J.K. SCANLAN COMPANY, LLC v. EDWARD J. BARTLETT, JR., Trustee, & Others.

CourtMassachusetts Appeals Court
DecidedJune 5, 2025
Docket24-P-0679
StatusUnpublished

This text of J.K. SCANLAN COMPANY, LLC v. EDWARD J. BARTLETT, JR., Trustee, & Others. (J.K. SCANLAN COMPANY, LLC v. EDWARD J. BARTLETT, JR., Trustee, & Others.) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J.K. SCANLAN COMPANY, LLC v. EDWARD J. BARTLETT, JR., Trustee, & Others., (Mass. Ct. App. 2025).

Opinion

NOTICE: Summary decisions issued by the Appeals Court pursuant to M.A.C. Rule 23.0, as appearing in 97 Mass. App. Ct. 1017 (2020) (formerly known as rule 1:28, as amended by 73 Mass. App. Ct. 1001 [2009]), are primarily directed to the parties and, therefore, may not fully address the facts of the case or the panel's decisional rationale. Moreover, such decisions are not circulated to the entire court and, therefore, represent only the views of the panel that decided the case. A summary decision pursuant to rule 23.0 or rule 1:28 issued after February 25, 2008, may be cited for its persuasive value but, because of the limitations noted above, not as binding precedent. See Chace v. Curran, 71 Mass. App. Ct. 258, 260 n.4 (2008).

COMMONWEALTH OF MASSACHUSETTS

APPEALS COURT

24-P-679

J.K. SCANLAN COMPANY, LLC

vs.

EDWARD J. BARTLETT, JR., trustee,1 & others.2

MEMORANDUM AND ORDER PURSUANT TO RULE 23.0

In 2016, the plaintiff, J.K. Scanlan Company, LLC, a

general contractor (contractor), entered into a contract with

the defendant, the Kargman Family Brookline Residence Trust (the

trust), to undertake a major renovation project at Robert and

Marjie Kargman's (the Kargmans) home in Brookline.3 The project

did not go smoothly. After eighteen months, the contractor left

under contested circumstances. When the trust refused to pay

the contractor for a large outstanding invoice, the contractor

1 Of the Kargman Family Brookline Residence Trust.

2 Robert Kargman and Marjie Kargman.

3The Kargman home was held in trust. Robert Kargman signed the contract on behalf of the trust. brought the present action alleging breach of contract and

related theories against the Kargmans and the trust. The trust

filed several counterclaims, including for breach of contract

and negligence.4 After a trial, a jury found that the trust, but

not the contractor, had breached the contract and that the

contractor was negligent in its supervision of the project but

the negligence did not cause the trust any damages. The jury

awarded the contractor $1,791,568.93 in damages for the trust's

breach of contract. On the trust's motions for judgment

notwithstanding the verdict and for a new trial, the trial judge

reduced the jury's damages award to $1,595,889 plus prejudgment

interest but denied all other requests for relief. An amended

judgment entered accordingly.

The trust appeals from the amended judgment. The trust

challenges the jury instructions and claims that the verdicts

were inconsistent. We conclude that these arguments are waived

and affirm.5

4 The parties stipulated to the dismissal of the Kargmans individually as defendants.

5 The counts in the complaint and counterclaims that were not decided by the jury were dismissed either by stipulation or by the judge. The trust does not challenge the dismissal of any such counterclaims here. Nor does it challenge the judge's calculation of the interest on the amended judgment.

2 Background. The jury could have found the following facts.

On June 15, 2016, the parties executed a contract (the contract)

pursuant to which the contractor was to "supervise and direct

the Work, using the Contractor’s best skill and attention"

(supervision clause). The contractor warranted the work would

conform to the requirements of the contract documents and be

free from defects, and agreed that "Work, materials, or

equipment not conforming to these requirements may be considered

defective."

As the project progressed, the relationship between the

Kargmans and the contractor became strained. From the

contractor's perspective, the Kargmans were difficult clients

because they frequently requested change orders and were

verbally abusive.

The trust claimed that the source of the strain was the

contractor's negligent supervision of the project. For example,

at one point in November 2017, the Kargmans returned home and

discovered that there was no heat in the portion of the house

where they were residing.6 Shortly thereafter, a sump pump that

had been installed to drain water from the roof froze, causing

6 The Kargmans chose to live in a portion of their home during the renovation project.

3 water to accumulate and pour through the temporary roof into the

home, damaging the hardwood floor.7

In October 2017, Robert Kargman spoke to the contractor's

principal, Mike Fish, about a path forward. Ultimately, in mid-

November 2017, the parties agreed that the contractor would

amicably separate from the project. The trust agreed to pay the

contractor for the work completed to that point, and the

contractor agreed to facilitate the transition of the project to

a new contractor on December 1, 2017. The contractor left the

project site, as agreed, on December 1, 2017, and expected to be

paid for its work.

Later that same day, December 1, 2017, the trust's attorney

sent a letter to the contractor purporting to terminate the

contractor for cause for materially breaching the contract and

abandoning the project. At that time, the trust still owed the

contractor $1,062,093.47.

In February 2018, the contractor filed the present action

to recover the amount due. As noted, the trust filed

counterclaims. From May 9, 2023, to June 1, 2023, the parties

tried their dueling claims to a jury. On June 1, 2023, the jury

returned a verdict, finding for the contractor on its claims for

7 In both instances, the contractor immediately took responsibility and repaired the damage.

4 breach of contract, fraud, and promissory estoppel, and awarding

damages. The jury rejected the trust's counterclaims for breach

of contract, fraud, and violations of the Consumer Protection

Act. The jury found for the trust on its counterclaims for

negligence and violations of the Home Improvement Contractors

Act, but, finding no causation, did not award the trust any

damages.

More than two months later, on August 17 and 18, 2023, the

trust filed motions for judgment notwithstanding the verdict and

a new trial, raising for the first time the issues that form the

basis of its appeal here. On October 16, 2023, the motion judge

(who was also the trial judge) denied both motions in a

comprehensive written memorandum of decision, and the amended

judgment now before us then entered.

Discussion. The trust makes two interrelated arguments.

First, the trust argues that the trial judge should have

determined as a matter of law that the supervision clause

related to "design and construction" of the project and should

have then instructed the jury that the contractor could not

recover on the contract without showing "complete and strict

performance" of the supervision clause pursuant to the

heightened standard of G4S Tech. LLC v. Massachusetts Tech. Park

Corp., 479 Mass. 721, 730-731 (2018) (G4S). The trust argues

that because the judge did not give that instruction, the

5 verdict must be vacated and the case must be remanded for a new

trial.

Second, the trust asserts that the jury's verdict that the

contractor was negligent is inconsistent with their verdict

finding that the contractor was entitled to recover damages on

its breach of contract claim. The trust reasons that because

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Uloth v. City Tank Corp.
384 N.E.2d 1188 (Massachusetts Supreme Judicial Court, 1978)
Stone v. W. E. Aubuchon Co.
562 N.E.2d 852 (Massachusetts Appeals Court, 1990)
Adams v. United States Steel Corp.
506 N.E.2d 893 (Massachusetts Appeals Court, 1987)
G4S Technology LLC v. Massachusetts Technology Park Corp.
99 N.E.3d 728 (Massachusetts Supreme Judicial Court, 2018)
Guardianship of Kelvin
114 N.E.3d 102 (Massachusetts Appeals Court, 2018)
Rotkiewicz v. Sadowsky
730 N.E.2d 282 (Massachusetts Supreme Judicial Court, 2000)
Kuwaiti Danish Computer Co. v. Digital Equipment Corp.
781 N.E.2d 787 (Massachusetts Supreme Judicial Court, 2003)
Grey v. Eastern Tank Lines, Inc.
387 N.E.2d 176 (Massachusetts Appeals Court, 1979)
Jarry v. Corsaro
666 N.E.2d 1012 (Massachusetts Appeals Court, 1996)
Composto v. Massachusetts Bay Transportation Authority
722 N.E.2d 984 (Massachusetts Appeals Court, 2000)
Chace v. Curran
881 N.E.2d 792 (Massachusetts Appeals Court, 2008)
JAYNE CONWAY v. PLANET FITNESS HOLDINGS, LLC, & others.
101 Mass. App. Ct. 89 (Massachusetts Appeals Court, 2022)

Cite This Page — Counsel Stack

Bluebook (online)
J.K. SCANLAN COMPANY, LLC v. EDWARD J. BARTLETT, JR., Trustee, & Others., Counsel Stack Legal Research, https://law.counselstack.com/opinion/jk-scanlan-company-llc-v-edward-j-bartlett-jr-trustee-others-massappct-2025.