Jim Waller v. Sabine River Authority of Texas

CourtCourt of Appeals of Texas
DecidedDecember 6, 2018
Docket09-18-00040-CV
StatusPublished

This text of Jim Waller v. Sabine River Authority of Texas (Jim Waller v. Sabine River Authority of Texas) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jim Waller v. Sabine River Authority of Texas, (Tex. Ct. App. 2018).

Opinion

In The

Court of Appeals

Ninth District of Texas at Beaumont

_________________

NO. 09-18-00040-CV _________________

JIM WALLER, ET AL., Appellants

V.

SABINE RIVER AUTHORITY OF TEXAS, Appellee ________________________________________________________________________

On Appeal from the 163rd District Court Orange County, Texas Trial Cause No. B160341-C ________________________________________________________________________

MEMORANDUM OPINION

Following a historic flooding event in March of 2016, Jim Waller, along with

approximately one hundred other landowners downstream from the Toledo Bend

Reservoir and Dam (“Appellants”), sued the Sabine River Authority of Texas (SRA-

T) for inverse condemnation, private nuisance, and trespass to real property. SRA-T

filed a plea to the jurisdiction asserting governmental immunity. SRA-T argued that

governmental immunity had not been waived as Appellants could not establish 1 causation, could not establish the requisite mens rea for a takings claim, and

Appellants’ claims were preempted by federal law. Following two separate hearings,

the trial court granted SRA-T’s plea and dismissed all claims. In three issues on

appeal, Waller argues the judgment must be reversed and the cause remanded for

trial because: (1) the Supreme Court of the United States has held in Arkansas Game

and Fish Commission v. United States1 that a temporary flooding event can rise to

the level of a governmental taking; (2) the trial court improperly applied a field

preemption analysis when conflict preemption analysis was the correct standard; and

(3) the evidence established causation, thus waiving government immunity. After

careful consideration, we affirm the trial court’s judgment.

I. Background

The SRA-T and Sabine River Authority of Louisiana (SRA-L) jointly operate

the Toledo Bend Project (Project), a hydroelectric power plant governed by the

Federal Power Act (FPA). The 81-megawatt Project is located on the Sabine River

at the Texas-Louisiana border. The Project includes a dam, reservoir, spillway,

powerhouse, tailrace channel, station transformer, and a transmission line. The

Project is operated pursuant to a Federal Energy Regulatory Commission (FERC)

license. The original fifty-year license for the Project was issued in 1963. In

1 568 U.S. 23 (2012). 2 September 2011, before SRA-T’s original license expired, SRA-T and SRA-L

sought to renew their license to operate the Project. The federal government issued

the new license, which covered a period of fifty years, in August 2014.

In connection with the licensing renewal process, FERC released a Draft and

Final Environmental Impact Statement for Hydropower License (EIS). FERC

released its draft EIS in June 2013. Afterwards, in July 2013, FERC held public

meetings in Orange, Texas, and in Many, Louisiana, to address questions about its

regulations that control SRA-T’s and SRA-L’s operation of the Project, which

included questions about flood control. In the EIS, FERC explained:

Flooding has occurred downstream of the Toledo Bend Project along the Sabine River, and several downstream residents recommend changes to current reservoir operations such as pre-releasing flows prior to storm events or drawing down the project reservoir.

The size of the reservoir and current project operations provide some incidental flood control, but substantially lower reservoir levels associated with dedicated flood control operations, as recommended by downstream residents, would have adverse effects on water supply, power production, and recreational use and could conceivably exacerbate downstream flooding if rainfall from a predicted storm falls predominantly downstream of the dam.

In December 2013, FERC released its final version of the EIS. In it, FERC

noted that “the [P]roject was built for the primary purposes of water supply

and secondary purposes of hydroelectric power generation and recreation.”

3 During the process to renew the Project’s license, residents who live

downstream of the Toledo Bend Dam presented their suggestions about changing

the regulations governing the operation of the Project. They suggested changing the

regulations so that SRA-T could lower Toledo Bend Reservoir from its usual

minimum level of 168-172 feet mean sea level (msl) to 165–167 msl, and that SRA-

T be authorized to release water in anticipation of events that might cause land

downstream of the reservoir to flood. But in its final EIS, FERC stated “that there

has (sic) been some flood storage benefits associated with operation of the project,”

and “found that the ability to efficiently practice pre-releases from the reservoir to

lower the reservoir level before a flood[] is limited by key factors[,]” including the

accuracy of rainfall predictions, the limited amount of water that could be pre-

released without causing flooding, the time required to lower the reservoir, the long

lag/travel time of flows, the effects of tributary inflow below the dam, and the

common occurrence of high inflows and high reservoir levels before most events

that had resulted in floods. The EIS also notes that SRA-T and SRA-L had taken

measures to improve their ability to notify the public about the potential that areas

downstream from the Project could flood.

During the 2003, FERC declined another request made by the residents who

live downstream of the Toledo Bend Reservoir to amend the regulations governing

4 SRA-T’s operation of the Project to allow the Project’s mission to include lowering

the reservoir level and pre-releasing water for the purpose of mitigating the damages

that result during floods. In a letter dated November 24, 2003, FERC stated:

The Toledo Bend Dam was not designed as a flood control dam. Review of historical flood-flow data indicates that the construction and operation of the Toledo Bend Dam has not increased the incidence of downstream flooding. In some flood events, the dam has been beneficial by delaying the flood flows by temporarily storing a portion of the flood inflow in the reservoir. The ability of the project to pre- release flow to obtain significant reservoir storage in anticipation of high inflows is severely limited by the downstream development, particularly [in] Deweyville, Texas. Therefore, to obtain flood control benefits, operation of the project would need to be changed to permanently lower the project reservoir level to provide flood control storage. Significantly lowering the reservoir to the extent necessary to provide appreciable flood control benefits would adversely impact the established reservoir recreation activities and power development.

While citizens made a similar request during the process involved in the renewal of

SRA-T’s license, FERC declined to amend the regulations to change the Project’s

goals to include using the dam on the Project to mitigate the effects inflicted on

downstream residents by floods.

On March 9 and March 10, 2016, a historic rainfall event occurred in East

Texas, which included areas upstream and downstream of the Toledo Bend Dam.

Some of the communities near the Project received twenty to twenty-five inches of

rain in a thirty-one-hour period. For example, the southern portion of the Project and

the area immediately downstream received record or near-record rain. The large 5 amount of rain experienced in East Texas in March 2016 resulted in floods on the

Free access — add to your briefcase to read the full text and ask questions with AI

Related

California v. Federal Energy Regulatory Commission
495 U.S. 490 (Supreme Court, 1990)
Ingrid Fisher v. Halliburton
667 F.3d 602 (Fifth Circuit, 2012)
Kurns v. Railroad Friction Products Corp.
132 S. Ct. 1261 (Supreme Court, 2012)
Arizona v. United States
132 S. Ct. 2492 (Supreme Court, 2012)
Arkansas Game & Fish Commission v. United States
133 S. Ct. 511 (Supreme Court, 2012)
Texas Department of Parks & Wildlife v. Miranda
133 S.W.3d 217 (Texas Supreme Court, 2004)
City of Dallas v. Jennings
142 S.W.3d 310 (Texas Supreme Court, 2004)
Texas Department of Transportation v. City of Sunset Valley
146 S.W.3d 637 (Texas Supreme Court, 2004)
State v. Holland
221 S.W.3d 639 (Texas Supreme Court, 2007)
Graber v. Fuqua
279 S.W.3d 608 (Texas Supreme Court, 2009)
City of Waco v. Kirwan
298 S.W.3d 618 (Texas Supreme Court, 2009)
Jeff Simmons v. Sabine River Authority, et
732 F.3d 469 (Fifth Circuit, 2013)
Whitten v. Vehicle Removal Corp.
56 S.W.3d 293 (Court of Appeals of Texas, 2001)
Bland Independent School District v. Blue
34 S.W.3d 547 (Texas Supreme Court, 2000)
City of Houston v. Crabb
905 S.W.2d 669 (Court of Appeals of Texas, 1995)
Burlington Northern & Santa Fe Railway Co. v. City of Houston
171 S.W.3d 240 (Court of Appeals of Texas, 2005)
Dallas Area Rapid Transit v. Whitley
104 S.W.3d 540 (Texas Supreme Court, 2003)
Great Dane Trailers, Inc. v. Estate of Wells
52 S.W.3d 737 (Texas Supreme Court, 2001)
SABINE RIVER AUTHORITY OF TEXAS v. Hughes
92 S.W.3d 640 (Court of Appeals of Texas, 2002)
General Services Commission v. Little-Tex Insulation Co.
39 S.W.3d 591 (Texas Supreme Court, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
Jim Waller v. Sabine River Authority of Texas, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jim-waller-v-sabine-river-authority-of-texas-texapp-2018.