NOT PRECEDENTIAL
UNITED STATES COURT OF APPEALS FOR THE THIRD CIRCUIT _______________
No. 23-2450 _______________
JIANGSU BEIER DECORATION MATERIALS CO., LTD., Appellant
v.
ANGLE WORLD LLC
________________
On Appeal from the United States District Court for the Eastern District of Pennsylvania (D.C. Civil No. 2:21-cv-02845) District Judge: Honorable Anita B. Brody _______________
Submitted Under Third Circuit L.A.R. 34.1(a) on May 24, 2024
Before: RESTREPO, FREEMAN, and MCKEE, Circuit Judges.
(Opinion filed: August 8, 2024) _______________
OPINION * _______________
* This disposition is not an opinion of the full Court and, under I.O.P. 5.7, is not binding precedent. FREEMAN, Circuit Judge.
After a remand from this Court, Jiangsu Beier Decoration Materials Co., Ltd.
renewed its petition to confirm its foreign arbitration award against Appellee Angle
World LLC. The District Court concluded that the parties did not agree to arbitrate, so it
denied the renewed petition. Jiangsu appealed, and we will affirm the District Court’s
order.
I
A
Jiangsu is a China-based flooring products manufacturer. Angle World was the
exclusive distributor of certain Jiangsu flooring products in Pennsylvania and several
other states.
In June 2018, Jiangsu asserted that Angle World owed it more than $1.3 million
for inventory Jiangsu had already delivered. Angle World disputed that amount, and the
parties attempted to settle their differences. On June 28, the parties entered into a
Memorandum of Understanding (“the June MOU”), under which Angle World agreed to
pay Jiangsu a total of $528,227.59 over a six-month period, with $50,000 of that amount
due the day after the execution of the agreement. The June MOU did not contain an
arbitration clause. Angle World did not make the $50,000 execution payment, but the
parties continued to negotiate a resolution to their dispute.
On July 3, 2018, Angle World’s accountant emailed a Jiangsu representative a
revised payment schedule that required Angle World to make six monthly payments of
$87,000 between July and December 2018, and eliminated the execution payment. A
2 representative of Angle World replied to add that the payment schedule “will be [an]
attachment to our agreement as discussed.” App. 88.
Sometime between July 10 and July 19, 2018, a Jiangsu representative sent an
Angle World representative a revised proposed agreement (the “July MOU”). The July
MOU attached the July 3 payment schedule with revised payment dates and included an
arbitration clause requiring any dispute arising from the agreement to be arbitrated before
the China International Economic and Trade Arbitration Commission (CIETAC). The
July MOU also included a provision stating that the MOU “shall enter into force upon
sealing of the two Parties or signatures of authorized representatives of the two Parties.”
App. 72.
Angle World claims that it rejected the proposed July MOU (and, thus, the
arbitration clause) in a July 19 email, in which its representative stated that “[i]t has not
been written in accordance with our negotiation” and declined any further negotiations.
App. 126. By contrast, Jiangsu alleges that the parties finalized the July MOU during a
July 20 meeting, where Angle World’s President placed the company’s corporate seal in
the margin of the document. Then, Jiangsu’s representatives allegedly signed, sealed,
and mailed a copy of the July MOU to Angle World so that Angle World could seal the
document on the signature page. Angle World did not place its seal on the signature
page.
Angle World did not sign the July MOU either. Throughout August and
September 2018, Jiangsu made several requests for it to do so, but Angle World never
complied. After receiving payment reminders and extensions from Jiangsu, Angle World
3 made two installment payments (on July 27 and September 8), but it claims to have paid
in accordance with the June MOU. It made no further payments.
B
In May 2019, Jiangsu commenced arbitration proceedings before CIETAC. Angle
World objected to CIETAC’s jurisdiction, but CIETAC and the Beijing Fourth
Intermediate People’s Court (“the Chinese Court”) determined that the July MOU and its
arbitration clause were enforceable under Chinese law. Following a merits hearing,
CIETAC issued a March 2021 award in favor of Jiangsu, ordering Angle World to pay
$624,227.59 plus interest and attorneys’ fees.
In June 2021, Jiangsu filed its initial petition to confirm the arbitration award in the
District Court pursuant to the Convention on the Recognition and Enforcement of Foreign
Arbitral Awards (the “New York Convention”). Angle World successfully moved to
dismiss the petition on the ground that it never agreed to arbitrate. Jiangsu appealed that
In November 2022, we vacated the order dismissing Jiangsu’s initial petition and
remanded for further proceedings regarding whether there was an agreement to arbitrate.
Jiangsu Beier Decoration Materials Co. v. Angle World LLC, 52 F.4th 554, 562–63 (3d
Cir. 2022) (“Jiangsu”). We also afforded Jiangsu the opportunity to renew its petition. Id.
at 563. Upon remand, Jiangsu filed a renewed petition to confirm the arbitration award,
and the District Court denied it. Jiangsu timely appealed.
4 II
The District Court had jurisdiction under 28 U.S.C. § 1331 and 9 U.S.C § 203, and
we have jurisdiction pursuant to 28 U.S.C. § 1291. “On review of a petition to confirm
an arbitration award, this Court reviews a district court’s factual findings for clear error
and its legal conclusions de novo.” Jiangsu, 52 F.4th at 559 (citing China Minmetals
Materials Imp. & Exp. Co. v. Chi Mei Corp., 334 F.3d 274, 278 (3d Cir. 2003) (“China
Minmetals”)).
III
“Before confirming a foreign award, . . . a district court must independently
assure itself that the parties consented to arbitrate the merits of their underlying dispute.”
Id. (citing China Minmetals, 334 F.3d at 289). In Jiangsu, we explained that “the New
York Convention subjects confirmation petitions thereunder to a burden-shifting
framework[:]”
First, Article IV requires the party seeking “recognition and enforcement” of an award to make a threshold showing by supplying, “at the time of the application,” certified copies of (a) the arbitration award and (b) “the agreement referred to in article II.” Second, Article V permits the party resisting recognition and enforcement to avoid confirmation by furnishing proof of one of five affirmative defenses, including that “the agreement referred to in article II” is invalid “under the law of the country where the award was made.”
Article II, in turn, provides that each signatory country shall recognize an agreement in writing under which the parties [agreed] to submit to arbitration. The treaty defines the phrase “agreement in writing” to include “an arbitral clause in a contract [that is] . . .
Free access — add to your briefcase to read the full text and ask questions with AI
NOT PRECEDENTIAL
UNITED STATES COURT OF APPEALS FOR THE THIRD CIRCUIT _______________
No. 23-2450 _______________
JIANGSU BEIER DECORATION MATERIALS CO., LTD., Appellant
v.
ANGLE WORLD LLC
________________
On Appeal from the United States District Court for the Eastern District of Pennsylvania (D.C. Civil No. 2:21-cv-02845) District Judge: Honorable Anita B. Brody _______________
Submitted Under Third Circuit L.A.R. 34.1(a) on May 24, 2024
Before: RESTREPO, FREEMAN, and MCKEE, Circuit Judges.
(Opinion filed: August 8, 2024) _______________
OPINION * _______________
* This disposition is not an opinion of the full Court and, under I.O.P. 5.7, is not binding precedent. FREEMAN, Circuit Judge.
After a remand from this Court, Jiangsu Beier Decoration Materials Co., Ltd.
renewed its petition to confirm its foreign arbitration award against Appellee Angle
World LLC. The District Court concluded that the parties did not agree to arbitrate, so it
denied the renewed petition. Jiangsu appealed, and we will affirm the District Court’s
order.
I
A
Jiangsu is a China-based flooring products manufacturer. Angle World was the
exclusive distributor of certain Jiangsu flooring products in Pennsylvania and several
other states.
In June 2018, Jiangsu asserted that Angle World owed it more than $1.3 million
for inventory Jiangsu had already delivered. Angle World disputed that amount, and the
parties attempted to settle their differences. On June 28, the parties entered into a
Memorandum of Understanding (“the June MOU”), under which Angle World agreed to
pay Jiangsu a total of $528,227.59 over a six-month period, with $50,000 of that amount
due the day after the execution of the agreement. The June MOU did not contain an
arbitration clause. Angle World did not make the $50,000 execution payment, but the
parties continued to negotiate a resolution to their dispute.
On July 3, 2018, Angle World’s accountant emailed a Jiangsu representative a
revised payment schedule that required Angle World to make six monthly payments of
$87,000 between July and December 2018, and eliminated the execution payment. A
2 representative of Angle World replied to add that the payment schedule “will be [an]
attachment to our agreement as discussed.” App. 88.
Sometime between July 10 and July 19, 2018, a Jiangsu representative sent an
Angle World representative a revised proposed agreement (the “July MOU”). The July
MOU attached the July 3 payment schedule with revised payment dates and included an
arbitration clause requiring any dispute arising from the agreement to be arbitrated before
the China International Economic and Trade Arbitration Commission (CIETAC). The
July MOU also included a provision stating that the MOU “shall enter into force upon
sealing of the two Parties or signatures of authorized representatives of the two Parties.”
App. 72.
Angle World claims that it rejected the proposed July MOU (and, thus, the
arbitration clause) in a July 19 email, in which its representative stated that “[i]t has not
been written in accordance with our negotiation” and declined any further negotiations.
App. 126. By contrast, Jiangsu alleges that the parties finalized the July MOU during a
July 20 meeting, where Angle World’s President placed the company’s corporate seal in
the margin of the document. Then, Jiangsu’s representatives allegedly signed, sealed,
and mailed a copy of the July MOU to Angle World so that Angle World could seal the
document on the signature page. Angle World did not place its seal on the signature
page.
Angle World did not sign the July MOU either. Throughout August and
September 2018, Jiangsu made several requests for it to do so, but Angle World never
complied. After receiving payment reminders and extensions from Jiangsu, Angle World
3 made two installment payments (on July 27 and September 8), but it claims to have paid
in accordance with the June MOU. It made no further payments.
B
In May 2019, Jiangsu commenced arbitration proceedings before CIETAC. Angle
World objected to CIETAC’s jurisdiction, but CIETAC and the Beijing Fourth
Intermediate People’s Court (“the Chinese Court”) determined that the July MOU and its
arbitration clause were enforceable under Chinese law. Following a merits hearing,
CIETAC issued a March 2021 award in favor of Jiangsu, ordering Angle World to pay
$624,227.59 plus interest and attorneys’ fees.
In June 2021, Jiangsu filed its initial petition to confirm the arbitration award in the
District Court pursuant to the Convention on the Recognition and Enforcement of Foreign
Arbitral Awards (the “New York Convention”). Angle World successfully moved to
dismiss the petition on the ground that it never agreed to arbitrate. Jiangsu appealed that
In November 2022, we vacated the order dismissing Jiangsu’s initial petition and
remanded for further proceedings regarding whether there was an agreement to arbitrate.
Jiangsu Beier Decoration Materials Co. v. Angle World LLC, 52 F.4th 554, 562–63 (3d
Cir. 2022) (“Jiangsu”). We also afforded Jiangsu the opportunity to renew its petition. Id.
at 563. Upon remand, Jiangsu filed a renewed petition to confirm the arbitration award,
and the District Court denied it. Jiangsu timely appealed.
4 II
The District Court had jurisdiction under 28 U.S.C. § 1331 and 9 U.S.C § 203, and
we have jurisdiction pursuant to 28 U.S.C. § 1291. “On review of a petition to confirm
an arbitration award, this Court reviews a district court’s factual findings for clear error
and its legal conclusions de novo.” Jiangsu, 52 F.4th at 559 (citing China Minmetals
Materials Imp. & Exp. Co. v. Chi Mei Corp., 334 F.3d 274, 278 (3d Cir. 2003) (“China
Minmetals”)).
III
“Before confirming a foreign award, . . . a district court must independently
assure itself that the parties consented to arbitrate the merits of their underlying dispute.”
Id. (citing China Minmetals, 334 F.3d at 289). In Jiangsu, we explained that “the New
York Convention subjects confirmation petitions thereunder to a burden-shifting
framework[:]”
First, Article IV requires the party seeking “recognition and enforcement” of an award to make a threshold showing by supplying, “at the time of the application,” certified copies of (a) the arbitration award and (b) “the agreement referred to in article II.” Second, Article V permits the party resisting recognition and enforcement to avoid confirmation by furnishing proof of one of five affirmative defenses, including that “the agreement referred to in article II” is invalid “under the law of the country where the award was made.”
Article II, in turn, provides that each signatory country shall recognize an agreement in writing under which the parties [agreed] to submit to arbitration. The treaty defines the phrase “agreement in writing” to include “an arbitral clause in a contract [that is] . . . signed by the parties or contained in an exchange of letters or telegrams.” Reading Articles II and IV together, proof of “the agreement referred to in article II,” i.e., an “agreement in writing,” is an essential prerequisite to the recognition and enforcement of an award under the New York Convention. Jiangsu claims it satisfied this
5 requirement through proof that Angle World agreed to the unsigned July MOU through an “exchange of letters.”
The New York Convention does not define the phrase “exchange of letters.” Fundamentally, such an exchange must at minimum demonstrate an “agreement” between the parties, that is, a manifestation of mutual assent to be bound by a contract containing an arbitration clause. Beyond this uncontroversial statement, however, courts must determine the existence of an agreement by reference to “background principles of . . . contract law,” to the extent those principles do not conflict with the New York Convention.
Id. at 561–62 (internal citations omitted). 1
Applying these guidelines, the District Court began its analysis by evaluating
whether Jiangsu satisfied Article IV’s prerequisites, which incorporate Article II’s written
agreement requirement. The District Court considered the entire record, including the
parties’ declarations, email exchanges, and other documentary evidence. It observed that
the record omitted “any written exchange showing that Angle World affirmatively agreed
to the Proposed July MOU and its arbitration clause.” App. 14. Jiangsu pointed to a
copy of the July MOU that purportedly contained Angle World’s seal in the margin, but
the District Court could not “identify any marks appearing to be the signature or seal of
Wang or any other Angle World representative.” App. 15; see also App. 106. Because
Article II of the New York Convention “prohibits the enforcement of an oral agreement
to arbitrate an international dispute,” Standard Bent Glass Corp. v. Glassrobots Oy, 333
1 In our previous opinion, we were persuaded by then-Judge Alito’s concurrence in China Minmetals, “emphasiz[ing] that a court must reject a confirmation petition if the petitioner fails to satisfy the prerequisites of Article IV—which does incorporate Article II’s written agreement requirement.” Jiangsu, 52 F.4th at 561 n.30 (citing 334 F.3d at 292–94 (Alito, J., concurring)). We thus concluded that “a party must supply proof of a written agreement to obtain enforcement under the New York Convention.” Id. (citing cases).
6 F.3d 440, 449 n.14 (3d Cir. 2003), the District Court concluded that Jiangsu failed to
establish Article IV’s second threshold requirement.
On appeal, Jiangsu makes three arguments, each of which we resolved in our prior
opinion. First, Jiangsu argues that we did not previously address what needs to be proven
with respect to Article IV’s second threshold requirement, and it asserts that the validity
of the parties’ agreement must be assessed under Article V of the New York Convention.
But we explained that Article IV requires an “exchange of letters . . . [that] at minimum
demonstrate . . . a manifestation of mutual assent to be bound by a contract containing an
arbitration clause.” Jiangsu, 52 F.4th at 561 (citing Agreement, Black’s Law Dictionary
(11th ed. 2019)). No such showing was made here. 2 Thus, the District Court properly
resolved this case by determining that Jiangsu failed to meet its burden under Article IV,
without turning to Article V’s affirmative defenses.
Second, Jiangsu contends that the District Court should have applied Chinese law,
rather than Pennsylvania law, when determining whether the agreement to arbitrate was
valid. It points to Article V, which permits a party resisting recognition and enforcement
of an award to assert that the parties’ agreement to arbitrate “is not valid . . . ‘under the
law of the country where the award was made.’” N.Y. Convention, art. V(1)(a). But
Article V’s affirmative defenses are not relevant to Article IV’s threshold analysis. The
2 To the extent that Jiangsu challenges the District Court’s factual findings, it has not demonstrated clear error. It is undisputed that Angle World never signed the July MOU nor sealed the document on its signature page, and we, like the District Court, cannot identify an Angle World seal elsewhere on the document. Jiangsu has not produced any other documentary evidence of Angle World’s affirmative assent to be bound by the July MOU’s arbitration clause.
7 District Court properly applied “background principles of contract law, to the extent
those principles do not conflict with the New York Convention” to “determine the
existence of an agreement.” Jiangsu, 52 F.4th at 561–62 (cleaned up).
Third, Jiangsu argues that the District Court should have granted comity to the
Beijing Court’s holding that the parties have a valid agreement to arbitrate the underlying
dispute. However, we previously held that the District Court had an obligation “to
determine independently the existence of an agreement to arbitrate even though an
arbitration panel in a foreign state already had rendered an award,” id. at 563 (citing
China Minmetals, 334 F.3d at 284), and that “a foreign court is ‘not entitled to comity on
issues the court did not decide,’” id. (quoting Remington Rand Corp.-Delaware v. Bus.
Sys. Inc., 830 F.2d 1260, 1266 (3d Cir. 1987)). Here, the Beijing Court “determined that
the July MOU was enforceable under Chinese domestic law but did not analyze the
separate issues of (a) whether an arbitration award would be subject to confirmation in a
foreign nation under Article IV of the New York Convention or (b) whether the parties’
email exchange satisfies the ‘writing’ requirement of Article II.” Id. As we instructed,
the District Court properly made “an independent determination as to arbitrability.” Id. at
564.
* * *
For the foregoing reasons, we will affirm the District Court’s order denying
Jiangsu’s renewed petition to confirm its arbitration award.