John A. Creighton Real Estate Co. v. City of Omaha

201 N.W. 657, 112 Neb. 802, 1924 Neb. LEXIS 251
Nebraska Supreme Court·Decided December 29, 1924·No. No. 22772·Published·Cited by 2 cases

Opinions

Good, J.

Action by John A. Creighton Real Estate Company against the city of Omaha and the Metropolitan Water District of said city, to recover the amount alleged to be due on three written contracts, entered into between plaintiff and the Omaha Water Company, and which, it is alleged, the defendants have assumed. General demurrers to the petition were sustained and the action dismissed. Plaintiff appeals.

We are required to determine whether ' the petition states a cause of action. The petition is too lengthy to be set out in this opinion, and we shall attempt to summarize only the material parts thereof.

From the petition it appears that the Omaha Water Company owned a franchise to operate a system of waterworks in the city of Omaha. Under its franchise its was authorized to lay and extend its mains in the streets of the city, and the city had power to require the company to lay and extend its water mains, providing the city ordered fire [804]*804hydrants to be placed, at intervals of not more than 400 feet, along such mains, and for which the city would pay a stipulated annual hydrant rental.

• In 1903 the city elected to take over the water plant at a price to be ascertained by appraisement. Upon completion of the appraisement in 1905, the city refused to take over the plant, and protracted litigation ensued between the water company and the city in the federal court over the question as to whether the city should be required to take over and pay for the plant at the appraised value. In 1912 a decree was entered requiring the city to take over the plant at the appraised value, and also to pay the further sum of $129,424 for extensions and improvements made to the water plant after the appraisement and pending litigation. This sum did not include the cost of the mains, constructed pursuant to the contracts on which this action is based. During the time of the litigation between the Omaha Water Company and the city of Omaha, the plaintiff in this action laid out Creighton’s First and Second additions to the city of Omaha, and which were incorporated in and became a part of the city. Plaintiff desirec a water supply for these additions to the city, but the water company refused to extend its water mains through the additions unless ordered by the city, or unless the cost thereof was advanced to it. The city did not order the extensions. Thereupon, plaintiff entered into three contracts, of like tenor, with the water company, whereby it agreed to advance to the water company the cost of laying and extending the mains through its additions to the city. Each contract contained the following provision: “Said The Omaha Water Company hereby agrees that when the city of Omaha shall by competent authority order the extensions herein provided for and shall order hydrants placed thereon at intervals of not more than 400 feet' under an agreement with said The Omaha Water Company to pay rental for such hydrants, said water company will thereupon refund the cost of the construction of said mains to the said John A. Creighton Real [805]*805Estate & Trust Company, and shall then become owner of said mains and their appurtenances.” These contracts are the ones on which plaintiff seeks to recover, on the theory that the city has assumed the obligations of the Omaha Water Company.

Pursuant to these contracts, the plaintiff paid to the Omaha Water Company the cost of the mains which were laid and extended through the additions, and the actual use and operation thereof passed to the defendants, with the plant, on July 1, 1912, when the Omaha Water Company, pursuant to the decree of the federal court, executed its deed conveying the plant to the city of Omaha. The Metropolitan Water District succeeded to the rights of the city in the management and operation of the water plant, under the provisions of chapter 143, Laws 1913. No fire hydrants had been placed on the mains in question, or order placed, by the city of Omaha, or its successor in interest.

The defendants urge that the petition does not state a cause of action for various reasons, among them: (1) That no cause of action has accrued because the ■ conditions on which the refund was to be made by the Omaha Water Company have never occurred, vizi, the ordering and placing bv the city of fire hydrants upon the extended mains; (2) that plaintiff’s cause of action, if any, accrued on the 1st day of July, 1912, and is barred by the statute of limitations, since the action was not begun until more than four years thereafter; and (3) that the city never assumed the contract obligations of the Omaha Water Company. In this connection it is proper to observe that, although the case was determined on demurrers to the petition, the petition did not set out a copy of the deed from the Omaha Water Company to the city, but it did allege that the city assumed the obligations of the Omaha Water Company. By stipulation of the parties, parts of the contract or deed were read into the record, and considered by the district court in passing upon the demurrers, and are before this court for consideration, the same as though they had been incorporated in the petition.

[806]*806We will first determine the question as to whether or not the petition chows that the city of Omaha became the owner of the mains which were laid, pursuant to the contracts between the plaintiff and the Omaha Water Company. It is apparent that the plaintiff had no right to enter upon the streets and lay water mains; nor did it do so; but he Omaha Water Company, possessing the right, did enter upon the streets and lay the mains, and they became a part of its water plant. The only thing that the plaintiff did was to advance to the Omaha Water Company the cost thereof, under an agreement for a refund upon the conditions stated. We think it very clear that the title to these mains, when laid, was in the Omaha Water Company.

From excerpts from the deed of the Omaha Water Company to the city, it appears that the descriptive part covers all water mains, hydrants, and appurtenances thereto, of the Omaha Water Company in the cities of Omaha, South Omaha, Florence, the village of Dundee, and places adjacent to the city of Omaha, in the county of Douglas, and all the property, rights and interest of the Omaha Water Company in and to connections between the pipes and mains and the various buildings, structures and enterprises in said cities, and then follows this clause: “ It being the purpose and intent of said The Omaha Water Company to convey, assign and transfer thereby to said city of Omaha, pursuant to the purchase elected to be made by said city of Omaha, as aforesaid, the entire system of waterworks operated by the said The Omaha Water Company, wherever located, together with the appurtenances, and all its property and rights.in and in respect thereto, except as herein excluded, including the right of said The Omaha Water Company to maintain and operate the same and every part thereof, and to receive the income from the further operation thereof.”

From this clause it appears beyond question that each and every part of the system of water mains, owned or operated by the Omaha Water Company, except such as were excluded, were conveyed to the city of Omaha, and [807]*807there is nothing in the deed, so far as set out, which shows that the mains in question were excluded.

Free access — add to your briefcase to read the full text and ask questions with AI

John A. Creighton Real Estate Co. v. City of Omaha, 201 N.W. 657, 112 Neb. 802, 1924 Neb. LEXIS 251 (Neb. 1924).

201 N.W. 657 (John A. Creighton Real Estate Co. v. City of Omaha) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Lee Sapp Leasing, Inc. v. Catholic Archbishop of Omaha
540 N.W.2d 101 (Nebraska Supreme Court, 1995)