JHC INDUSTRIAL SERVICES, LLC VS. CENTURION COMPANIES, INC. (L-7635-17, BERGEN COUNTY AND STATEWIDE)

New Jersey Superior Court Appellate Division·Decided September 17, 2021·No. A-1980-19·Published

Opinion

NOT FOR PUBLICATION WITHOUT THE APPROVAL OF THE APPELLATE DIVISION

SUPERIOR COURT OF NEW JERSEY APPELLATE DIVISION

DOCKET NO. A-1980-19

JHC INDUSTRIAL SERVICES, LLC,

Plaintiff-Appellant, APPROVED FOR PUBLICATION September 17, 2021

v.

APPELLATE DIVISION

CENTURION COMPANIES, INC., and BONDEX INSURANCE COMPANY,

Defendants-Respondents.

Argued January 27, 2021 - Decided September 17, 2021 Before Judges Ostrer, Accurso, and Enright.

On appeal from the Superior Court of New Jersey, Law Division, Bergen County, Docket No. L-7635-17.

Autumn N. McCourt argued the cause for appellant (Brach Eichler, LLC, attorneys; Anthony M. Rainone, of counsel and on the briefs; Autumn M. McCourt, on the briefs).

Harold P. Cook, III, argued the cause for respondent.

The opinion of the court was delivered by ACCURSO, J.A.D.

Defendant Centurion Companies, Inc. subcontracted demolition work it agreed to perform for Alfred Sanzari Construction, Inc. to plaintiff JHC Industrial Services, Inc. JHC did the work and Sanzari paid Centurion for it. Centurion, however, did not pay JHC in full, prompting this action under N.J.S.A. 2A:30A-1 to -2, the legislation designed to ensure the prompt payment of subcontractors and known as the Prompt Payment Act. Although JHC completely prevailed in this two-year, contested case, the trial judge refused its application for $104,670.51 in "reasonable costs and attorney fees" pursuant to N.J.S.A. 2A:30A-2(f), instead awarding it $12,250.40 in fees and $4,125.33 in costs for a total award of $16,375.73, reasoning it could not "[u]nder Rendine [v. Pantzer, 141 N.J. 292, 334-35 (1995)], . . . grant over $100,000 in fees on a judgment that could not have exceeded $30,500."

We reverse. The Prompt Payment Act is a fee-shifting statute that makes an award of "reasonable costs and attorney fees" mandatory to a prevailing party. N.J.S.A. 2A:30A-2(f). Our Supreme Court has expressly "decline[d] to construe New Jersey's fee-shifting statutes to require proportionality between damages recovered and counsel-fee awards even if the litigation . . . vindicates no rights other than those of the plaintiff." Szczepanski v. Newcomb Med. Ctr., 141 N.J. 346, 366 (1995). As the clear purpose of the Prompt Payment Act is to ensure that subcontractors are fully

A-1980-19

and promptly paid for their work, a mandatory award of reasonable costs and attorney fees is necessary to vindicate the Act's salutary purposes. Because the trial court erred in imposing a proportionality requirement where none exists, we vacate the fee award and remand for the trial court to award plaintiff reasonable costs and attorney fees under the relevant Rendine factors.

The facts essential to deciding this appeal concern only Centurion's unwillingness to pay plaintiff for the demolition work it fully performed and its efforts to drag out the litigation plaintiff was forced to file to recover what was due. Plaintiff prevailed on its partial summary judgment motion establishing Centurion owed it $30,500, a judgment Centurion has not appealed. Thus, we dispense with any discussion of the facts giving rise to plaintiff's claim and focus on the effort it took plaintiff to secure its final judgment.

Following timely completion of JHC's work in June 2017, it was owed $30,500 by Centurion. When Centurion failed to pay, JHC threatened to lien the job. Glen Poppe, Centurion's project manager 1 testified at deposition and confirmed at trial that he told JHC "right up front if you put a lien on the job, I'm going to bond it, and I'm not going to pay you." Poppe made good on his threat.

1 Poppe also testified his son Christopher "owns" the Centurion companies.

A-1980-19

After plaintiff sued Centurion and the owner to foreclose the lien JHC filed notwithstanding Poppe's threat, it was advised by the owner's counsel that Centurion had secured a bond for release of the lien months before, requiring plaintiff to discharge its lis pendens against the property and file an amended complaint substituting the bonding company for the owner. Centurion then failed to answer, necessitating plaintiff to enter default against it. The parties entered a consent order to vacate default, and Centurion filed a motion to dismiss the action and compel arbitration. Plaintiff was forced to oppose the motion, which after protracted motion practice and oral argument was denied in a written opinion finding no agreement to arbitrate.

After its motion to compel arbitration was denied, Centurion filed an answer and counterclaimed for breach of contract, intentional interference with contract, breach of the implied covenant of good faith and fair dealing and overstatement of a construction lien. The court thereafter ordered the parties to mediation, and they agreed on a mediator. A week before the scheduled date, however, Centurion balked at the mediator's fees and refused to participate, necessitating a motion to the court to compel its participation. 2 Plaintiff won that motion, too.

2 Included in that motion was a request to compel Centurion to answer the interrogatories and document demands it had previously ignored. While the

A-1980-19

Centurion thereafter missed a court-ordered deadline to supply complete discovery, forcing yet another motion by plaintiff. After Centurion served amended discovery responses, plaintiff withdrew its motion. Keeping to the same pattern, Centurion refused to confirm deposition dates of its principals, forcing plaintiff to file yet another motion, this time to extend discovery to permit those depositions to go forward. After Centurion finally committed to dates for depositions, plaintiff also withdrew that motion.

After close of discovery, plaintiff filed a motion for partial summary judgment on its breach of contract and Prompt Payment Act claims. Centurion cross-moved for summary judgment dismissing the Prompt Payment Act claim. Following oral argument, the court entered summary judgment for plaintiff on its contract claim, finding "it is undisputed that JHC completed its work on the contract in full." The court denied both parties' motions on the Prompt Payment Act claim based on Centurion's assertion that plaintiff's delays in completing its work delayed the job and caused Centurion to incur additional costs and damages. Plaintiff's motion for reconsideration was denied.

motion prompted Centurion to finally provide some discovery, the answers were inadequate. The court ordered Centurion to provide complete responses within thirty days.

A-1980-19

Accordingly, Centurion forced plaintiff to trial on its Prompt Payment Act claim and on Centurion's counterclaims for breach of contract, intentional interference with contract, breach of the implied covenant of good faith and fair dealing and overstatement of a construction lien. Then, less than a week before the scheduled trial date, when it was reasonable to conclude plaintiff's counsel had already begun to prepare for trial, Centurion sought and received a thirty-day adjournment.

The case was finally tried without a jury by a different judge, who had not heard any of the pre-trial motions. The trial began with defendant dismissing all of its counterclaims. After hearing two days of testimony, the court awarded judgment to plaintiff on its Prompt Payment Act claim.

The court found that notwithstanding plaintiff had fully and promptly performed, Centurion never paid plaintiff the remaining $30,500 due, forcing plaintiff to file its lien. The court found the money "still hasn't been paid, even though it's over two years outstanding." The court further found Centurion produced "no evidence that there was a problem with the work done, or the job, or that there was a dispute." In sum, "[t]here was no problem with this job. The job was done. . . . [T]here's just non-payment."

The court directed plaintiff to file a certification of services, although noting "[t]his matter was not that complicated," and that it was "not sure how

A-1980-19

Free access — add to your briefcase to read the full text and ask questions with AI

JHC INDUSTRIAL SERVICES, LLC VS. CENTURION COMPANIES, INC. (L-7635-17, BERGEN COUNTY AND STATEWIDE), (N.J. Ct. App. 2021).

JHC INDUSTRIAL SERVICES, LLC VS. CENTURION COMPANIES, INC. (L-7635-17, BERGEN COUNTY AND STATEWIDE) (JHC INDUSTRIAL SERVICES, LLC VS. CENTURION COMPANIES, INC. (L-7635-17, BERGEN COUNTY AND STATEWIDE)) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

DiProspero v. Penn
874 A.2d 1039 (Supreme Court of New Jersey, 2005)
Szczepanski v. Newcomb Medical Center, Inc.
661 A.2d 1232 (Supreme Court of New Jersey, 1995)
Rendine v. Pantzer
661 A.2d 1202 (Supreme Court of New Jersey, 1995)
Coleman v. Fiore Bros., Inc.
552 A.2d 141 (Supreme Court of New Jersey, 1989)
Packard-Bamberger & Co., Inc. v. Collier
771 A.2d 1194 (Supreme Court of New Jersey, 2001)
New Jersey Democratic Party, Inc. v. Samson
814 A.2d 1028 (Supreme Court of New Jersey, 2002)
Craster v. BOARD OF COMMISSIONERS, CITY OF NEWARK
87 A.2d 721 (Supreme Court of New Jersey, 1952)
Furst v. Einstein Moomjy, Inc.
860 A.2d 435 (Supreme Court of New Jersey, 2004)