Knott
128 S.W.3d 211 (Texas Supreme Court, 2003)
American Tobacco Co., Inc. v. Grinnell
951 S.W.2d 420 (Texas Supreme Court, 1997)
Murphy v. Campbell
964 S.W.2d 265 (Texas Supreme Court, 1998)
Childs v. Haussecker
974 S.W.2d 31 (Texas Supreme Court, 1998)
KPMG Peat Marwick v. Harrison County Housing Finance Corp.
988 S.W.2d 746 (Texas Supreme Court, 1999)
Etan Industries, Inc. v. Lehmann
359 S.W.3d 620 (Texas Supreme Court, 2011)