Jimmie Joseph Johnson v. Amoco Production Co., Amoco Production Co., Third-Party v. Technical Compression Services, Inc., Third-Party

5 F.3d 949, 1993 U.S. App. LEXIS 28709, 1993 WL 413855
CourtCourt of Appeals for the Third Circuit
DecidedNovember 3, 1993
Docket93-4839
StatusPublished
Cited by25 cases

This text of 5 F.3d 949 (Jimmie Joseph Johnson v. Amoco Production Co., Amoco Production Co., Third-Party v. Technical Compression Services, Inc., Third-Party) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jimmie Joseph Johnson v. Amoco Production Co., Amoco Production Co., Third-Party v. Technical Compression Services, Inc., Third-Party, 5 F.3d 949, 1993 U.S. App. LEXIS 28709, 1993 WL 413855 (3d Cir. 1993).

Opinion

PER CURIAM:

This third-party indemnity action arises out of an injury that occurred at Amoco Production Co.’s (“Amoco”) Chalybeat Springs oil and gas production facility. The injured party and plaintiff in the principal action, Jimmie Joseph Johnson, brought a tort claim in diversity against Amoco, the Third-Party Plaintiff-Appellee in the instant case. Amoco in turn filed a third-party demand against the injured party’s asserted employer, Third-Party Defendant-Appellant Technical Compression Services, Inc. (“TCS”). The third-party demand was *951 premised on the notion that TCS owed Amoco defense and indemnification for its employee, Johnson, according to the master contract between TCS and Amoco. Amoco argued that Johnson was an employee of TCS as defined in the indemnification provision in that master contract, and that the Louisiana Oilfield Anti-Indemnity Act (“LO-ALA”) 1 did not render the indemnification provision unenforceable. The district court agreed and entered summary judgment for Amoco. Finding no error, we affirm.

I

FACTS AND PROCEEDINGS

In September 1990, Johnson was injured while installing and adjusting an engine and compressor at Amoeo’s facility in Chalybeat Springs, Arkansas. 2 The Amoco facility where Johnson was injured processes oil and gas produced from thirty-one Amoco wells located nearby. All thirty-one wells are connected to that facility by a gathering system consisting of one gathering line into which each well connects. At the facility, that line feeds into a separator which separates the oil from the gas. The gas then goes through an inlet scrubber, then through a glycol unit, and finally through a compressor at the compressor station where Johnson was injured. The compressed gas leaves the facility in a transmission pipeline that feeds into a United Gas Pipeline trunk line approximately ten miles away.

The work in which Johnson was engaged at the Amoco facility was undertaken by TCS pursuant to a work order issued by Amoco to rebuild and install an engine and compressor. This work order in turn was governed by a master contract between Amoco and TCS entered into in May 1984. 3 This contract includes an indemnification provision that provides in pertinent part:

Contractor [TCS] assumes all liability for and hereby agrees to defend, indemnify and hold Amoco, its joint owner or owners, if any, and their insurers, harmless from and against any and all losses, costs, expenses and causes of action, including attorney’s fees and court costs, for injuries to and death of Contractor’s and its Subcontractor’s employees, arising out of, incident to, or in connection with any and all operations under this contract ...

After it was sued by Johnson, Amoco im-pleaded TCS, maintaining that, as Johnson was an employee of TCS within the meaning of' the indemnification provision, TCS was liable for defense and indemnification under that provision. In the main action — Johnson’s tort claim — Amoco successfully argued to the district court that it (Amoco) was Johnson’s statutory employer, thereby barring that claim under Louisiana’s worker’s compensation law. 4

Having succeeded in avoiding tort liability to Johnson, 5 ’Amoco next moved for summary judgment on its indemnity and defense claim against TCS. In opposing that motion, TCS advanced two defenses. 6 First, TCS argued that Amoeo’s status as Johnson’s statutory employer excluded him from coverage under the indemnity agreement as it only applies to “employees” of TCS. Second, TCS claimed that the LOAIA rendered the indemnity provision unenforceable as applied to Johnson’s claim because the work order that Johnson was executing fell within the coverage of that act. According to TCS, the work order for *952 equipment at the compressor station “pertained to a 1 well” as required by the LOAIA.

The district court disagreed with TCS’s contentions. The court first reasoned that statutorily identifying a party as an employer for tort immunity purposes in a state’s worker’s compensation system does not necessarily control the definition of the term “employee” as it is used in a contract. Rather, the court looked to the contractual intent of the parties and concluded that the indemnity provision unambiguously applied to TCS’s actual or payroll employees, among whom Johnson was one. Next, the court concluded that the contract at issue — the work order to rebuild and replace the engine and compressor located at the compressor station within Amoco’s facility — did not “pertain to a well” because the gas at that point could no longer be identified with a particular well. By the time the gas reached the compressor station it had been commingled and undergone substantial processing to prepare it for transmission and distribution, so that it was no longer identifiable with any given well. Thus, concluded the district court, the indemnification provision of the contract was not rendered unenforceable by the LOAIA. Accordingly, the district court entered summary judgment for Amoco for its costs and expenses in defending against the suit by Johnson, which totaled $27,932.65. TCS timely appealed.

II

STANDARD OF REVIEW

We review the district court’s grant of summary judgment by “reviewing the record under the same standards which guided the district court.” 7 A grant of summary judgment is proper when no issue of material fact exists that would necessitate a trial. 8 We affirm a grant of summary judgment when “ Ve are convinced, after an independent review of the record, that “there is no genuine issue of material fact” and that the mov-ant is “entitled to a judgment as a matter of law.” ’ ” 9 In determining whether the grant was proper, all fact questions are viewed in the light most favorable to the nonmovant. Questions of law, however, are decided as they are outside of the summary judgment context:, de novo. 10

Ill

DÍSCUSSION

The facts underlying this indemnity claim are not in dispute. Summary judgment is thus an appropriate vehicle with which to dispose of this claim. On appeal, TCS contends that the district court erred in concluding that Johnson was an “employee” of TCS under the indemnity agreement. TCS alternatively contends that, even if Johnson were such an employee, the district court erred in concluding that the LOAIA did not render this agreement unenforceable as applied to Johnson’s, claim. We analyze each contention in turn.

A. Meaning of “Employee” in the Master Contract

TCS argues that Amoco’s status as Johnson’s “statutory employer” removes Johnson from the ambit of the indemnification provision.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
5 F.3d 949, 1993 U.S. App. LEXIS 28709, 1993 WL 413855, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jimmie-joseph-johnson-v-amoco-production-co-amoco-production-co-ca3-1993.