J.H. Berra Construction Co. v. City of Ballwin

786 S.W.2d 908, 1990 Mo. App. LEXIS 481, 1990 WL 34226
CourtMissouri Court of Appeals
DecidedMarch 27, 1990
DocketNo. 56466
StatusPublished

This text of 786 S.W.2d 908 (J.H. Berra Construction Co. v. City of Ballwin) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J.H. Berra Construction Co. v. City of Ballwin, 786 S.W.2d 908, 1990 Mo. App. LEXIS 481, 1990 WL 34226 (Mo. Ct. App. 1990).

Opinion

STEPHAN, Judge.

City of Ballwin (“Ballwin”) appeals the judgment of the trial court awarding approximately $15,000 and pre-judgment interest pursuant to a jury verdict in favor of respondent J.H. Berra Construction Co., Inc. (“J.H. Berra”). J.H. Berra had brought its action against Ballwin to recover payment of its security posted with its bid for a construction contract to remodel Ballwin’s police facility. We affirm the judgment of the trial court.

Ballwin desires only to have us review legal questions concerning certain instructions. Under Rule 81.16, appellant designated the record on appeal to include the legal file, transcript of the instruction conference, and statement of facts, along with certain trial exhibits. No transcript of the instruction conference, however, has been filed. In lieu of a transcript of the evidence at trial, the parties have filed a joint statement of material facts.

Ballwin, a city of the fourth class in St. Louis County, had requested a number of contractors, including respondent, to sub[910]*910mit proposals for construction of an addition and remodeling its police facility. The proposals were prepared in accordance with specifications and conditions in a booklet entitled “Contract Documents”. On March 7, 1986, J.H. Berra submitted its proposal to Ballwin, accompanied by its bid security bond of $15,032, an amount equal to five percent of its bid amount. On March 24, 1986, at a public meeting, the Ballwin Board of Aldermen considered respondent’s proposal and awarded the contract of $301,-651 to respondent. The next day, Ballwin directed its architect to prepare the contract documents for delivery to respondent. On April 15, 1986, the architect mailed the contract documents to J.H. Berra and they were received on April 16.

Ballwin had not advised respondent of the action taken on March 24 by the Board of Aldermen on respondent’s proposal before the contract documents were delivered. Until it received the contract documents on April 16, respondent was not aware of the action taken by Ballwin’s Board of Aldermen on March 24, 1986. Upon receiving the contract documents, respondent wrote a letter on April 16, 1986, withdrawing its proposal of March 7, and requesting the return of its bid bond. On May 9, 1986, appellant awarded the contract to the next lowest bidder. That contract was in the amount of $330,975, an increase of $29,324 over J.H. Berra’s bid.

A trial exhibit reflects that appellant notified J.H. Berra of its intention to retain the bid security as liquidated damages under a provision of its Instructions to Bidders after J.H. Berra refused to sign the contract.1 J.H. Berra then initiated this lawsuit to recover the bid security it had posted, and Ballwin filed a counterclaim for the amount of the difference between Berra’s bid and the amount of the next lowest bid. The jury returned a verdict for J.H. Berra on both its claim against Ballwin and on the counterclaim.

Appellant’s first point challenges the propriety of Instruction 7, J.H. Berra’s not-in-M.A.I. verdict director. Appellant argues the instruction incorrectly states the law, went beyond the scope of the pleadings, conflicted with another instruction to appellant’s prejudice and violated Rule 70.02(e). The instruction provided:

Your verdict must be for Plaintiff on Plaintiff’s claim if you believe:
First, Defendant did not communicate its acceptance of Plaintiff’s bid within thirty days after the date Plaintiff’s bid was received, and
Second, Defendant did not return Plaintiff’s bid security after the time specified in the Instructions to Bidders, and Third, Plaintiff was thereby damaged.

Whether the “Instructions to Bidders” referred to in this verdict director were in evidence in toto before the jury is not apparent from the record before us. We do have plaintiff’s trial exhibit one, a four page document containing three sections which are entitled “Notice to Bidders”, “Instructions to Bidders” and “General Conditions”.

In the Notice to Bidders, paragraph 1.01 “Advertisement for Bids” stated that sealed proposals for the construction of the Ballwin Police Facility would be received at the Ballwin City Hall until 2:00 p.m. on March 7, 1986. Paragraph 1.01 of the Instructions to Bidders dictating the bidding procedure provided in pertinent part:

No bid can be withdrawn after the time set for receiving of bids, or during the period when bids are being considered for an award by the Owner. In no case will action on the bids be deferred beyond thirty days from the date on which bids are received. (Emphasis added).
The Owner reserves the right to reject any or all bids and to waive any technicalities therein.

[911]*911Paragraph 1.03 of the Instructions to Bidders captioned “Bid Security” required the following:

Bids must be accompanied by a Certified or Cashier’s Check or a Bid Bond in the amount of 5% of the bid, made payable to the City of Ballwin which will be forfeited as liquidated damages in the event the bidder fails to sign a contract and furnish a satisfactory Performance and Payment Bond within ten (10) days following the date on which he is awarded a contract.
If a proposal is not accepted within thirty days after the date bids are received, or if the bidder executes a contract and furnishes said bond, his bid security will be returned.
Deposits of unsuccessful bidders will be returned shortly after opening of bids. (Emphasis added).

Ballwin contends that neither the Instructions to Bidders nor Missouri law required Ballwin to communicate to J.H. Berra acceptance of its bid within thirty days after Ballwin received the bid. Ballwin states it met the requirement of paragraph 1.01 that no “action on the bids be deferred beyond thirty days on which bids are received,” because Ballwin's “action” at its meeting of the Board of Aldermen voting to award J.H. Berra the construction contract on March 24, 1986, was within thirty days of the bid submission on March 7, 1986. Ballwin argues that the proposal terms themselves did not state that acceptance had to be communicated to respondent within thirty days and that the proposal terms are silent on the necessity of communicating the acceptance. Ballwin concludes that, in the absence of any language in the proposal requiring communication of acceptance within thirty days, Missouri law requires only that such acceptance be communicated within a reasonable time.

We disagree with Ballwin’s premise that nothing in the proposal terms required Ballwin communicate its acceptance of the bid within thirty days. Paragraph 1.03 expressly states “[i]f a proposal is not accepted within thirty days after the date the bids are received, ... his bid security will be returned.” That Ballwin “acted” on J.H. Berra’s proposal within thirty days pursuant to paragraph 1.01 does not constitute acceptance.

We are mindful of authority stating that awarding the contract to a particular bidder is an acceptance of the bid. Flinn v. Gillen, 320 Mo. 1047, 10 S.W.2d 923, 927 (1928). We also realize that no ordinance is required by law to award a contract. Grant City v. Salmon, 221 Mo.App. 853, 288 S.W. 88, 90[3] (1926). For example, as was done here, in

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Susanville v. Lee C. Hess Co.
290 P.2d 520 (California Supreme Court, 1955)
Medicine Shoppe International, Inc. v. J-Pral Corp.
662 S.W.2d 263 (Missouri Court of Appeals, 1984)
City of Grant City Ex Rel. O'Neil v. Salmon
288 S.W. 88 (Missouri Court of Appeals, 1926)
Flinn v. Gillen
10 S.W.2d 923 (Supreme Court of Missouri, 1928)
McCoy v. Randall
121 S.W. 31 (Supreme Court of Missouri, 1909)

Cite This Page — Counsel Stack

Bluebook (online)
786 S.W.2d 908, 1990 Mo. App. LEXIS 481, 1990 WL 34226, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jh-berra-construction-co-v-city-of-ballwin-moctapp-1990.