John H. Marchese v. Moore-Mccormack Lines, Inc., and Third-Party v. Court Carpentry & Marine Contractor Co., Inc., Third-Party

525 F.2d 831, 1975 U.S. App. LEXIS 12986
CourtCourt of Appeals for the Second Circuit
DecidedAugust 25, 1975
Docket821, Docket 75-7022
StatusPublished
Cited by5 cases

This text of 525 F.2d 831 (John H. Marchese v. Moore-Mccormack Lines, Inc., and Third-Party v. Court Carpentry & Marine Contractor Co., Inc., Third-Party) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
John H. Marchese v. Moore-Mccormack Lines, Inc., and Third-Party v. Court Carpentry & Marine Contractor Co., Inc., Third-Party, 525 F.2d 831, 1975 U.S. App. LEXIS 12986 (2d Cir. 1975).

Opinion

TIMBERS, Circuit Judge:

On this appeal from a judgment entered November 7, 1974 in the Eastern District of New York, Anthony J. Travia, District Judge, confirming the report of a magistrate and dismissing the complaint of a lasher and marine carpenter who sought damages for injuries sustained while unlashing pipes stowed on the main deck of a vessel, the issues are *833 whether the findings below that the vessel was not unseaworthy and that plaintiff’s negligence was the sole cause of his injuries were clearly erroneous. We hold that they were. Accordingly, we reverse and remand for a new trial.

I.

The following facts, as proven at a non-jury trial before a magistrate on the issue of liability *, are substantially undisputed, except as otherwise indicated.

On August 17, 1970, John H. Márchese was employed as a lasher and marine carpenter by Court Carpentry & Marine Contractor Co., Inc. (Court Carpentry). He was injured that day while working aboard the S.S. Mormacglen which was owned and operated by Moore-McCormack Lines, Inc. (shipowner).

The vessel, a large ocean going steamer, lay moored at Pier 23rd Street Terminal in Brooklyn. She had come from Brazil. She had on deck as cargo four long steel pipes which had been loaded and lashed to the deck in Brazil. They were each 20 feet long and 4 feet in diameter. Three of the pipes were stowed on wooden sleepers. The fourth was on top of two of the other pipes, those nearest No. 5 hatch. The length of all of the pipes ran fore and aft between the hatch coaming and the vessel’s solid steel bulwark or rail. The deck sloped toward the bulwark. There was about 18 inches of space between the pipes and the hatch coaming and about the same space between the pipes and the bulwark.

The pipes were secured with lashing wires in three places. One lashing was at each end of the pipes and one was in the center. The lashings went over the pipes from the bulwark to the coaming. Each lashing was secured to the deck with a turnbuckle attached to a padeye. The end of the lashing which passed through the eye of the turnbuckle was clamped with two clips. Each clip was held in place by two bolts and nuts.

At about 9 A. M. on August 17, Márchese was directed by a snapper (assistant foreman), also employed by Court Carpentry, to unlash the pipe cargo at No. 5 hatch on the inshore side. He was told to work quickly because a longshore gang was standing by waiting to unload the cargo. He started at the forward end of the pipes near the bulwark. Using a ratchet wrench, he released two of the three lashing wires by removing the nuts from the clips which held together the ends of the lashing wires. 1 2 He was working on the third lashing wire at the after end of the pipes, having loosened the first nut from the clip, when the pipes shifted and pinned him against the bulwark. Immediately before the pipes shifted, he had been working in the 18 inch space between the pipes and the bulwark, with his back toward the bulwark. He sustained injuries to his knees and back for which he sought damages in the district court.

It is undisputed that the pipes as stowed had neither chocks nor crib to hold them in position. They were held in position only by the lashing wires. It *834 also is undisputed that before releasing the lashing wires Márchese did not look to see if the pipes were chocked or otherwise held in position.

The magistrate found that the vessel was not unseaworthy and that the sole cause of Marchese’s injuries was his own negligence. The district court confirmed the magistrate’s report. From the judgment dismissing his complaint, Márchese appeals.

II.

We turn first to the finding that the vessel was not unseaworthy.

It is common ground that a shipowner is required to furnish a safe place to work for seamen, longshoremen and harbor workers. This duty is absolute and non-delegable. Mahnich v. Southern Steamship Co., 321 U.S. 96, 102 (1944). A shipowner’s liability for unseaworthiness essentially is a “species of liability without fault .... Derived from and shaped to meet the hazards which performing the service imposes, the liability is neither limited by conceptions of negligence nor contractual in character.” Seas Shipping Co. v. Sieracki, 328 U.S. 85, 94 (1946). Seamen and others who work on a vessel must “accept without critical examination and without protest, working conditions and appliances as commanded by [their] superior officers”, and they do not assume the risk of working under such conditions. Mahnich v. Southern Steamship Co., supra, 321 U.S. at 103. Nor is a shipowner who provides an unseaworthy vessel relieved of liability because the unseaworthiness is attributable to the negligence of a fellow servant of the injured person rather than to the shipowner’s negligence. Id. at 101-02. It is true that an isolated negligent act of a fellow servant which causes an injury may not render a vessel unseaworthy. Usner v. Luckenbach Overseas Corp., 400 U.S. 494, 500 (1971). But where such a negligent act brings into play an unseaworthy condition, a shipowner will be held liable. Crumady v. The Joachim Hendrik Fisser, 358 U.S. 423 (1959). And any contributory negligence on the part of an injured worker which brings into play an unseaworthy condition does not bar recovery; rather, the degree of contributory negligence is ground only for mitigation of damages. Socony-Vacuum Oil Co. v. Smith, 305 U.S. 424, 429 (1939). See Rivera v. Farrell Lines, Inc., 474 F.2d 255, 257 n. 1 (2 Cir.), cert. denied, 414 U.S. 822 (1973). 3

The unseaworthiness of the vessel in the instant case was the stowage of the pipes without chocks or crib. Such stowage was dangerous to anyone releasing the lashings. The place for the lashers to work was not reasonably safe. The danger from pipes which were unchocked and otherwise unsupported except for the lashing was that they were sure to roll once they were unlashed. Especially since they were stowed on a sloping deck in pyramid formation with the top pipe exerting pressure on the lower ones, movement of the unchocked pipes was inevitable once unlashed. In short, the improperly stowed pipes constituted unseaworthiness. See Scott v. S.S. Ciudad Ibaque, 285 F.Supp. 613, 616 (E.D.La.1968), aff’d, 426 F.2d 1105 (5 Cir. 1970).

In Palazzolo v. Pan-Atlantic S.S. Corp.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
525 F.2d 831, 1975 U.S. App. LEXIS 12986, Counsel Stack Legal Research, https://law.counselstack.com/opinion/john-h-marchese-v-moore-mccormack-lines-inc-and-third-party-v-court-ca2-1975.