Jim Waller v. Sabine River Authority of Texas

Court of Appeals of Texas·Decided December 6, 2018·No. 09-18-00040-CV·Published

Opinion

In The

Court of Appeals

Ninth District of Texas at Beaumont

NO. 09-18-00040-CV

JIM WALLER, ET AL., Appellants V.

SABINE RIVER AUTHORITY OF TEXAS, Appellee

On Appeal from the 163rd District Court Orange County, Texas

Trial Cause No. B160341-C

MEMORANDUM OPINION

Following a historic flooding event in March of 2016, Jim Waller, along with approximately one hundred other landowners downstream from the Toledo Bend Reservoir and Dam (“Appellants”), sued the Sabine River Authority of Texas (SRA- T) for inverse condemnation, private nuisance, and trespass to real property. SRA-T filed a plea to the jurisdiction asserting governmental immunity. SRA-T argued that governmental immunity had not been waived as Appellants could not establish

causation, could not establish the requisite mens rea for a takings claim, and Appellants’ claims were preempted by federal law. Following two separate hearings, the trial court granted SRA-T’s plea and dismissed all claims. In three issues on appeal, Waller argues the judgment must be reversed and the cause remanded for trial because: (1) the Supreme Court of the United States has held in Arkansas Game and Fish Commission v. United States1 that a temporary flooding event can rise to the level of a governmental taking; (2) the trial court improperly applied a field preemption analysis when conflict preemption analysis was the correct standard; and (3) the evidence established causation, thus waiving government immunity. After careful consideration, we affirm the trial court’s judgment.

I. Background

The SRA-T and Sabine River Authority of Louisiana (SRA-L) jointly operate the Toledo Bend Project (Project), a hydroelectric power plant governed by the Federal Power Act (FPA). The 81-megawatt Project is located on the Sabine River at the Texas-Louisiana border. The Project includes a dam, reservoir, spillway, powerhouse, tailrace channel, station transformer, and a transmission line. The Project is operated pursuant to a Federal Energy Regulatory Commission (FERC) license. The original fifty-year license for the Project was issued in 1963. In

1 568 U.S. 23 (2012).

September 2011, before SRA-T’s original license expired, SRA-T and SRA-L sought to renew their license to operate the Project. The federal government issued the new license, which covered a period of fifty years, in August 2014.

In connection with the licensing renewal process, FERC released a Draft and Final Environmental Impact Statement for Hydropower License (EIS). FERC released its draft EIS in June 2013. Afterwards, in July 2013, FERC held public meetings in Orange, Texas, and in Many, Louisiana, to address questions about its regulations that control SRA-T’s and SRA-L’s operation of the Project, which included questions about flood control. In the EIS, FERC explained:

Flooding has occurred downstream of the Toledo Bend Project along the Sabine River, and several downstream residents recommend changes to current reservoir operations such as pre-releasing flows prior to storm events or drawing down the project reservoir.

The size of the reservoir and current project operations provide some incidental flood control, but substantially lower reservoir levels associated with dedicated flood control operations, as recommended by downstream residents, would have adverse effects on water supply, power production, and recreational use and could conceivably exacerbate downstream flooding if rainfall from a predicted storm falls predominantly downstream of the dam.

In December 2013, FERC released its final version of the EIS. In it, FERC noted that “the [P]roject was built for the primary purposes of water supply and secondary purposes of hydroelectric power generation and recreation.”

During the process to renew the Project’s license, residents who live downstream of the Toledo Bend Dam presented their suggestions about changing the regulations governing the operation of the Project. They suggested changing the regulations so that SRA-T could lower Toledo Bend Reservoir from its usual minimum level of 168-172 feet mean sea level (msl) to 165–167 msl, and that SRA- T be authorized to release water in anticipation of events that might cause land downstream of the reservoir to flood. But in its final EIS, FERC stated “that there has (sic) been some flood storage benefits associated with operation of the project,” and “found that the ability to efficiently practice pre-releases from the reservoir to lower the reservoir level before a flood[] is limited by key factors[,]” including the accuracy of rainfall predictions, the limited amount of water that could be pre- released without causing flooding, the time required to lower the reservoir, the long lag/travel time of flows, the effects of tributary inflow below the dam, and the common occurrence of high inflows and high reservoir levels before most events that had resulted in floods. The EIS also notes that SRA-T and SRA-L had taken measures to improve their ability to notify the public about the potential that areas downstream from the Project could flood.

During the 2003, FERC declined another request made by the residents who live downstream of the Toledo Bend Reservoir to amend the regulations governing

SRA-T’s operation of the Project to allow the Project’s mission to include lowering the reservoir level and pre-releasing water for the purpose of mitigating the damages that result during floods. In a letter dated November 24, 2003, FERC stated:

The Toledo Bend Dam was not designed as a flood control dam.

Review of historical flood-flow data indicates that the construction and operation of the Toledo Bend Dam has not increased the incidence of downstream flooding. In some flood events, the dam has been beneficial by delaying the flood flows by temporarily storing a portion of the flood inflow in the reservoir. The ability of the project to pre-

release flow to obtain significant reservoir storage in anticipation of high inflows is severely limited by the downstream development, particularly [in] Deweyville, Texas. Therefore, to obtain flood control benefits, operation of the project would need to be changed to permanently lower the project reservoir level to provide flood control storage. Significantly lowering the reservoir to the extent necessary to provide appreciable flood control benefits would adversely impact the established reservoir recreation activities and power development.

While citizens made a similar request during the process involved in the renewal of SRA-T’s license, FERC declined to amend the regulations to change the Project’s goals to include using the dam on the Project to mitigate the effects inflicted on downstream residents by floods.

On March 9 and March 10, 2016, a historic rainfall event occurred in East Texas, which included areas upstream and downstream of the Toledo Bend Dam. Some of the communities near the Project received twenty to twenty-five inches of rain in a thirty-one-hour period. For example, the southern portion of the Project and the area immediately downstream received record or near-record rain. The large

amount of rain experienced in East Texas in March 2016 resulted in floods on the lower Sabine River and its downstream tributaries.

The Project notified the public that water would be released from the Toledo Bend Dam at 7:00 a.m. on Wednesday, March 9, 2016, when the reservoir rose to 172.27 feet msl. During the height of the March 2016 storm, the peak inflows measured for the Toledo Bend Reservoir exceeded 600,000 cubic feet per second (cfs), and the peak discharge was 207,644 cfs. The tributaries of the Sabine River, downstream from the Toledo Bend Dam, were recorded as having been at near- record or record levels during the storm.

Free access — add to your briefcase to read the full text and ask questions with AI

Jim Waller v. Sabine River Authority of Texas, (Tex. Ct. App. 2018).

Jim Waller v. Sabine River Authority of Texas (Jim Waller v. Sabine River Authority of Texas) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

California v. Federal Energy Regulatory Commission
495 U.S. 490 (Supreme Court, 1990)
Ingrid Fisher v. Halliburton
667 F.3d 602 (Fifth Circuit, 2012)
Kurns v. Railroad Friction Products Corp.
132 S. Ct. 1261 (Supreme Court, 2012)
Arizona v. United States
132 S. Ct. 2492 (Supreme Court, 2012)
Arkansas Game & Fish Commission v. United States
133 S. Ct. 511 (Supreme Court, 2012)
Texas Department of Parks & Wildlife v. Miranda
133 S.W.3d 217 (Texas Supreme Court, 2004)
City of Dallas v. Jennings
142 S.W.3d 310 (Texas Supreme Court, 2004)
Texas Department of Transportation v. City of Sunset Valley
146 S.W.3d 637 (Texas Supreme Court, 2004)
State v. Holland
221 S.W.3d 639 (Texas Supreme Court, 2007)
Graber v. Fuqua
279 S.W.3d 608 (Texas Supreme Court, 2009)
City of Waco v. Kirwan
298 S.W.3d 618 (Texas Supreme Court, 2009)
Jeff Simmons v. Sabine River Authority, et
732 F.3d 469 (Fifth Circuit, 2013)
Whitten v. Vehicle Removal Corp.
56 S.W.3d 293 (Court of Appeals of Texas, 2001)
Bland Independent School District v. Blue
34 S.W.3d 547 (Texas Supreme Court, 2000)
City of Houston v. Crabb
905 S.W.2d 669 (Court of Appeals of Texas, 1995)
Burlington Northern & Santa Fe Railway Co. v. City of Houston
171 S.W.3d 240 (Court of Appeals of Texas, 2005)
Dallas Area Rapid Transit v. Whitley
104 S.W.3d 540 (Texas Supreme Court, 2003)
Great Dane Trailers, Inc. v. Estate of Wells
52 S.W.3d 737 (Texas Supreme Court, 2001)
SABINE RIVER AUTHORITY OF TEXAS v. Hughes
92 S.W.3d 640 (Court of Appeals of Texas, 2002)
General Services Commission v. Little-Tex Insulation Co.
39 S.W.3d 591 (Texas Supreme Court, 2001)