GILL PLUMBING CO. v. Jimenez

714 S.E.2d 342, 310 Ga. App. 863
CourtCourt of Appeals of Georgia
DecidedJune 16, 2011
DocketA11A0607, A11A0608
StatusPublished
Cited by10 cases

This text of 714 S.E.2d 342 (GILL PLUMBING CO. v. Jimenez) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
GILL PLUMBING CO. v. Jimenez, 714 S.E.2d 342, 310 Ga. App. 863 (Ga. Ct. App. 2011).

Opinion

Barnes, Presiding Judge.

This is the second appearance of this contractual indemnity case before this court. See Jimenez v. Gilbane Bldg. Co., 303 Ga. App. 125 (693 SE2d 126) (2010). On remand from the first appeal, a jury trial was held that addressed, among other things, whether and to what extent a plumbing subcontractor was required to indemnify a plumbing contractor for damages resulting from a burst pipe. Using *864 a special verdict form, the jury found that the parties had entered into a valid written contract that included an indemnity agreement and awarded the plumbing contractor damages in the amount of $191,382.01. The trial court entered judgment on the verdict, leading to these companion appeals.

In Case No. A11A0607, the plumbing contractor, Gill Plumbing Company, contends that the trial court erred in refusing to enter a judgment that molded the verdict to correct an alleged illegality and inconsistency in the damages award. In Case No. A11A0608, the plumbing subcontractor, Jose Alfredo Jimenez, contends that the trial court erred in denying his motion for a directed verdict on Gill Plumbing’s indemnity claim because the evidence purportedly failed to show that the parties entered into a valid written contract. For the reasons discussed below, we affirm in both appeals.

The record shows that Gilbane Building Company was the general contractor for the construction of a dormitory at Georgia Southern University. Gilbane hired Gill Plumbing as the plumbing contractor. Gill Plumbing then subcontracted with Jimenez to install the pipes in the slab floor and walls of the dormitory.

After the dormitory was completed and occupied by students, a pipe in one of the walls burst, causing water to flood the residential housing units on three levels of the building. The flooding caused extensive structural damage to the units and significant mold growth. Students who had been living at the dormitory were displaced to a nearby hotel for several weeks, and the university deducted the costs associated with housing them from what it owed to Gilbane for the project.

Gilbane hired Belfor USA Group, Inc. to perform the structural repair work and the mold remediation of the dormitory. Belfor completed the repair and remediation of the dormitory and submitted a final bill to Gilbane in the amount of $990,060.63.

When its repair bill was not paid, Belfor sued Gilbane for breach of contract and other claims. Asserting a contractual right of indemnity for damages resulting from the burst pipe, Gilbane brought Gill Plumbing into the case as a third-party defendant. Gill Plumbing ultimately admitted liability under its indemnity agreement with Gilbane, but disputed the amount that it owed. Gilbane assigned its indemnity claim against Gill Plumbing to Belfor, and the parties were realigned. Belfor, on its own behalf and as assignee of Gilbane, then proceeded against Gill Plumbing directly for the costs of the mold remediation, dormitory repairs, and housing of the university students, plus prejudgment interest and attorney fees.

Gill Plumbing brought Jimenez into the case as a fourth-party defendant, alleging that it had a written contract with him that included an indemnity agreement. Its contractual indemnity claim *865 against Jimenez was based on two documents, both of which were undisputedly signed by him. The first document, entitled “Labor Contract,” contained several provisions relating to the dormitory project and made reference to the terms of an “attached Exhibit ‘A.’ ” The second document, entitled “Exhibit A: Insurance and Indemnity Subcontractor Agreement” (the “Indemnity Provision”), provided in relevant part:

The Work performed by the Subcontractor shall be at the risk of the Subcontractor exclusively. To the fullest extent permitted by law, Subcontractor shall indemnify, defend (at Subcontractor’s sole expense) and hold harmless Contractor, the Owner (if different from Contractor), affiliated companies of Contractor, . . . from and against any and all claims for . . . damage to property . . . which arise or are in any way connected with the Work performed, Materials furnished, or Services provided under this Agreement by Subcontractor or its agents. These indemnity and defense obligations shall apply to any acts or omissions, negligent or willful misconduct of Subcontractor, its employees or agents, whether active or passive. Said indemnity and defense obligations shall further apply, whether or not said claims arise out of the concurrent act, omission, or negligence of the Indemnified Parties, whether active or passive. Subcontractor shall not be obligated to indemnify and defend Contractor or Owner for claims found to be due to the sole negligence or willful misconduct of Indemnified Parties.

Gill Plumbing moved for and was granted partial summary judgment on its contractual indemnity claim against Jimenez. The trial court’s order granting partial summary judgment to Gill Plumbing was reversed on the first appeal to this court. See Jimenez, 303 Ga. App. at 130. We held that a jury had to resolve whether the parties had entered into an enforceable written contract that included an indemnity agreement and, if so, what were the contractual terms. Id. at 129-130.

On remand, the claims of the parties, including Gill Plumbing’s contractual indemnity claim against Jimenez, were tried before a jury. There was no dispute that Gill Plumbing and Jimenez had an oral agreement under which Jimenez agreed to install the pipes in the slab floor and walls of the dormitory in return for $167,000. Rather, the primary questions for the jury were whether the parties had agreed to a written contract that included an indemnity agreement, and, if so, whether and to what extent Jimenez was liable to *866 Gill Plumbing for damages caused by the burst pipe.

At the close of the evidence, Jimenez moved for a directed verdict on the issue of the existence of a written contract that included an indemnity agreement. Jimenez contended that the two documents relied upon by Gill Plumbing, the Labor Contract and the Indemnity Provision, were unenforceable as a written contract because they lacked essential terms and there was no meeting of the minds or mutual assent to the terms of the contract. The trial court took the motion under advisement and allowed the case to go to the jury.

The jury subsequently entered a two-part special verdict. In section one of the special verdict, the jury found that Belfor, for itself and as assignee of Gilbane, was owed a combined total of $864,746.51 in damages from Gill Plumbing as a result of the burst pipe. In section two of the special verdict, the jury found that there was a written contract between Gill Plumbing and Jimenez that included indemnification for the dormitory project; that Gill Plumbing was not solely negligent in causing the damage to the dormitory; and that Jimenez was at fault for causing damage to the dormitory. However, the jury in section two of the special verdict went on to find that Jimenez owed contractual indemnity to Gill Plumbing only in the amount of $191,382.01 for the burst pipe.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

TACTICAL SECURITY GROUP, LLC v. CYNTHIA WELCH
Court of Appeals of Georgia, 2024
BARRY N. STRAUS v. RENASANT BANK
Court of Appeals of Georgia, 2014
Straus v. Renasant Bank
756 S.E.2d 340 (Court of Appeals of Georgia, 2014)
Kaufman Development Partners, L.P. v. Eichenblatt
749 S.E.2d 374 (Court of Appeals of Georgia, 2013)
Patterson v. Long
741 S.E.2d 242 (Court of Appeals of Georgia, 2013)
Maxum Indemnity Company v. Jose Jimenez
Court of Appeals of Georgia, 2012
Maxum Indemnity Co. v. Jimenez
734 S.E.2d 499 (Court of Appeals of Georgia, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
714 S.E.2d 342, 310 Ga. App. 863, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gill-plumbing-co-v-jimenez-gactapp-2011.