Jimenez v. Gilbane Building Co.

693 S.E.2d 126, 303 Ga. App. 125, 2010 Fulton County D. Rep. 1053, 2010 Ga. App. LEXIS 299
CourtCourt of Appeals of Georgia
DecidedMarch 25, 2010
DocketA09A2061
StatusPublished
Cited by8 cases

This text of 693 S.E.2d 126 (Jimenez v. Gilbane Building Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jimenez v. Gilbane Building Co., 693 S.E.2d 126, 303 Ga. App. 125, 2010 Fulton County D. Rep. 1053, 2010 Ga. App. LEXIS 299 (Ga. Ct. App. 2010).

Opinion

Adams, Judge.

The issue in this case is whether a plumbing subcontractor is liable as a matter of law for indemnification to the plumbing *126 contractor for whom he worked for the damages arising from a pipe failure. The background facts are that Gilbane Building Company was the general contractor for the construction of a new dormitory at Georgia Southern University. Gilbane hired Gill Plumbing as the plumbing contractor, and Gill Plumbing, in turn, hired Jose Alfredo Jimenez to perform plumbing installation work. The building was completed in July 2005, but in October, after the dormitory was occupied by students, a pipe failed causing extensive water damage to the dormitory and to some students’ personal belongings. Gilbane was forced to hire Belfor USA Group, Inc. to perform remediation and repair work. Belfor’s $990,060.63 bill for the services has not been paid.

Belfor filed this action against Gilbane, Gilbane filed a third-party action against Gill Plumbing, and Gill Plumbing filed a fourth-party action against Jimenez. The parties have since been realigned. Currently, both Belfor and Gilbane have claims against Gill Plumbing, and Gill Plumbing has a third-party claim against Jimenez for the costs of the remediation and repair.

In its third-party claim, Gill Plumbing asserts that it had a written agreement with Jimenez that included an indemnity agreement, and that the damages to the dormitory resulted from negligent work performed by Jimenez. Jimenez denied that he entered into a valid and enforceable contract or an indemnity agreement with Gill Plumbing and denied the negligence. The trial court granted Gill’s motion for partial summary judgment against Jimenez, finding that he was liable “for indemnification to Gill Plumbing” “in the amount, if any, of damages proven to have resulted from Mr. Jimenez’s defective work.” Jimenez appeals this ruling and contends that “no contract existed between Mr. Jimenez and the Appellee as a matter of law” or, at least, that there are material issues of fact regarding the contract and the indemnity agreement.

Summary judgment is proper when there is no genuine issue of material fact and the movant is entitled to judgment as a matter of law. OCGA § 9-11-56 (c). We review a grant or denial of summary judgment de novo and construe the evidence in the light most favorable to the nonmovant. Home Builders Assn. &c. v. Chatham County, 276 Ga. 243, 245 (1) (577 SE2d 564) (2003).

There is no question that the parties had an oral agreement. The issue before us is whether there was an enforceable written agreement and, if so, what were the terms of that agreement. The undisputed facts show that Jimenez was hired by Gill Plumbing to perform plumbing services in the “Eagle Village” construction project at Georgia Southern University, that he performed plumbing services, and that he has been paid for the work in the amount of $167,000.

*127 Jimenez has never worked for any company other than Gill Plumbing and the two have worked together for at least fifteen years. On September 15, 2004, Jimenez signed two documents, which, Gill Plumbing contends, constitute the parties’ entire written agreement; Jimenez has signed other documents for Gill Plumbing in the past. The first document is contained on one page, it is dated September 15, 2004, and it has Jimenez’s typewritten name and his signature. The main body of the document is as follows:

LABOR CONTRACT
Project: Eagle Village.
Item 1 Slab 50,100.00
Item 2 Rough 66,800.00
Item 3 Set Out 50,100.00
— Weekly billing to be submitted in draw format.
All work must be approved by Larry Pollett.
— Weekly safety meetings must be attended. Sub required to attend all jobsite agenda & safety meetings.
— Subs required to comply with all general contractor regulations & jobsite regulations.
— All Subs required to provide certificate of insurance with adequate coverages per limits set by general contractor.
— Subs are required to honor subcontractor Warranty for labor & installation free of all defects for a period of (1) [sic] year from date of substantial completion.
Subs agree & abide by all terms in the attached Exhibit “A” for insurance & indemnity.
Total Contract Amount $ 167,000.00

(Emphasis supplied.) Jimenez’s signature appears below the following words, which are written on the side of the above chart:

Sub-Labor
Affidavit
I certify the work for which above payment is requested has been completed according to the plans and specifications and in compliance with the terms of our contract and all labor and material bills applicable to this job have been paid to date and that Federal income, social security, and unemployment taxes have been withheld and will be paid when due on all employees employed by me on this job.
________/s/_______
CONTRACTOR

*128 Notably, this first document does not name Gill Plumbing anywhere, and the “affidavit” is written in the past tense, as if the project had already been completed; but as of the date on the document, Jimenez’s work at Eagle Village had not begun. The second document — “Exhibit A” — is two pages long, and it begins as follows:

INSURANCE AND INDEMNITY SUBCONTRACTOR AGREEMENT
The Work performed by the Subcontractor shall be at the risk of the Subcontractor exclusively. To the fullest extent permitted by law, Subcontractor shall indemnify, defend (at Subcontractor’s sole expense) and hold harmless Contractor, the Owner (if different from Contractor), affiliated companies of Contractor, . . . from and against any and all claims for . . . damage to property . . . which arise or are in any way connected with the Work performed, Materials furnished, or Services provided under this Agreement by Subcontractor or its agents....

The exhibit goes on to require the “Subcontractor” to obtain commercial general liability insurance in the amount of $1,000,000, and to meet other related requirements. The exhibit is signed by Jimenez on the second page over the word “Subcontractor,” but it is not dated. Also, the document does not include Gill Plumbing’s name anywhere. Finally, Jimenez never performed any work at Eagle Village that could be called “Set Out” as stated on page one of the document.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bath v. Int'l Paper Co.
807 S.E.2d 64 (Court of Appeals of Georgia, 2017)
ROBERTS Et Al. v. SMITH
801 S.E.2d 915 (Court of Appeals of Georgia, 2017)
Maxum Indemnity Company v. Jose Jimenez
Court of Appeals of Georgia, 2012
Maxum Indemnity Co. v. Jimenez
734 S.E.2d 499 (Court of Appeals of Georgia, 2012)
Lufthansa Systems Infratec GmbH v. Wi-Sky Inflight, Inc.
894 F. Supp. 2d 677 (E.D. Virginia, 2012)
GILL PLUMBING CO. v. Jimenez
714 S.E.2d 342 (Court of Appeals of Georgia, 2011)
Fred's Stores of Tennessee, Inc. v. Davenport
703 S.E.2d 700 (Court of Appeals of Georgia, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
693 S.E.2d 126, 303 Ga. App. 125, 2010 Fulton County D. Rep. 1053, 2010 Ga. App. LEXIS 299, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jimenez-v-gilbane-building-co-gactapp-2010.