Jesco, Inc. v. Whitehead

451 So. 2d 706, 1984 Miss. LEXIS 1640
CourtMississippi Supreme Court
DecidedFebruary 29, 1984
Docket53833
StatusPublished
Cited by96 cases

This text of 451 So. 2d 706 (Jesco, Inc. v. Whitehead) is published on Counsel Stack Legal Research, covering Mississippi Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jesco, Inc. v. Whitehead, 451 So. 2d 706, 1984 Miss. LEXIS 1640 (Mich. 1984).

Opinion

451 So.2d 706 (1984)

JESCO, INC.
v.
Gerald WHITEHEAD.

No. 53833.

Supreme Court of Mississippi.

February 29, 1984.
Rehearing Denied July 11, 1984.

*707 William M. Beasley, W.P. Mitchell, Mitchell, Eskridge, Voge, Clayton & Beasley, Tupelo, Darden, Sumners, Carter & Trout, New Albany, for appellant.

William S. Lawson, Tupelo, Talmadge Littlejohn, New Albany, Roscoe B. Hogan, William W. Smith, Birmingham, Ala., for appellee.

En Banc.

WALKER, Presiding Justice, for the Court:

This is an appeal from the Circuit Court of Lee County wherein the appellee, Gerald Whitehead, was awarded damages resulting from personal injuries received on December 22, 1977 when an explosion occurred in a grain mill operated by Sunshine Mills, Inc. (hereinafter referred to as Sunshine). Jesco, Inc. was an independent contractor performing work which required, among other things, welding on a grain conveyor and grain bin.

We reverse and remand for a new trial.

During the plaintiff's case in chief the plaintiff attempted to prove through *708 the testimony of an engineering expert, Phillip Lawson, that Jesco caused the explosion. The evidence presented by the plaintiff is largely uncontradicted except for the testimony of the experts. On December 22, 1977, an explosion occurred in the mill building operated by Sunshine. The four-story concrete building was being used by Sunshine to manufacture dog food at the time of the explosion. The first story of the building contained the main control panel for the production equipment. Also on the first floor of the mill building were the expander units, the weigh hopper for the mixer, and screw conveyors which feed grain into the weigh hopper. At the time of the explosion the conveyor lines had been turned on and were running. Plaintiff, Gerald Whitehead, was an employee of Sunshine. He was an expander operator and was approximately three or four feet away from the scales and mixing controls on the first floor at the time of the explosion.

For many years Jesco, a general contractor, had assisted Sunshine in building additions and making assorted alterations to the plant. On the day of the explosion Jesco employees were performing two separate jobs on the second floor of the building. Tommy May and Roger Hawkins had been assigned the task of building (cutting and welding) term spouts coming off the hopper of the grain bins. They had finished their work on two of the bins, the last having been completed at least thirty minutes before the explosion. Both bins were in full operation and grain had already refilled the bins above the area where the work had been performed. Jimmy Rickman and Jerry Thompson were assembling a screw conveyor in the middle of the second floor area at the time of the explosion. In the process of assembling the screw conveyor, Jerry Thompson had used the acetylene cutting torch to cut two bolt holes.

Phillip Lawson, the plaintiff's industrial engineer and expert witness, inspected the explosion site five days after the explosion occurred. On the second floor, twelve to fifteen feet from the area where Thompson and Rickman were working on the screw conveyor, Lawson found a burned hole in an acetylene hose. On top of the hose was a piece of sheet metal. Based on the fact that he found the burned hose under the sheet metal, Lawson theorized: (a) that in the process of cutting the bolt holes it was necessary for Jerry Thompson to pull the hose taut; (b) that when he pulled the hose against the adjacent metal, the edge of the metal cut the hose; (c) that acetylene gas leaked from the hole and spewed directly into dust assumed to be lying on the floor blowing the dust into a thick cloud; (d) that the acetylene gas and dust cloud were ignited by an unknown source creating a small explosion in the southwest corner twelve to fifteen feet from Rickman and Thompson; (e) that the small explosion shook the entire building, stirring up grain dust; (f) that the flame front from the first explosion ignited the stirred-up dust cloud on the east side of the second floor, creating the second big explosion which caused the major damage and the burns suffered by the plaintiff.

The theory testified to by Phillip Lawson, Whitehead's expert, was sharply contradicted by Jesco's witnesses who were on the second floor when the explosion occurred. They testified that the metal plates were not on the hose at the time of the explosion and that the explosion and fire did not originate on the second floor. They further testified that it was not necessary to pull the hose taut in order for them to perform their welding and cutting operations.

There was much evidence presented by Whitehead that Jesco had violated the Standard Fire Prevention Ordinance adopted by the City of Tupelo, which ordinance contained provisions directed toward the prevention of dust explosions. Whitehead charged and proved, inter alia, that Jesco had violated the City Ordinance by performing welding and cutting operations within thirty-five feet of combustible materials exposed to the operation; failed to have a fire watcher to watch for fires during the job and for thirty minutes after the *709 welding and cutting operations were finished; welding or cutting in or near rooms or locations where flammable dust was present; and performing welding or cutting on a container which had contained flammable solids without cleaning, inerting, or purging same.

The question presented in this case is whether Whitehead proved by a preponderance of the evidence that Jesco's negligence proximately contributed to the explosion and Whitehead's resulting injuries and damages. The jury found that it did.

However, after a meticulous combing and studying of this record and the briefs of able counsel, we are of the opinion that the verdict is contrary to the overwhelming weight of the evidence and that the judgment in favor of Whitehead against Jesco should be and is hereby set aside and a new trial ordered. In doing so, we have considered the cases cited by appellant, Jesco, urging that the case be reversed and rendered as well as those cited by appellee, Whitehead, urging that the case be affirmed. In our opinion justice demands another trial.

In remanding the case, we feel it is necessary to comment on several of appellant's assignments of error.

I.

The first question is whether the trial court erred in not instructing the jury that they must rely on the evidence presented by the plaintiff's expert witness, Phillip Lawson, as to the cause of the explosion if the plaintiff was to recover.

The primary thrust of Whitehead's case was that the hole in the acetylene hose line was caused by Jesco's employees' negligence and was the proximate cause of the explosion. However, it had been pled and there was presented to the jury throughout the case evidence that Jesco had violated several sections of the Ordinance of the City of Tupelo dealing with welding and cutting operations. Because of this evidence, we are unable to say that the trial court erred in refusing to grant Jesco's instruction DJ9A[1] and in granting Whitehead's instruction P7[2].

We do not find it necessary to comment on the testimony of Whitehead's other expert, Sims, offered on rebuttal, as this will, in all probability not occur again upon retrial.

II.

It was error for Whitehead's attorney to tell the jury in closing argument that all sums paid by the Workmen's Compensation insuror must be repaid before the plaintiff could receive anything out of any sum awarded by them. See Merchants Co.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Winter v. Cowart
N.D. Mississippi, 2024
Georgia Pacific Corporation v. Cook Timber Company, Inc.
194 So. 3d 118 (Mississippi Supreme Court, 2016)
Kathy May Huber v. Cecilia Eubanks
197 So. 3d 861 (Mississippi Supreme Court, 2015)
Smith v. Union Carbide Corp.
130 So. 3d 66 (Mississippi Supreme Court, 2013)
Jackson HMA, LLC v. Morales
130 So. 3d 493 (Mississippi Supreme Court, 2013)
Laney v. Vance
112 So. 3d 1079 (Mississippi Supreme Court, 2013)
Mississippi Baptist Health Systems, Inc. v. Kelly
88 So. 3d 769 (Court of Appeals of Mississippi, 2011)
Charles H. Laney v. Martin Vance
Mississippi Supreme Court, 2011
Robinson Property Group, L.P. v. Mitchell
7 So. 3d 240 (Mississippi Supreme Court, 2009)
Goodyear Tire & Rubber Co. v. Kirby
156 So. 3d 281 (Court of Appeals of Mississippi, 2009)
River Region Medical Corp. v. Patterson
975 So. 2d 205 (Mississippi Supreme Court, 2008)
Bullock v. Lott
964 So. 2d 1119 (Mississippi Supreme Court, 2007)
Fitch v. Valentine
959 So. 2d 1012 (Mississippi Supreme Court, 2007)
Champluvier v. State
942 So. 2d 145 (Mississippi Supreme Court, 2006)
Milton Watts v. Radiator Specialty Company
Mississippi Supreme Court, 2006
Irby v. Travis
935 So. 2d 884 (Mississippi Supreme Court, 2006)
Williams v. State
923 So. 2d 990 (Mississippi Supreme Court, 2006)
Ronald A. Bullock v. W. L. Lott
Mississippi Supreme Court, 2005

Cite This Page — Counsel Stack

Bluebook (online)
451 So. 2d 706, 1984 Miss. LEXIS 1640, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jesco-inc-v-whitehead-miss-1984.