John Allen Construction, LLC v. Jerome Hancock, Sandra Hancock, and Carroll Bank and Trust

CourtCourt of Appeals of Tennessee
DecidedMarch 1, 2006
DocketW2004-02920-COA-R3-CV
StatusPublished

This text of John Allen Construction, LLC v. Jerome Hancock, Sandra Hancock, and Carroll Bank and Trust (John Allen Construction, LLC v. Jerome Hancock, Sandra Hancock, and Carroll Bank and Trust) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
John Allen Construction, LLC v. Jerome Hancock, Sandra Hancock, and Carroll Bank and Trust, (Tenn. Ct. App. 2006).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT JACKSON September 21, 2005 Session

JOHN ALLEN CONSTRUCTION, LLC v. JEROME HANCOCK, SANDRA HANCOCK, and CARROLL BANK AND TRUST

An Appeal from the Chancery Court for Benton County No. 00-195 Ron E. Harmon, Chancellor

No. W2004-02920-COA-R3-CV - Filed March 1, 2006

This is a construction case. The defendant homeowners entered into an oral contract with the plaintiff contractor to construct a house for the defendants. After the contractor had substantially completed construction of the house, the homeowners discharged the contractor. The contractor then filed suit for unpaid costs and fees. The defendant homeowners counter-sued, alleging breach of the original contract. After a trial, the trial court entered a final order granting a monetary award to the contractor for his unpaid fees, minus several credits awarded to the defendant homeowners. The record does not include any factual findings or legal conclusions detailing the basis for the award. The defendant homeowners appeal, asserting that the trial court erred in admitting the testimony of an expert witness and in its calculation of the award to the contractor. We affirm the trial court’s admission of the expert testimony, but vacate the judgment and remand to the trial court for factual findings and legal conclusions in order to resolve the remaining issues on appeal.

Tenn. R. App. P. 3; Judgment of the Chancery Court is Vacated and Remanded

HOLLY M. KIRBY , J., delivered the opinion of the Court, in which W. FRANK CRAWFORD , P.J., W.S., and ALAN E. HIGHERS, J., joined.

Carthel L. Smith, Jr., Lexington, Tennessee, for appellants Jerome Hancock and Sandra Hancock.

John W. Whitworth, Camden, Tennessee, for appellee John Allen Construction, LLC.

OPINION

The parties entered into an oral contract for the construction of a new home in Benton County, Tennessee. Under the terms of the contract, Plaintiff/Appellee John Allen Construction, LLC (“John Allen Construction”), would build the home for Defendant/Appellants Jerome Hancock and Sandra Hancock (collectively, “Hancocks”). Pursuant to the oral agreement, John Allen Construction would be paid on a time and materials basis, plus an eight percent profit. In August 1999, John Allen Construction ordered the initial plans for the Hancocks’ home. Ultimately, several alterations to the initial plans were requested and made. At some point during the construction, one of the carpenters for John Allen Construction was arrested. Subsequently, after construction of a significant portion of the home had been completed, the Hancocks dismissed John Allen Construction. The Hancocks allege that John Allen Construction was dismissed because of numerous structural deficiencies in the construction of the home.

After the Hancocks severed their relationship with John Allen Construction, on December 5, 2000, John Allen Construction filed a lawsuit against the Hancocks in the Benton County Chancery Court. The complaint alleged that John Allen Construction was not paid for a portion of the labor and materials furnished in its performance of the contract, and sought a monetary award of damages in the amount of $71,092.50, plus interest.

On January 12, 2001, the Hancocks filed their answer and counter-complaint. The Hancocks asserted that the parties had agreed upon a “cap” or maximum on the price for constructing the home, and that John Allen Construction had exceeded the agreed-upon contract price. The Hancocks contended that John Allen Construction had performed the work in a defective manner, had performed unnecessary work, and had failed to complete the construction in a timely manner. The Hancocks denied that John Allen Construction was due the $71,092.50 in damages sought in the complaint.

The Hancocks’ counter-complaint alleged that the parties had agreed that construction of the home would not exceed $250,000, although the parties later agreed to amend the original “cap” to add additional features to the home for a price of $42,000. The Hancocks asserted that, at the time the Hancocks discharged John Allen Construction for breaching the contract, they had already paid John Allen Construction $318,668.46, even though the home was not yet finished. Consequently, the Hancocks claimed, they were forced to hire third-party contractors to complete the project. Allegedly, these new contractors discovered a number of latent defects in John Allen Construction’s work.1 The Hancocks claimed that they spent $181,333.00 to correct the defects and complete the home. In the counter-complaint, they sought monetary damages of $208,000, plus compensatory and consequential damages, as well as interest.

In the course of trial preparation, the trial court ordered the Hancocks to furnish John Allen Construction with site-evaluation reports and permitted John Allen Construction’s engineering and construction experts to inspect the premises. The parties propounded discovery requests, including requests seeking the identity of expert witnesses expected to testify at trial.

The trial was held on multiple days between January 14, 2004, and February 25, 2004. Twenty-two witnesses testified, and over one hundred exhibits were entered into evidence.

1 The Hancocks later amended their counter-complaint to note additional problems related to John Allen Construction’s construction of the house.

-2- At the close of the Hancocks’ proof, John Allen Construction called an expert witness, John Mishu (“Mishu”), to testify. Neither Mishu’s identity nor the substance of his testimony had been disclosed to the Hancocks during discovery. John Allen Construction contended that Mishu’s testimony was necessary to rebut the testimony of one of the Hancocks’ experts, David Evans, a technical engineer. Mishu’s qualifications as an expert were not disputed. The Hancocks, however, objected to his testimony, asserting that Mishu was a surprise witness and that they were unable to adequately prepare for his cross-examination.

The trial court permitted Mishu to testify for the limited purpose of rebutting the testimony of David Evans. Toward that end, Mishu was not permitted to provide factual testimony, but was limited to critiquing Evans’ testing procedures and the assumptions made from those tests. To address the concern of the Hancocks’ counsel that he was unprepared to cross-examine Mishu, the trial court offered to recess the proceedings and return on another day to allow time to prepare for the cross-examination:

The Court: You have the opportunity to take a recess if you wish. You understand that? Mr. Smith: Yes. The Court: The Court will recess; we’ll come back another day if you need time. If you wish to do that. Mr. Smith: We might ought to talk about that.

The proceedings were adjourned after this exchange, and the trial proceeded without any further reference to the trial court’s offer of a continuance.2

Final judgment was entered on November 8, 2004. The order simply provided:

[T]he Court finds that the Plaintiff, John Allen Construction, LLC, is due an unpaid bill from the Defendants, Jerome Hancock and wife Sandra Hancock, in the amount of $71,092.00. The Court further finds that profits added to said bill in the amount of $5,680.00 and credits for money spent by the Defendants in the amount of $43,800.00 should be credited against said debt.

Based on the foregoing, the trial court entered a judgment in favor of John Allen Construction against the Hancocks in the amount of $21,612.00. From this order, the Hancocks now appeal.

On appeal, the Hancocks raise several issues for our review. First, the Hancocks argue that John Allen Construction was licensed to build homes only up to a cost of $110,000, and beyond that amount could recover only documented expenses.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mercer v. Vanderbilt University, Inc.
134 S.W.3d 121 (Tennessee Supreme Court, 2004)
Buckner v. Hassell
44 S.W.3d 78 (Court of Appeals of Tennessee, 2000)
White v. Vanderbilt University
21 S.W.3d 215 (Court of Appeals of Tennessee, 1999)
Lyle v. Exxon Corp.
746 S.W.2d 694 (Tennessee Supreme Court, 1988)
Strickland v. Strickland
618 S.W.2d 496 (Court of Appeals of Tennessee, 1981)
Carter v. Patrick
163 S.W.3d 69 (Court of Appeals of Tennessee, 2004)
Overstreet v. Shoney's, Inc.
4 S.W.3d 694 (Court of Appeals of Tennessee, 1999)
Hazard v. Hazard
833 S.W.2d 911 (Court of Appeals of Tennessee, 1991)
Brooks v. United Uniform Co.
682 S.W.2d 913 (Tennessee Supreme Court, 1984)
Carver v. Crocker
311 S.W.2d 316 (Court of Appeals of Tennessee, 1957)

Cite This Page — Counsel Stack

Bluebook (online)
John Allen Construction, LLC v. Jerome Hancock, Sandra Hancock, and Carroll Bank and Trust, Counsel Stack Legal Research, https://law.counselstack.com/opinion/john-allen-construction-llc-v-jerome-hancock-sandr-tennctapp-2006.