John F. Trainor Co. v. G. Amsinck & Co.

199 A.D. 693, 192 N.Y.S. 469, 1922 N.Y. App. Div. LEXIS 8075
CourtAppellate Division of the Supreme Court of the State of New York
DecidedFebruary 10, 1922
StatusPublished
Cited by5 cases

This text of 199 A.D. 693 (John F. Trainor Co. v. G. Amsinck & Co.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
John F. Trainor Co. v. G. Amsinck & Co., 199 A.D. 693, 192 N.Y.S. 469, 1922 N.Y. App. Div. LEXIS 8075 (N.Y. Ct. App. 1922).

Opinions

Clarke, P. J.:

The action was brought to recover damages for breach of a contract made by a written proposition of the plaintiff to sell and deliver cotton yarn, accepted in writing by the defendant, [694]*694The quantity ordered was 29,000 pounds of 8 ¡1 soft twist, that is, “a thread that measures eight times 840 yards to a pound.” The contract provided: “ This order is taken subject to discontinuance or cancellation only in case of fires, strikes, lockouts or any unforeseen casualty at your mill or that of our mill where the yarns are to be made, and in that event deliveries to be made proportionate to the running of the respective mills, you to take and we to deliver all goods made at that time or in process of manufacture. If shipments are delayed for any reason, it is understood that the order remains in force until cancelled. All understandings and verbal agreements embodied herein.” Also “ Price 65^ lb. Terms 3% 10 days from B /L f.o.b. mill. Frt. prepaid. • Deliveries — Beginning September, sooner if possible. This delivery is subject to delays over which we have no control.”

On the trial the complaint was amended. The original complaint alleged as follows:

Fifth. That plaintiff and defendant thereafter agreed that deliveries were to be made on the aforesaid contract in December, 1918, or early in January, 1919.

“ Sixth. That thereafter and on or about December 2nd, 1918, the defendant gave notice in writing to plaintiff that it would not accept the yarn when delivered.”

The amendment to paragraph 5th on the trial was that on or about August 27th plaintiff and defendant agreed that deliveries were to be made on the aforesaid contract within a reasonable time.” The proof showed that on the 30th of November, 1918, the defendant wrote: Referring to the contract we placed with you on May 29th, * * * we have to advise you that we regret that you have made no deliveries as yet on yarns # 32 and #81. Our order stated delivery August-September, or better. We find that owing to late delivery we are forced to cancel this contract. Our customers will not take the goods on these late dates, and there is no option before us other than to send you a formal cancellation for these two items as yet undelivered to us, and accordingly this may be regarded as a formal cancellation of the same.”

The appellant claims that, when the contract was modified by changing the time for delivery from the time fixed in the contract to a reasonable time, the absolute cancellation without [695]*695previous notice of a date for delivery, considered by it to be a reasonable time, was a breach of the contract on defendant’s part and entitled appellant to a direction of a verdict in its favor for which it moved, and being denied, it excepted.

The learned trial court charged the jury as follows: “ The issue in this case, as we have finally worked it out, is exceedingly simple and is a single one: What did the parties intend by a reasonable time when, on August 27th, they changed the date of delivery as it had theretofore been, to a delivery within a reasonable time. What was such reasonable time? If the reasonable time intended by them, and as it actually was, expired on or before November 30th, then the defendant had the right to, as he calls it, cancel the contract. If on .the other hand the reasonable time extended beyond November 30th, then they had no right to cancel the contract on November 30th for a failure of delivery, because you s.ee that under those circumstances the plaintiff would have had further time to make the delivery, and the defendant, therefore, would have breached the contract by this letter of cancellation.”

So that the question is clearly presented, the court leaving reasonable time ” alone to the jury and refusing to consider the necessity for notice of limitation before cancellation.

In Taylor v. Ooelet (142 App. Div. 467) defendant entered into a contract for the construction of a building which provided for its completion ready for occupancy on or before July 1,1907. The building was not completed at that time but the plaintiffs continued to make regular monthly payments until February 17, 1908. On the twelfth of March defendant gave the construction company three days’ notice, pursuant to the contract, to supply a sufficiency of workmen and materials to prosecute the work with promptness and diligence, and that, upon its neglect or refusal to do so, he would take possession for the purpose of completing the work; and, pursuant to that notice, the defendant did take possession. Mr. Justice Miller said: It was testified on the trial, and conceded by the defendant, that the reasonable time to erect the building expired on July 1, 1907. The court ruled that, from the nature of the contract, the defendant was notified from the beginning that the building had to be erected within a reasonable time, and that no notice was necessary to put him in default; but that, [696]*696as. the reasonable time expired July 1, 1907, the continued monthly payments thereafter operated to waive the default, and to extend the time of performance indefinitely, wherefore, the defendant could not be again put in default without notice, requiring performance within a" reasonable time specified. * * * We are of the opinion that, on definite time of performance having been specified in the contract, the plaintiffs could not rescind without giving the defendant a reasonable time after notice to perform. Of course, where the time of performance is not specified -in the contract, the law presumes that the parties intended performance within a reasonable time; but 'it does not follow that, in such case, one party may suddenly and without notice terminate the contract, while the other is in good faith endeavoring to perform it. * * * The law is settled in this State by a long line of authorities that, where the time of performance is indefinite, neither party can put the other in default without notice, giving a reasonable time specified to complete performance. [Citing cases.] To be sure the question has usually been raised where the definite or specified time in the contract has been extended indefinitely, i. e., for a reasonable time. But we fail to perceive any distinction between a case where the parties originally contracted for performance within a reasonable time, not specified, and one where the original contract for performance within a specified time has been modified, either by contract or by the acts of the parties amounting to the same thing, so as to .substitute a reasonable time for the specified time, or to extend the specified time for a reasonable time.”

This case was affirmed (208 N. Y. 253), the Court of Appeals saying: This court has held that where an executory contract fixes the time within which it is to be performed and performance within that time is waived by the parties to the agreement, neither party can thereafter rescind the contract on account of such delay without notice to the other requiring performance within a reasonable time, to be specified in the notice, or the contract will be abrogated. By the waiver time as an essential element of the contract has been removed therefrom, but it can be restored by a reasonable notice demanding performance and stating that the contract will be rescinded if the notice is [697]*697not complied with. (Lawson v. Hogan, 93 N. Y. 39; Schmidt v. Reed, 132 N. Y. 108.)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Scharf v. Tolley
2025 NY Slip Op 31143(U) (New York Supreme Court, New York County, 2025)
Forsstrom v. Utility Steel Co.
131 Misc. 471 (New York City Court, 1928)
John F. Trainor Co. v. G. Amsinck & Co.
205 A.D. 840 (Appellate Division of the Supreme Court of New York, 1923)
Temerson v. Esskay Dress Corp.
120 Misc. 55 (Appellate Terms of the Supreme Court of New York, 1922)
Neverfail Lighter Co. v. Blum
201 A.D. 153 (Appellate Division of the Supreme Court of New York, 1922)

Cite This Page — Counsel Stack

Bluebook (online)
199 A.D. 693, 192 N.Y.S. 469, 1922 N.Y. App. Div. LEXIS 8075, Counsel Stack Legal Research, https://law.counselstack.com/opinion/john-f-trainor-co-v-g-amsinck-co-nyappdiv-1922.