Jessica Howard Ltd. v. Norfolk Southern Railway Co.

316 F.3d 165
CourtCourt of Appeals for the Second Circuit
DecidedJanuary 10, 2003
DocketDocket No. 02-7305
StatusPublished
Cited by1 cases

This text of 316 F.3d 165 (Jessica Howard Ltd. v. Norfolk Southern Railway Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jessica Howard Ltd. v. Norfolk Southern Railway Co., 316 F.3d 165 (2d Cir. 2003).

Opinion

SOTOMAYOR, Circuit Judge.

Plaintiff-appellant Jessica Howard Ltd. (“Jessica Howard”) appeals from a judgment of the United States District Court for the Southern District of New York (Allen G. Schwartz, J.) holding that the contract damages owed by defendant-ap-pellee Norfolk Southern Railway Co. (“Norfolk Southern”), which has conceded liability for the partial loss of Jessica Howard’s shipment of ladies’ garments during their transit from Shanghai, China to North Bergen, New Jersey, are, as a mat[166]*166ter of law, limited to Jessica Howard’s cost of acquiring the goods in Shanghai or $15,164.70. Jessica Howard Ltd. v. M/V Sky Light, No. 00 CIV. 6319(AGS), 2002 WL 362767 (S.D.N.Y. March 5, 2002). The district court did not resolve which of several potentially operative documents controlled Norfolk Southern’s liability and instead determined that each of the four documents limited damages to the same figure. We hold that under the terms of one of these documents, the Norfolk Southern Intermodal Rules Circular # 1, damages cannot, as a matter of law, be measured by the value of the goods at the origin of the shipment. We therefore vacate the district court judgment and remand to the district court for further consideration of which document governs this dispute and what the proper measure of damages should be under the governing document.

BACKGROUND

Appellant Jessica Howard, plaintiff below, contracted to have 4440 ladies’ garments shipped via intermodal transport from Shanghai, China to North Bergen, New Jersey. The containerized goods traveled from China to the West Coast by ship and then to the East Coast by rail service provided by defendant-appellee, Norfolk Southern. Upon arrival, the shipment was missing 1243 garments. Jessica Howard initially sued multiple parties, but Norfolk Southern has since admitted liability for the loss, and Jessica Howard has voluntarily dismissed its claims against all defendants except Norfolk Southern.

In the district court, both parties moved for summary judgment on damages. They agree that Norfolk Southern’s liability is governed by contract documents generated in connection with the shipment, but they disagree about the extent of this liability. Norfolk Southern claims that its liability is limited to $15,164.70, the alleged cost of acquiring the goods at the shipment’s origin in Shanghai; Jessica Howard claims that the amount is $62,142.00, the alleged actual market value of the goods at destination, plus interest and costs.

In its March 5, 2002 Order, the district court directed entry of judgment against Norfolk Southern in the amount of $15,164.70. The district court noted that four documents, each potentially impacting Norfolk Southern’s contractual liability, were generated in conjunction with the shipment. Direct Forwarding Co., Inc., a freight forwarder, issued a Combined Transport Bill of Lading1 (the “DFC Bill of Lading”). K Line, the ocean carrier of the shipment, issued a separate bill of lading (the “K Line Bill of Lading”). Norfolk Southern used its Intermodal Rules Circular # 1, dated June 1, 1999 (the “Circular”), to govern its liability during its segment of intermodal shipments in general. Finally, the district court found there was “some evidence” that Norfolk Southern issued an “edi waybill” in connection with the Jessica Howard shipment.

Although the parties disputed which of these documents controlled Norfolk Southern’s liability, the district court did “not resolve that question ... because the result [was] the same under any of’ them and held that Norfolk Southern’s liability is limited to Jessica Howard’s cost of ac[167]*167quiring the lost goods in Shanghai “regardless of which document governs.” The district court left open whether the “edi waybill” existed and whether certain documents incorporated the terms of others; instead of resolving these disputes as a matter of law or leaving them for trial, it determined that under any possible factual scenario, only two liability provisions could apply — the provision in the Circular or the provision in the K Line Bill of Lading2— and that both measured damages by the cost of acquiring the goods in Shanghai.

The Circular offers two liability options, “Standard” and “Carmack”;3 the district court determined, and the parties do not dispute on appeal, that the Standard terms apply as Jessica Howard never opted into the Carmack regime. In the “Standard Liability Provisions and Restrictions” seetion, the Circular provides that Norfolk Southern’s liability:

[W]ill not extend beyond the actual physical loss or damage to the cargo itself, plus any costs reasonably incurred in efforts to mitigate the loss or damage. [Norfolk Southern] will not be liable for attorney’s fees ..., for interest, or for special, consequential, indirect or punitive damages. Unless amended ..., [Norfolk Southern’s] liability for loss, damage or delay to any shipments under this circular shall be limited to the lesser of the destination value of the cargo or $250,000.

The district court interpreted the “actual physical loss” to be Jessica Howard’s cost of acquiring the goods in Shanghai,4 and noted that “the parties agree[d that the cost of acquisition] is $15,164.70.”5 It rea[168]*168soned that the Carmack terms limit liability to the fair market value of the lost goods at destination, and that measuring liability under the Standard terms by value at destination “would render the standard liability option meaningless.” It also noted that the Standard terms expressly excluded consequential damages. Because lost profits are a type of consequential damages and because measuring Jessica Howard’s loss by the destination value of the garments would compensate for lost profits, the district court determined the Standard terms could not measure “actual physical loss” by the destination value of the lost goods.

The district court held that the K Line Bill of Lading, presuming its own terms apply, includes a “Himalaya Clause” that extends limitations of liability included in the K Line Bill of Lading to all “Connecting Carriers,” including Norfolk Southern. By its own terms, the K Line Bill of Lading thus limits Norfolk Southern’s liability to “Merchants^] net invoice cost, plus freight and insurance premium, if paid.” As under the Circular, the district court determined the merchants’ net invoice cost also to be Jessica Howard’s cost of acquiring the goods in Shanghai.

On March 11, 2002, the district court entered judgment in favor of Jessica Howard in the amount of $15,164.70.

DISCUSSION

We review a district court’s grant of summary judgment de novo. See Rogers v. City of Amsterdam, 303 F.3d 155, 158 (2d Cir.2002). The district court construes the terms of a contract as a matter of law, and we review the district court’s construction de novo. State Farm Fire & Cas. Ins. Co. v. Sayles, 289 F.3d 181, 185-86 (2d Cir.2002).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jessica Howard Ltd. v. Norfolk Southern Railway Co.
316 F.3d 165 (Second Circuit, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
316 F.3d 165, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jessica-howard-ltd-v-norfolk-southern-railway-co-ca2-2003.