John Lahoud v. Anthony & Sylvan Corp., Etc.

CourtNew Jersey Superior Court Appellate Division
DecidedFebruary 6, 2025
DocketA-3049-23
StatusPublished

This text of John Lahoud v. Anthony & Sylvan Corp., Etc. (John Lahoud v. Anthony & Sylvan Corp., Etc.) is published on Counsel Stack Legal Research, covering New Jersey Superior Court Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
John Lahoud v. Anthony & Sylvan Corp., Etc., (N.J. Ct. App. 2025).

Opinion

NOT FOR PUBLICATION WITHOUT THE APPROVAL OF THE APPELLATE DIVISION

SUPERIOR COURT OF NEW JERSEY APPELLATE DIVISION DOCKET NO. A-3049-23

JOHN LAHOUD,

Plaintiff-Appellant, APPROVED FOR PUBLICATION

February 6, 2025 v. APPELLATE DIVISION ANTHONY & SYLVAN CORP., t/a ANTHONY SYLVAN POOLS,

Defendant-Respondent. ______________________________

Argued January 22, 2025 – Decided February 6, 2025

Before Judges Gilson, Firko and Augostini.

On appeal from the Superior Court of New Jersey, Law Division, Bergen County, Docket No. L-0967-24.

Joseph M. Cerra argued the cause for appellant (Lynch Law Firm, PC, attorneys; Joseph M. Cerra, on the briefs).

Daniel J. DeFiglio argued the cause for respondent (Archer & Greiner, PC, attorneys; William L. Ryan and Daniel J. DeFiglio, on the brief).

The opinion of the court was delivered by

FIRKO, J.A.D. This appeal presents a novel issue: is an alternative dispute resolution

(ADR) provision enforceable if the party who drafted the contract reserves the

right to file certain claims in court while the other party does not. Plaintiff

John Lahoud appeals from the Law Division's two May 30, 2024, orders

granting defendant Anthony & Sylvan Corporation's (A&S) motion to dismiss

the complaint and compel arbitration and denying his cross-motion to declare

the ADR provision contained in the contract unenforceable and violative of

public policy. Because the ADR provision contains a reservation of rights

provision here that is not enforceable, we affirm in part, reverse in part, and

remand.

I.

The pertinent facts are gleaned from the motion record and are relatively

straightforward. On January 28, 2023, plaintiff entered into a written contract

with A&S to build an in-ground swimming pool at his beachfront home in

Mantoloking. A&S prepared the contract using its own form. The contract

included an ADR clause:

YOU AND WE AGREE THAT ANY CONTROVERSY, DISPUTE OR CLAIM, INCLUDING BUT NOT LIMITED TO ANY CLAIM FOR CONSUMER FRAUD OR ANY OTHER STATUTORY CLAIM, (COLLECTIVELY "CLAIM") ARISING OUT OF OR RELATING IN ANY WAY TO THIS AGREEMENT OR ITS BREACH THAT CANNOT BE SETTLED

A-3049-23 2 THROUGH DIRECT DISCUSSIONS SHOULD BE SUBMITTED BY THE CLAIMANT TO NON- BINDING MEDIATION, ADMINISTERED BY A MEDIATOR MUTUALLY SELECTED AND AGREED TO BY THE PARTIES, OR IF THE PARTIES CANNOT AGREE ON A MEDIATOR, BY A MEDIATOR WITH THE AMERICAN ARBITRATION ASSOCIATION ("AAA") PURSUANT TO ITS COMMERCIAL MEDIATION RULES. MEDIATION MAY PROCEED REMOTELY AT A&S'S OR CUSTOMER'S ELECTION. IF THE PARTIES ARE UNABLE TO RESOLVE THE CLAIM THROUGH MEDIATION, THE CLAIM SHALL BE SUBMITTED BY CLAIMANT FOR AND RESOLVED BY BINDING ARBITRATION PURSUANT TO THE AAA COMMERCIAL ARBITRATION RULES AND ADMINISTERED BY AN ARBITRATOR MUTUALLY SELECTED AND AGREED TO BY THE PARTIES, OR IF THE PARTIES CANNOT AGREE THEN ONE ASSIGNED BY THE AAA. THE JUDGMENT ON THE AWARD RENDERED BY THE ARBITRATOR MAY BE ENTERED IN ANY COURT HAVING JURISDICTION. YOU AND WE ARE CHOOSING MEDIATION AND ARBITRATION INSTEAD OF LITIGATION TO RESOLVE OUR CLAIMS AND VOLUNTARILY AND KNOWINGLY WAIVE A RIGHT TO A JURY TRIAL. UNLESS OTHERWISE DETERMINED, EACH OF US WILL BEAR OUR OWN COSTS OF THE MEDIATION AND ARBITRATION PURSUANT TO THE THEN CURRENT FEE SCHEDULE LOCATED AT WWW.ADR.ORG. YOU AGREE THAT WE CAN IN OUR DISCRETION JOIN CONTRACTORS, INSURANCE COMPANIES AND ANY OTHER PERSONS OR ENTITIES INTO THE MEDIATION AND/OR ARBITRATION AT ANY TIME, AND CONSENT TO JOINDER AND PARTICIPATION OF SUCH PARTIES. NO ACTIONS BY US IN RESPONSE TO A LEGAL

A-3049-23 3 CLAIM SHALL BE DEEMED A WAIVER OF OUR RIGHT TO MEDIATION OR ARBITRATION. NOTWITHSTANDING THE FOREGOING, WE RESERVE THE RIGHT AND MAY AT OUR DISCRETION EXERCISE THE RIGHT TO COMMENCE LEGAL ACTION IN ANY COURT OF COMPETENT JURISDICTION TO COLLECT MONIES YOU OWE UNDER THIS AGREEMENT, IN WHICH YOU AGREE TO WAIVE THE RIGHT TO MEDIATION OR ARBITRATION. 1

YOU AND WE, IN PROCEEDING TO MEDIATION AND/OR ARBITRATION, AGREE THAT ALL FACTS ARISING FROM OR RELATED TO THE DISPUTE, INCLUDING RELATED DOCUMENTS USED IN THE MEDIATION AND/OR ARBITRATION, ARE CONFIDENTIAL, AND IF APPLICABLE, ANY ARBITRATION DECISION ISSUED IS ALSO CONFIDENTIAL. SAID DECISION IS FINAL AND BINDING ON THE PARTIES. THE PARTIES FURTHER AGREE THAT THIS DISPUTE RESOLUTION AND ARBITRATION PROVISION DOES NOT, AND IS NOT INTENDED TO, LIMIT, WAIVE AND/OR RELEASE ANY PARTY'S CLAIMS, DAMAGES, AND/OR DEFENSES EACH PARTY MAY HAVE AGAINST THE OTHER, OTHER THAN EACH PARTY WAIVING AND RELEASING THE RIGHT TO PROCEED WITH LITIGATION IN A COURT OF COMPETENT JURISDICTION TO RESOLVE THEIR DISPUTES.

[(Emphasis added).]

1 We refer to this as the "reservation of rights provision" in our opinion.

A-3049-23 4 The contract was for a total of $114,788.00 and did not specify the

project start or end date. On January 28, 2023, the contract was electronically

signed by plaintiff and an A&S employee.

Sometime in August 2023, plaintiff requested A&S to begin the pool

installation after a series of delays. On September 29, 2023, A&S began

excavation on the pool along with a subcontractor, who worked for two hours

and did not return. Plaintiff had a discussion with A&S's general manager,

who acknowledged that the subcontractor was inexperienced and unfamiliar

with excavation in a beach town. A&S's general manager advised plaintiff he

would find a new excavator within a few days. On October 16, 2023, after the

excavation work had not restarted, plaintiff declared A&S in "material breach"

of the contract and informed A&S that he was terminating the contract.

A&S sought $15,617.00 from plaintiff for three days' worth of

excavation work and $4,493.00 for permits it had obtained. Therefore, A&S

agreed to refund plaintiff $27,890.00 of his approximate $50,000.00 deposit. 2

2 The contract stated the following under "PAYMENT":

Payment Terms: You agree to pay us through our iSwim electronic payment system the following amounts at the times noted below:

A. Due at signing of this Agreement: Line 2 B. Due at excavation: 40% of Line 3

A-3049-23 5 According to plaintiff, A&S's representative falsely advised him that

helical pilings needed to be installed, which plaintiff claims he later learned

were unnecessary. Plaintiff alleges the helical pilings were installed and cost

him $14,000.00.

In February 2024, plaintiff filed a three-count complaint in the Law

Division against A&S asserting claims for breach of contract, a violation of the

New Jersey Consumer Fraud Act (CFA), N.J.S.A. 56:8-1 to -20, and for

declaratory relief declaring that the "non-mutual and so-called arbitration

provision" violates the public policy of this State and is not enforceable.

Plaintiff also alleged A&S breached the contract by failing to provide

bargained-for services and by "failing to commence, continue, or complete the

project in a timely fashion."

Under the CFA, plaintiff asserted A&S's failure to specify a start and

completion date constituted an ascertainable loss. Plaintiff alleged the ADR

____________________

C. Due at installation of concrete shell: 55% of Line 3 D. Due prior to application of interior finish: the balance of Line 3 less $250.00 E. Due upon securing Certificate of Occupancy: Final Payment of $250.00

1. TOTAL THIS AGREEMENT: $114,788.00 2. LESS DEPOSIT: - $8,791.00 3. BALANCE: $105,997.00

A-3049-23 6 provision is "unconscionable." Plaintiff sought compensatory and

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Michael E. Hirsch v. Amper Financial Services, LLC (070751)
71 A.3d 849 (Supreme Court of New Jersey, 2013)
Impink Ex Rel. Baldi v. Reynes
935 A.2d 808 (New Jersey Superior Court App Division, 2007)
Sitogum Holdings, Inc. v. Ropes
800 A.2d 915 (New Jersey Superior Court App Division, 2002)
Martindale v. Sandvik, Inc.
800 A.2d 872 (Supreme Court of New Jersey, 2002)
Kampf v. Franklin Life Insurance
161 A.2d 717 (Supreme Court of New Jersey, 1960)
Wildwood Trust Co. v. DeCorrevant
90 A.2d 110 (New Jersey Superior Court App Division, 1952)
Jacob v. Norris, McLaughlin & Marcus
607 A.2d 142 (Supreme Court of New Jersey, 1992)
Garfinkel v. Morristown Obstetrics & Gynecology Associates, P.A.
773 A.2d 665 (Supreme Court of New Jersey, 2001)
Rudbart v. North Jersey District Water Supply Commission
605 A.2d 681 (Supreme Court of New Jersey, 1992)
Levison v. Weintraub
521 A.2d 909 (New Jersey Superior Court App Division, 1987)
Karl's Sales & Serv., Inc. v. Gimbel Bros., Inc.
592 A.2d 647 (New Jersey Superior Court App Division, 1991)
Delta Funding Corp. v. Harris
912 A.2d 104 (Supreme Court of New Jersey, 2006)
Muhammad v. County Bank of Rehoboth Beach, Delaware
912 A.2d 88 (Supreme Court of New Jersey, 2006)
James v. Federal Insurance Co.
73 A.2d 720 (Supreme Court of New Jersey, 1950)
Morton v. 4 Orchard Land Trust
849 A.2d 164 (Supreme Court of New Jersey, 2004)
Delta Funding Corp. v. Harris
396 F. Supp. 2d 512 (D. New Jersey, 2004)
Patricia Atalese v. U.S. Legal Services Group, L.P. (072314)
99 A.3d 306 (Supreme Court of New Jersey, 2014)
Annemarie Morgan v. Sanford Brown Institute(075074)
137 A.3d 1168 (Supreme Court of New Jersey, 2016)
Sergio Rodriguez v. Raymours Furniture(074603)
138 A.3d 528 (Supreme Court of New Jersey, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
John Lahoud v. Anthony & Sylvan Corp., Etc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/john-lahoud-v-anthony-sylvan-corp-etc-njsuperctappdiv-2025.