NOTICE: Summary decisions issued by the Appeals Court pursuant to M.A.C. Rule 23.0, as appearing in 97 Mass. App. Ct. 1017 (2020) (formerly known as rule 1:28, as amended by 73 Mass. App. Ct. 1001 [2009]), are primarily directed to the parties and, therefore, may not fully address the facts of the case or the panel's decisional rationale. Moreover, such decisions are not circulated to the entire court and, therefore, represent only the views of the panel that decided the case. A summary decision pursuant to rule 23.0 or rule 1:28 issued after February 25, 2008, may be cited for its persuasive value but, because of the limitations noted above, not as binding precedent. See Chace v. Curran, 71 Mass. App. Ct. 258, 260 n.4 (2008).
COMMONWEALTH OF MASSACHUSETTS
APPEALS COURT
24-P-679
J.K. SCANLAN COMPANY, LLC
vs.
EDWARD J. BARTLETT, JR., trustee,1 & others.2
MEMORANDUM AND ORDER PURSUANT TO RULE 23.0
In 2016, the plaintiff, J.K. Scanlan Company, LLC, a
general contractor (contractor), entered into a contract with
the defendant, the Kargman Family Brookline Residence Trust (the
trust), to undertake a major renovation project at Robert and
Marjie Kargman's (the Kargmans) home in Brookline.3 The project
did not go smoothly. After eighteen months, the contractor left
under contested circumstances. When the trust refused to pay
the contractor for a large outstanding invoice, the contractor
1 Of the Kargman Family Brookline Residence Trust.
2 Robert Kargman and Marjie Kargman.
3The Kargman home was held in trust. Robert Kargman signed the contract on behalf of the trust. brought the present action alleging breach of contract and
related theories against the Kargmans and the trust. The trust
filed several counterclaims, including for breach of contract
and negligence.4 After a trial, a jury found that the trust, but
not the contractor, had breached the contract and that the
contractor was negligent in its supervision of the project but
the negligence did not cause the trust any damages. The jury
awarded the contractor $1,791,568.93 in damages for the trust's
breach of contract. On the trust's motions for judgment
notwithstanding the verdict and for a new trial, the trial judge
reduced the jury's damages award to $1,595,889 plus prejudgment
interest but denied all other requests for relief. An amended
judgment entered accordingly.
The trust appeals from the amended judgment. The trust
challenges the jury instructions and claims that the verdicts
were inconsistent. We conclude that these arguments are waived
and affirm.5
4 The parties stipulated to the dismissal of the Kargmans individually as defendants.
5 The counts in the complaint and counterclaims that were not decided by the jury were dismissed either by stipulation or by the judge. The trust does not challenge the dismissal of any such counterclaims here. Nor does it challenge the judge's calculation of the interest on the amended judgment.
2 Background. The jury could have found the following facts.
On June 15, 2016, the parties executed a contract (the contract)
pursuant to which the contractor was to "supervise and direct
the Work, using the Contractor’s best skill and attention"
(supervision clause). The contractor warranted the work would
conform to the requirements of the contract documents and be
free from defects, and agreed that "Work, materials, or
equipment not conforming to these requirements may be considered
defective."
As the project progressed, the relationship between the
Kargmans and the contractor became strained. From the
contractor's perspective, the Kargmans were difficult clients
because they frequently requested change orders and were
verbally abusive.
The trust claimed that the source of the strain was the
contractor's negligent supervision of the project. For example,
at one point in November 2017, the Kargmans returned home and
discovered that there was no heat in the portion of the house
where they were residing.6 Shortly thereafter, a sump pump that
had been installed to drain water from the roof froze, causing
6 The Kargmans chose to live in a portion of their home during the renovation project.
3 water to accumulate and pour through the temporary roof into the
home, damaging the hardwood floor.7
In October 2017, Robert Kargman spoke to the contractor's
principal, Mike Fish, about a path forward. Ultimately, in mid-
November 2017, the parties agreed that the contractor would
amicably separate from the project. The trust agreed to pay the
contractor for the work completed to that point, and the
contractor agreed to facilitate the transition of the project to
a new contractor on December 1, 2017. The contractor left the
project site, as agreed, on December 1, 2017, and expected to be
paid for its work.
Later that same day, December 1, 2017, the trust's attorney
sent a letter to the contractor purporting to terminate the
contractor for cause for materially breaching the contract and
abandoning the project. At that time, the trust still owed the
contractor $1,062,093.47.
In February 2018, the contractor filed the present action
to recover the amount due. As noted, the trust filed
counterclaims. From May 9, 2023, to June 1, 2023, the parties
tried their dueling claims to a jury. On June 1, 2023, the jury
returned a verdict, finding for the contractor on its claims for
7 In both instances, the contractor immediately took responsibility and repaired the damage.
4 breach of contract, fraud, and promissory estoppel, and awarding
damages. The jury rejected the trust's counterclaims for breach
of contract, fraud, and violations of the Consumer Protection
Act. The jury found for the trust on its counterclaims for
negligence and violations of the Home Improvement Contractors
Act, but, finding no causation, did not award the trust any
damages.
More than two months later, on August 17 and 18, 2023, the
trust filed motions for judgment notwithstanding the verdict and
a new trial, raising for the first time the issues that form the
basis of its appeal here. On October 16, 2023, the motion judge
(who was also the trial judge) denied both motions in a
comprehensive written memorandum of decision, and the amended
judgment now before us then entered.
Discussion. The trust makes two interrelated arguments.
First, the trust argues that the trial judge should have
determined as a matter of law that the supervision clause
related to "design and construction" of the project and should
have then instructed the jury that the contractor could not
recover on the contract without showing "complete and strict
performance" of the supervision clause pursuant to the
heightened standard of G4S Tech. LLC v. Massachusetts Tech. Park
Corp., 479 Mass. 721, 730-731 (2018) (G4S). The trust argues
that because the judge did not give that instruction, the
5 verdict must be vacated and the case must be remanded for a new
trial.
Second, the trust asserts that the jury's verdict that the
contractor was negligent is inconsistent with their verdict
finding that the contractor was entitled to recover damages on
its breach of contract claim. The trust reasons that because
Free access — add to your briefcase to read the full text and ask questions with AI
NOTICE: Summary decisions issued by the Appeals Court pursuant to M.A.C. Rule 23.0, as appearing in 97 Mass. App. Ct. 1017 (2020) (formerly known as rule 1:28, as amended by 73 Mass. App. Ct. 1001 [2009]), are primarily directed to the parties and, therefore, may not fully address the facts of the case or the panel's decisional rationale. Moreover, such decisions are not circulated to the entire court and, therefore, represent only the views of the panel that decided the case. A summary decision pursuant to rule 23.0 or rule 1:28 issued after February 25, 2008, may be cited for its persuasive value but, because of the limitations noted above, not as binding precedent. See Chace v. Curran, 71 Mass. App. Ct. 258, 260 n.4 (2008).
COMMONWEALTH OF MASSACHUSETTS
APPEALS COURT
24-P-679
J.K. SCANLAN COMPANY, LLC
vs.
EDWARD J. BARTLETT, JR., trustee,1 & others.2
MEMORANDUM AND ORDER PURSUANT TO RULE 23.0
In 2016, the plaintiff, J.K. Scanlan Company, LLC, a
general contractor (contractor), entered into a contract with
the defendant, the Kargman Family Brookline Residence Trust (the
trust), to undertake a major renovation project at Robert and
Marjie Kargman's (the Kargmans) home in Brookline.3 The project
did not go smoothly. After eighteen months, the contractor left
under contested circumstances. When the trust refused to pay
the contractor for a large outstanding invoice, the contractor
1 Of the Kargman Family Brookline Residence Trust.
2 Robert Kargman and Marjie Kargman.
3The Kargman home was held in trust. Robert Kargman signed the contract on behalf of the trust. brought the present action alleging breach of contract and
related theories against the Kargmans and the trust. The trust
filed several counterclaims, including for breach of contract
and negligence.4 After a trial, a jury found that the trust, but
not the contractor, had breached the contract and that the
contractor was negligent in its supervision of the project but
the negligence did not cause the trust any damages. The jury
awarded the contractor $1,791,568.93 in damages for the trust's
breach of contract. On the trust's motions for judgment
notwithstanding the verdict and for a new trial, the trial judge
reduced the jury's damages award to $1,595,889 plus prejudgment
interest but denied all other requests for relief. An amended
judgment entered accordingly.
The trust appeals from the amended judgment. The trust
challenges the jury instructions and claims that the verdicts
were inconsistent. We conclude that these arguments are waived
and affirm.5
4 The parties stipulated to the dismissal of the Kargmans individually as defendants.
5 The counts in the complaint and counterclaims that were not decided by the jury were dismissed either by stipulation or by the judge. The trust does not challenge the dismissal of any such counterclaims here. Nor does it challenge the judge's calculation of the interest on the amended judgment.
2 Background. The jury could have found the following facts.
On June 15, 2016, the parties executed a contract (the contract)
pursuant to which the contractor was to "supervise and direct
the Work, using the Contractor’s best skill and attention"
(supervision clause). The contractor warranted the work would
conform to the requirements of the contract documents and be
free from defects, and agreed that "Work, materials, or
equipment not conforming to these requirements may be considered
defective."
As the project progressed, the relationship between the
Kargmans and the contractor became strained. From the
contractor's perspective, the Kargmans were difficult clients
because they frequently requested change orders and were
verbally abusive.
The trust claimed that the source of the strain was the
contractor's negligent supervision of the project. For example,
at one point in November 2017, the Kargmans returned home and
discovered that there was no heat in the portion of the house
where they were residing.6 Shortly thereafter, a sump pump that
had been installed to drain water from the roof froze, causing
6 The Kargmans chose to live in a portion of their home during the renovation project.
3 water to accumulate and pour through the temporary roof into the
home, damaging the hardwood floor.7
In October 2017, Robert Kargman spoke to the contractor's
principal, Mike Fish, about a path forward. Ultimately, in mid-
November 2017, the parties agreed that the contractor would
amicably separate from the project. The trust agreed to pay the
contractor for the work completed to that point, and the
contractor agreed to facilitate the transition of the project to
a new contractor on December 1, 2017. The contractor left the
project site, as agreed, on December 1, 2017, and expected to be
paid for its work.
Later that same day, December 1, 2017, the trust's attorney
sent a letter to the contractor purporting to terminate the
contractor for cause for materially breaching the contract and
abandoning the project. At that time, the trust still owed the
contractor $1,062,093.47.
In February 2018, the contractor filed the present action
to recover the amount due. As noted, the trust filed
counterclaims. From May 9, 2023, to June 1, 2023, the parties
tried their dueling claims to a jury. On June 1, 2023, the jury
returned a verdict, finding for the contractor on its claims for
7 In both instances, the contractor immediately took responsibility and repaired the damage.
4 breach of contract, fraud, and promissory estoppel, and awarding
damages. The jury rejected the trust's counterclaims for breach
of contract, fraud, and violations of the Consumer Protection
Act. The jury found for the trust on its counterclaims for
negligence and violations of the Home Improvement Contractors
Act, but, finding no causation, did not award the trust any
damages.
More than two months later, on August 17 and 18, 2023, the
trust filed motions for judgment notwithstanding the verdict and
a new trial, raising for the first time the issues that form the
basis of its appeal here. On October 16, 2023, the motion judge
(who was also the trial judge) denied both motions in a
comprehensive written memorandum of decision, and the amended
judgment now before us then entered.
Discussion. The trust makes two interrelated arguments.
First, the trust argues that the trial judge should have
determined as a matter of law that the supervision clause
related to "design and construction" of the project and should
have then instructed the jury that the contractor could not
recover on the contract without showing "complete and strict
performance" of the supervision clause pursuant to the
heightened standard of G4S Tech. LLC v. Massachusetts Tech. Park
Corp., 479 Mass. 721, 730-731 (2018) (G4S). The trust argues
that because the judge did not give that instruction, the
5 verdict must be vacated and the case must be remanded for a new
trial.
Second, the trust asserts that the jury's verdict that the
contractor was negligent is inconsistent with their verdict
finding that the contractor was entitled to recover damages on
its breach of contract claim. The trust reasons that because
the jury found that the contractor had negligently supervised
the construction, this finding necessarily was inconsistent with
the jury's award of damages to the contractor for breach of
contract because "a contractor cannot recover on the contract
itself without showing complete and strict performance
[quotation omitted]" of all contract provisions relating to
"design and construction." G4S, 479 Mass. at 730-731.
For the reasons explained below, we conclude that both of
these arguments are waived. We then address the trust's
arguments that waiver should be excused.
1. The jury instructions. At no point before or during
the trial did the trust ask the judge to determine as a matter
of law that the supervision clause related to "design and
construction" of the project and was thus subject to the
heightened "complete and strict performance" standard of G4S.
In fact, the trust received the instruction its counsel sought;
did not object to the instructions given; and did not request
the instruction it now presses in the first instance, despite
6 ample opportunity to do so. Thus, the argument is waived.
Jarry v. Corsaro, 40 Mass. App. Ct. 601, 603 (1996) ("A party
must make a proper objection to a jury instruction before the
jury retires in order to preserve the issue for appeal"). See
Mass. R. Civ. P. 51 (b), 365 Mass. 816 (1974).
On the eleventh day of trial, the judge met with counsel to
discuss the proposed jury instructions and verdict slips. The
trust's counsel requested a jury instruction on G4S's complete
and strict performance standard. The trust's counsel made the
request in general terms, asking that the judge instruct the
jury about the contractor's "obligation of complete and strict
performance of all terms relating to the design and construction
work." The judge took the request under advisement.
At the charge conference on May 30, 2023, the judge
discussed her draft jury instructions with all counsel. The
draft jury instructions included an instruction, as the trust
requested, that "under our law [the contractor] must show
complete and strict performance of all of the contract's claims
that relate to construction." The trust's counsel did not
object to the proposed instruction. The judge subsequently
revised other jury instructions based on input from counsel and
emailed the revised draft to counsel that evening.
On May 31, 2023, the judge discussed the revised jury
instructions and verdict slip with counsel, and made additional
7 revisions based on comments raised by counsel that morning. Yet
again, the trust's counsel did not object to the judge's
proposed jury instruction on the G4S complete and strict
performance standard.
The judge then charged the jury. Consistent with her
initial draft G4S instruction, to which the trust did not
object, the judge instructed the jury that "because [the
plaintiff] is a contractor, under our law it must show complete
and strict performance of all of the contract's claims that
relate to construction." The judge then called all counsel to
sidebar and invited any objections to her instructions. The
trust's counsel did not object.
"As provided by the Massachusetts Rules of Civil Procedure,
'no party may assign as error the giving or failure to give an
instruction unless [the party] objects thereto before the jury
retire[] to consider [their] verdict, stating distinctly the
matter to which [the party] objects and the grounds of [the]
objection.'" Rotkiewicz v. Sadowsky, 431 Mass. 748, 750-751
(2000), quoting Mass. R. Civ. P. 51 (b). "The primary purpose
of the rule is to put the judge on notice of the issue," and
thus "[a] party objecting to the inclusion or exclusion of an
instruction must . . . clearly bring the objection and the
grounds for it to the attention of the judge." Rotkiewicz,
supra at 751.
8 Here, the trust did not bring to the judge's attention the
issue it now raises -- that whether the supervision clause
relates to "design and construction" is a predicate legal
determination that the judge should have made before the start
of trial. Nor did the trust make a timely request for a G4S
instruction relating to the supervision clause in particular, or
even object to the jury instructions as drafted and delivered,
despite ample opportunity to do so. The trust has thus waived
its opportunity to challenge the jury instructions on appeal.
See Greene v. Philip Morris USA Inc., 491 Mass. 866, 877-878
(2023) (defendant waived its challenge to jury instruction on
causation where there was "no indication in the record that the
judge was on notice of [the defendant's] objection"; "[i]f [the
causation] instructions . . . were not enough to satisfy [the
defendant], it needed to expressly say so"); Stone v. W.E.
Aubuchon Co., 29 Mass. App. Ct. 523, 529 (1990) ("As the lessee
did not object to the judge's instructions on this issue, it may
not raise an objection in this court"); Grey v. Eastern Tank
Lines, Inc., 7 Mass. App. Ct. 889, 889 (1979) (no error in
denial of plaintiffs' motion for new trial where "[p]laintiffs'
counsel did not request such an instruction, and there was no
objection made to the charge as delivered").
2. The jury verdict. The trust's second argument on
appeal is that the jury's verdict that the contractor was
9 negligent was inconsistent with their verdict that the
contractor was entitled to recover damages for the trust's
breach of the contract. Once again, because the trust did not
raise this argument when the judge could have addressed it with
the jury, but instead raised it long after the jury had been
discharged, it is waived.
It is well established that when a party does not object to
a perceived inconsistency in the jury verdict before the jury is
discharged, that party "may not raise the issue as of right by
way of a motion for new trial." Adams v. United States Steel
Corp., 24 Mass. App. Ct. 102, 104 (1987) (affirming denial of
new trial motion because trial counsel did not object to
inconsistent verdicts prior to discharge of jury). See Kuwaiti
Danish Computer Co. v. Digital Equip. Corp., 438 Mass. 459, 466
(2003) ("[A] party must request the judge to instruct the jury
to reconsider their verdict . . . when there is time to correct
any inconsistency. Failure to make such a timely request
constitutes a waiver of any challenge to the verdict on the
ground that it is inconsistent"); Uloth v. City Tank Corp., 376
Mass. 874, 884 (1978) (having failed to raise inconsistency in
jury's verdict before jury was dismissed, defendants could not
argue inconsistency on appeal).
"Where, as here, a jury returns a special verdict, an objection that verdicts on several counts are inconsistent with each other must be taken at the time when the verdicts
10 are returned and before they are recorded, so that the trial judge has an opportunity to correct the error if there is one" (quotation and citation omitted).
Conway v. Planet Fitness Holdings, LLC, 101 Mass. App. Ct. 89,
101 (2022). Here, the trust did not contemporaneously object to
the jury verdict. As noted, the trust raised this issue for the
first time in motions for new trial and judgment notwithstanding
the verdict. The trust's failure to raise a contemporaneous
objection to the jury verdict is fatal to its claim at this
point. See id.8
3. Grounds to excuse waiver. Notwithstanding that the
trust failed to raise both of the above claims in a timely
manner, the trust urges us to consider them on appeal because
"the issues are (1) unresolved in the Commonwealth, (2) a matter
8 We disagree with the trust that a contemporaneous objection to the jury verdict would have been futile. As the judge concluded in denying the trust's posttrial motions, the jury's findings could have been harmonized in several ways, including that the jury could have found that the supervision clause did not involve construction and so did not trigger the "complete and strict performance" standard of G4S. See Adams, 24 Mass. App. Ct. at 104 (a trial judge can resolve inconsistency in a jury's verdicts by "find[ing] a view of the evidence which harmonizes the answers"). This harmonization is consistent with the trust's closing argument, which identified several ways in which the contractor allegedly failed to completely and strictly comply with contract terms related to construction, without mentioning the supervision clause. Alternatively, if the judge had found that the verdicts could have been inconsistent, she could have asked the jury to answer additional special verdict questions to address any such inconsistencies.
11 of public importance, (3) likely to arise again in later cases,
and (4) fully briefed by the parties on appeal." See, e.g.,
Guardianship of Kelvin, 94 Mass. App. Ct. 448, 452-453 (2018).
We disagree.
We do not think that this case presents an appropriate
opportunity to exercise our discretion to consider the waived
issues. First, we disagree with the trust that G4S marked a
"sea change in construction law"; the Supreme Judicial Court was
merely "interpret[ing]" its prior cases, "all" of which
"concerned breaches of the actual design and construction of the
project." G4S, 479 Mass. at 731. Second, the trust cites no
case overturning a jury verdict on a waived ground, much less
one where the jury's verdict, following a lengthy trial in which
both sides were represented by counsel, appears reasonable based
on the record evidence. Compare Composto v. Massachusetts Bay
Transp. Auth., 48 Mass. App. Ct. 477, 480 (2000) (judge's
instructions to jury provided adequate and necessary guidance to
12 decide issues related to liability and did not create risk that
jury's determinations were "distorted in any manner").
Amended judgment affirmed.
By the Court (Neyman, Shin & Wood, JJ.9),
Clerk
Entered: June 5, 2025.
9 The panelists are listed in order of seniority.