John C. Grimberg Co., Inc.

Armed Services Board of Contract Appeals·Decided October 25, 2018·No. ASBCA No. 58791, 59167, 59168, 59169, 59170, 59171, 59717·Published

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of -- ) ) John C. Grimberg Co., Inc. ) ASBCA Nos. 58791, 59167, 59168 ) 59169, 59170,59171 ) 59717 ) Under Contract No. W912DR-09-C-0038 )

APPEARANCES FOR THE APPELLANT: Edward J. Parrott, Esq. Stephanie M. Rochel, Esq. Watt, Tieder, Hoffar & Fitzgerald, LLP McLean, VA

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Scott C. Seufert, Esq. David B. Jerger, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Baltimore

OPINION BY ADMINISTRATIVE JUDGE PEACOCK

These appeals involve claims for alleged differing site conditions, delays, acceleration and multiple changes arising out of construction of a Bio lab facility at Fort Detrick, Maryland. Entitlement only is before us for decision. For the reasons detailed below, we sustain ASBCA No. 58791, sustain in part ASBCA No. 59717 and deny ASBCA Nos. 59167, 59168, 59169 and 59170. At trial, the parties agreed to dismiss ASBCA No. 59171 with prejudice (tr. 4/6-7).

FINDINGS OF FACT

A. CAISSONS DIFFERING SITE CONDITION-ASBCA No. 58791

1. The referenced contract was awarded to John C. Grimberg Co., Inc. (appellant. JCG or Grimberg) by the Baltimore, Maryland, District U.S. Army Corps of Engineers (Corps or government) on May 29, 2009, for construction of the Navy Medical Biological Defense Research Laboratory (Biolab or Project) (R4, tab 2 at I). The amount of the contract was $21,087,000.00 (id. at 2). The period of performance was 720 days from receiving notice to proceed (id. at 1). The contract was a design-build contract (id; GPF 62 1). As is typical of a design-build contract, no unit prices for rock excavation were set forth because the contractor's foundation solution is not established at the time of award (tr. 2/43, 4/40; GPF 63). The contract incorporated Federal Acquisition Regulation (FAR) 52.236-2, DIFFERING SITE CONDITIONS (APR 1984J(the DSC clause); FAR 52.243-4, CHANGES (JUN 2007); and FAR 52.249-10, DEFAULT (FIXED-PRICE CONSTRUCTION) (APR 1984) (APFs 5-9; GPF 13).

t. Fort Detrick and its Karst Geology Generally

2. The Project is located at Fort Detrick in Frederick County, Western Maryland (tr. 5/28, 31). Geologically, the rock beneath Fort Detrick is part of the Frederick Formation (R4, tab 5 at 2-3). The Frederick Formation is known for its karst geology (tr. 5/26; GPF 1).

3. Karst geology is a geological formation shaped by the dissolution of a layer or layers of soluble bedrock, usually carbonate rock such as limestone, dolomite, or gypsum, but has also been documented for weathering-resistant rocks, such as quartzite, given the right conditions (R4, tab l at 4 n.3). Karst is a recognized geohazard, "[k]nown for its variability and its degree of inconsistency, both vertically and horizontally over extremely short distances" (tr. 5/27). Karst also has significant top of rock variation (tr. 8/127, 167). Karst is unique in that the existence of a solid appearing outcrop right at the location of a footing or pier does not guarantee that good rock will appear below the outcrop (tr. 7/167). For this reason offerors should anticipate that conditions at one location can differ from conditions at another location (tr. 7/169). Karst conditions can vary over short distances (tr. 8/139). In karst, "you can have a mass of soil in the solution feature, or a karst feature, and immediately adjacent to it is good hard rock (tr. 3/89, see also tr~ 8/139, 141). Karst is "consistently inconsistent" (tr. 5/32-33; GPF 2).

4. Voids are present throughout the Frederick Formation (tr. 8/130). They are present in areas without strong evidence of ·'strike and dip'' (tr. 8/159-60). Strike and dip are considerations in karst limestone but are not the defining features for understanding

1 The Board issued a briefing order in these appeals, inter alia, requirihg that each party, in its initial post-hearing brief, propose findings of fact supported by detailed citations to pertinent portions of the record. The briefing order.further required that each party, in its reply brief, respond to the opposing party's proposed findings of fact with specificity interposing all objections it had to those proposed findings. Both parties have filed excellent briefs in compliance with that\>rder. Accordingly, the Board has extensively adopted many of each party's findings to the extent that there was no objection. Appellant's and the government's proposed findings are designated APF and GPF, respectively followed by the proposed finding number. In adopting party-proposed findings, the Board generally incorporates the citations to the record set forth in the proposed findings (without repetition in this decision) as support for the Board's own findings.

2 conditions at the Project site (tr. 8/123, 155-56, 159-60). Other factors and conditions that can impact incompetent rock, 2 such as top of rock variation, must be accounted for (tr. 8/128, 139, 141; GPF 3).

5. Grimberg has pe1formed several contracts at Fmt Detrick, which is approximately 40 miles from Grimberg's home office (tr. 1/53). The other Grimberg projects at Fort Detrick involving deep foundations were design-bid-build projects and had unit prices for rock excavation. On at least one of these prior contracts, Grimberg contracted with the same drilling subcontractor, Seaboard Foundations, as it did on this project. One prior contract involved construction of the Steam Sterilization Plant (SSP), located approximately 400 yards from the Project (tr. 1/57). Because the earlier contracts were design-bid-build, the government, not Grimberg, performed all design functions. (Tr. 1/57-58, 62, 149; GPF 5)

6. Grimberg had not bid a design-build project at Fort Detrick with deep foundations before. In addition, this was Grimberg's first project involving deep foundations that did not contain unit prices. (Tr. 1/147; GPF 6)

ii. The Government's Constntction Cost Estimate Foundation Assumptions

7. Mr. Brian Glock is a senior geotechnical engineer with the Baltimore District, Corps of Engineers. He has lived and worked in the Baltimore area almost his entire life. He has extensive geotechnical knowledge of the Baltimore area and experience covering the design of numerous foundation types, including drilled piers, and in designs involving karst geology. (Tr. 4/32-37; GPF 7)

8. On October 14, 2008, Mr. Glock prepared assumptions for the government's construction cost estimate for the Project's deep foundation work (R4, tab 156; tr. 4/42-43; GPF 8).

9. Mr. Glock' s estimate assumed a contractor would install drilled piers with an average diameter of 4 feet, and an average total length of 35 feet (tr. 4/156-57; R4, tab 156). Each pier would end with a rock socket, the portion of the pier that carries the Project building's structural load. The rock socket must be set in competent rock. (See, e.g., R4, tab 5 at 9, tab 9 at 5) The piers would extend through an estimated 20 feet of soil and 15 feet of rock (R4, tab 156 at 2). Mr. Glock did not differentiate between estimated quantities of competent and incompetent rock to be excavated (id.). Mr. Glock indicated in his trial testimony, however, that of the 15 feet of rock excavation, 10 to 11 feet he assumed would be allocated for incompetent rock and 4 to 5 feet was allocated for competent rock, in which the rock socket would be set (tr. 4/181-82). The 15-foot figure represented his estimated average across all drilled piers (tr. 4/158-59, 8/136; GPF 9).

2 As used by both parties, "incompetent" rock refers to poor quality rock unsuitable for supporting the drilled pier foundation designed for this project.

3 10. Mr. Glock included excavation costs for approximately 10 to 11 feet of incompetent rock in his estimate (GPF 10).

lll. The Contract Geotechnical Report

Free access — add to your briefcase to read the full text and ask questions with AI

John C. Grimberg Co., Inc., (asbca 2018).

John C. Grimberg Co., Inc. (John C. Grimberg Co., Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related