John A. Becker Co. v. Jedson Eng'g, Inc.

2018 Ohio 3924, 121 N.E.3d 788
CourtOhio Court of Appeals
DecidedSeptember 28, 2018
Docket27891
StatusPublished
Cited by12 cases

This text of 2018 Ohio 3924 (John A. Becker Co. v. Jedson Eng'g, Inc.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
John A. Becker Co. v. Jedson Eng'g, Inc., 2018 Ohio 3924, 121 N.E.3d 788 (Ohio Ct. App. 2018).

Opinion

HALL, J.

*790 {¶ 1} Two appeals are before us. Defendant-appellant, Jedson Engineering, Inc., appeals from an order overruling its motion for a stay pending arbitration. Jedson contends that the trial court erred by finding that it waived its right to arbitration by actively participating in litigation for nine months before raising the issue of arbitration. Plaintiff-cross-appellant, the John A. Becker Co., cross-appeals from the same order, but does not want the order reversed or modified. Rather, Becker seeks to change the reason for the denial of a stay. Becker contends that the arbitration clause in Jedson's "purchase order," which was submitted in response to Becker's "Credit Application Agreement" and Becker's quotation for materials, was not part of the contract, and consequently Jedson has no contractual right to arbitration.

{¶ 2} We conclude that the trial court did not abuse its discretion by finding that Jedson waived its right to arbitration. We also conclude that the trial court's findings as to the content of the parties' contract, which are raised by Becker in its cross-appeal, remain interlocutory in nature at this point in the proceedings and are not properly before us. We affirm the trial court's order.

I. Background

{¶ 3} This case arises out of a project in Oklahoma in which Jedson was the general contractor hired by CP Kelco to convert an existing manufacturing line from one product to another product. Jedson sought to purchase certain lighting materials from Becker, and on April 20, 2016, Jedson executed Becker's "Credit Application Agreement," which included sale terms and conditions, including payment terms. The next day, April 21, Becker sent Jedson a quotation for certain materials, totaling $40,998. Jedson submitted a "Purchase Order" the same day for the items listed in the quotation. Accompanying the purchase order were certain terms and conditions, including these two provisions:

2. Acceptance . Acceptance of the Order is expressly limited to the terms of the Agreement. Shipment and/or delivery by Seller of the items covered by the Agreement with the consent of the buyer shall in all cases constitute an unqualified acceptance of all the terms and conditions of the Agreement by Seller, whether or not Seller has countersigned the Agreement and/or the Order. No additional and/or different terms, including those which appear in any quotation, acceptance, invoice, sales order, or acknowledgement or written confirmation from Seller, shall be of any force or effect. Buyer has hereby notified Seller of Buyer's objection to any additional and/or different terms, in a duly executed writing. The Agreement shall constitute the entire agreement between Buyer and Seller unless otherwise expressly agreed to in a writing duly executed by Buyer and Seller.
16. Law and Jurisdiction : Dispute Resolution. * * * Buyer, at its option may also invoke binding and exclusive arbitration in Cincinnati, Ohio under the American Arbitration Association's Commercial Arbitration Rules, and Seller agrees to submit to such arbitration and to dismiss any legal proceedings related to the subject matter of such arbitration * * *. Buyer, at its option, may also invoke non-binding mediation, and Seller agrees to submit to such mediation and to stay or dismiss any legal proceedings relating to the subject matter there.

{¶ 4} On June 7, 2016, Becker delivered the materials to Oklahoma, in accordance *791 with the parties' agreement. But Jedson did not pay. According to Jedson, disputes about the project arose between it and CP Kelco, and CP Kelco refused to pay Jedson for work performed on the project. As a result, Jedson failed to pay approximately fifty subcontractors and material suppliers, including Becker. In August 2016, one of these subcontractors, Miller Valve & Controls, Inc., filed suit in Oklahoma state court against Jedson, CP Kelco, and six other defendants related to lien foreclosure and payment claims for the project. In September 2016, Jedson filed cross-claims against CP Kelco, and CP Kelco then filed cross-claims against Jedson for, among other things, "defective, nonconforming and unfit design and construction work" by Jedson's subcontractors and vendors. CP Kelco's cross-claims did not specify the nature of the alleged defective, nonconforming work, and unfit work or the responsibility of specific subcontractors or vendors. As a result, Jedson claimed that it did not know if the materials supplied by Becker were defective, nonconforming, or unfit, as alleged by CP Kelco.

{¶ 5} On December 9, 2016, Becker filed suit against Jedson in the Montgomery County Common Pleas Court for breach of contract. The parties originally stipulated to an extension of time until April 11, 2017, for Jedson to respond to the complaint, but the trial court found this unreasonable and shortened the deadline to February 28. Jedson did not file a response by the deadline, so on March 7, the trial court issued a notice of default. Jedson responded to the notice, and the court granted it leave to respond. On April 19, Jedson filed a motion to dismiss or, alternatively, a motion for a stay of the proceedings. Jedson asked the court to dismiss Becker's complaint or to stay any further proceedings under the doctrine of forum non conveniens, as a matter of comity (due to the pending Oklahoma litigation), or because of a failure to join CP Kelco as a necessary party. The motion also mentioned a stay based on a request for mediation, but Jedson did not argue this basis and, according to an affidavit filed by Becker, Jedson never requested that Becker engage in mediation. In response, Becker pointed out that it did not have a claim against CP Kelco, nor did it have a lien on CP Kelco's property. Moreover, Becker said that it was not involved in the Oklahoma litigation and that there was no litigation pending between it and Jedson in Oklahoma.

{¶ 6} The trial court and both parties agreed to hold the case in abeyance while the parties in the Oklahoma litigation tried to resolve the matter and get all the subcontractors and vendors paid. Counsel for Becker updated the trial court on the status of the Oklahoma litigation. In May 2017, Jedson filed a third-party complaint against Becker in the Oklahoma litigation, but it later voluntarily dismissed its claims against Becker, after Becker filed a motion to dismiss for lack of personal jurisdiction. This occurred after the Oklahoma court had dismissed on the same ground Jedson's claims against another Ohio-based defendant similarly situated to Becker.

{¶ 7} Back in Ohio, on September 22, 2017, while Jedson's first motion for a stay was still pending, Jedson filed a second motion for a stay pending arbitration. On November 6, the trial court overruled Jedson's first motion to dismiss or stay proceedings, and on January 29, 2018, the court overruled Jedson's motion for a stay pending arbitration. The court concluded that, while the terms of parties' contract gave Jedson the right to invoke arbitration, Jedson had waived the right by failing to seek (or even mention) arbitration as a remedy for over nine months while actively participating in litigation.

*792

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Absolute Resolutions Invests., L.L.C. v. Moran
2025 Ohio 2999 (Ohio Court of Appeals, 2025)
State v. Wells
2025 Ohio 2792 (Ohio Court of Appeals, 2025)
Hogg v. Grace Community Church
2024 Ohio 1729 (Ohio Court of Appeals, 2024)
State v. Debord
2023 Ohio 4204 (Ohio Court of Appeals, 2023)
Coldly v. Fuyao Glass America, Inc.
2022 Ohio 1960 (Ohio Court of Appeals, 2022)
McCullough v. Bennett
2022 Ohio 1880 (Ohio Court of Appeals, 2022)
Cook v. Pitter Patter Learning Ctr., L.L.C.
2022 Ohio 961 (Ohio Court of Appeals, 2022)
State v. Clark
2021 Ohio 2531 (Ohio Court of Appeals, 2021)
Rudolph v. Wright Patt Credit Union
2021 Ohio 2215 (Ohio Court of Appeals, 2021)
Fontanarosa v. Connors
2021 Ohio 2346 (Ohio Court of Appeals, 2021)
BND Rentals, Inc. v. Dayton Power & Light Co.
2020 Ohio 4484 (Ohio Court of Appeals, 2020)
State v. Middleton
2020 Ohio 1308 (Ohio Court of Appeals, 2020)

Cite This Page — Counsel Stack

Bluebook (online)
2018 Ohio 3924, 121 N.E.3d 788, Counsel Stack Legal Research, https://law.counselstack.com/opinion/john-a-becker-co-v-jedson-engg-inc-ohioctapp-2018.