John Bailey Contr. v. St., Dept. of Tr. & Dev.
This text of 439 So. 2d 1055 (John Bailey Contr. v. St., Dept. of Tr. & Dev.) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
JOHN BAILEY CONTRACTOR, INC.
v.
STATE of Louisiana, Through the DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT.
Supreme Court of Louisiana.
*1056 Emmett C. Sole, Stockwell, Sievert, Viccellio, Clements & Shaddock, Lake Charles, for applicant.
James A. Smith, Smith & Wise, Lake Charles, James B. Frederick, Jr., Marshall W. Wroten, Sharon F. Lyles, L. Gordon King, Asst. Gen. Counsels, Baton Rouge, for respondent.
BLANCHE, Justice.
Plaintiff sued to recover from the Department of Transportation and Development (DOTD) for the construction of a temporary detour road in connection with the construction of approaches to a new bridge on Highway 27 at Bayou Choupique in Calcasieu Parish.[1] Following trial on the merits, the judge rendered judgment in favor of Bailey for the sum of $30,000 against F. Miller & Sons, Inc., and DOTD, in solido. In his oral reasons for judgment, the trial judge found that the plaintiff could not recover under the contract, but that he was entitled to relief under the theory of equitable estoppel. On appeal, the Third Circuit reversed, holding that equitable estoppel did not apply. The issue of recovery under *1057 the contract was not raised in either this Court or the Court of Appeal. This Court, believing that a proper resolution of the case could not be made without a consideration of certain contractual provisions, ordered the parties hereto to submit supplemental briefs on the following issue:
Does the following contractual provision entitled "Maintenance of Traffic" (No. 104.04) which states in pertinent part:
"No direct payment will be made for providing for and maintaining traffic, except payment for temporary signs, barricades, traffic markings and detours." (emphasis ours).
apply so as to provide for a detour road not included in the original project plans. 425 So.2d 326.
We affirm the Third Circuit in its ruling that equitable estoppel does not apply in this case, and we also hold that the plaintiff is not entitled to recover under the terms of the contract.
FACTS
In 1976 DOTD notified general contractors that it would receive bids for the construction of approaches to a new bridge on Bayou Choupique. Included in that notification were a set of plans for the project. The plans provided, in part, for a detour road to be built on the north side of Bayou Choupique, that item being listed as S-2 as one of over fifty different line items included in the contractors' bids. The plans did not provide for a detour road on the south side of the bayou. The bid submitted by F. Miller & Sons, Inc. was accepted by DOTD and a contract accordingly entered into by those parties. The agreement consisted of the "Louisiana Standard Specifications for Roads and Bridges, dated 1971" (a document which is over 700 pages long) and over 30 pages of amendments to the Standard Specifications.
About five days after Miller entered into the contract with DOTD, it entered into an agreement with plaintiff subcontracting part of the work on the project. In this subcontract, Bailey agreed to assume all obligations owed DOTD by Miller; the sub-contract incorporated by reference all provisions of the contract Miller had with the State.
Sometime after construction had commenced, it became apparent that a decision would have to be made concerning the maintenance of traffic on the south side of the bayou. A discussion was held between the project engineer of DOTD, employees of Miller, John Bailey, and others. Three options were discussed: (1) Maintaining traffic by using one lane while working on the other, (2) widening one shoulder so two-way traffic could be maintained by using one lane and the shoulder while work proceeded on the other lane, and (3) constructing a temporary detour road. This last was generally agreed upon as the safest alternative under the particular circumstances of this project.
Bailey built the south detour road at a cost of approximately $30,000, for which he billed Miller. Both Miller and DOTD refused to pay, arguing that under the contract Bailey had the duty to maintain traffic and that this detour road fell within the scope of that duty. This suit followed wherein Bailey sought relief under the contract and, in the alternative, under the doctrine of equitable estoppel.
THE CONTRACT
In the supplemental brief ordered by this court, plaintiff contends that the last sentence of Sec. 104.04 of the contract clearly entitles him to demand direct payment for the construction of the south detour road. DOTD, on the other hand, contends that the one sentence must not be taken out of context, but must be construed in light of the remainder of Sec. 104.4, as well as with other parts of the contract as a whole. Sec. 104.04 reads in its entirety:
§ 104.04 MAINTENANCE OF TRAFFIC
Reasonable provisions for local traffic throughout the length of the project and the life of the contract must be made by the contractor, at his own expense, during construction.
*1058 When required on the plans or in the special provisions, the contractor may also be required to provide for through traffic, at his own expense, over the entire project or any designated portion thereof.
If the engineer directs special maintenance for the benefit of the traveling public, then the contractor will be paid therefor at unit prices in the contract or as provided in Subsection 104.03. The engineer will be the sole judge of work to be classified as special maintenance.
The contractor shall provide for and maintain through and local traffic at all times and shall conduct his operations in such manner as to cause the least possible interference with traffic in the vicinity of this project.
In order to maintain traffic, the contractor shall construct temporary detours as provided under item S-2, elsewhere herein.
No direct payment will be made for providing for and maintaining traffic, except payment for temporary signs, barricades, traffic markings and detours. (emphasis added.)
The entire contract in question, as mentioned earlier, consists of over 700 pages of "Standard Specifications" and 30 pages of amendments tailored to this particular project. Part of the contract is the "Schedule of Items," completed as per the Miller bid. It is important to note that the "Schedule of Items" included Item 713(1), a lump sum for "Temporary Signs and Barricades"; Item 729(14), for eight "Hazard Marker Assemblies"; Item S-3, a lump sum for "Temporary Traffic Markings"; and Item S-4, for one "Roadway Barricade."
The Civil Code mandates that all clauses or parts of contracts be interpreted "one by the other, giving to each the sense that results from the entire act." LSA-C.C. Art. 1955. Likewise, the courts have long held that,
A cardinal rule in the construction of contracts is that the contract must be viewed as a whole and, if possible, practical effect given to all its parts, according to each the sense that results from the entire agreement so as to avoid neutralizing or ignoring any of them or treating them as surplusage. (citations omitted; emphasis added.) Lambert v. Maryland Casualty Company, 418 So.2d 553, 559 (La.1982), reh. den. See also, Polozola v. Garlock, Inc., 343 So.2d 1000, (La.1977); Long-Bell Petroleum Col., Inc. v. Tritico,
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
439 So. 2d 1055, Counsel Stack Legal Research, https://law.counselstack.com/opinion/john-bailey-contr-v-st-dept-of-tr-dev-la-1983.