Jerry L. Starkey, TBDL, L.P., and PBW Development Corporation v. Glen Graves

448 S.W.3d 88, 2014 Tex. App. LEXIS 10210, 2014 WL 4459113
CourtCourt of Appeals of Texas
DecidedSeptember 11, 2014
Docket14-12-00633-CV, 14-12-00709-CV
StatusPublished
Cited by28 cases

This text of 448 S.W.3d 88 (Jerry L. Starkey, TBDL, L.P., and PBW Development Corporation v. Glen Graves) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jerry L. Starkey, TBDL, L.P., and PBW Development Corporation v. Glen Graves, 448 S.W.3d 88, 2014 Tex. App. LEXIS 10210, 2014 WL 4459113 (Tex. Ct. App. 2014).

Opinion

OPINION

TRACY CHRISTOPHER, Justice.

When the relationship between the companies and individuals involved in a limited partnership broke down, the aggrieved limited partner sued the other partners and their owner, alleging that they breached successive partnership agreements and committed or conspired to commit statutory and common-law fraud and breaches of the duties of loyalty and care. The plaintiff sought the same two categories of actual damages for every theory of liability, and the jury assessed the same damages against at least one of the defendants under each cause of action submitted. On appeal, the liable defendants argue that the plaintiff cannot recover either category of damages, and that judgment cannot be supported under any theory of liability.

We affirm the award of actual damages under some of the jury findings but reverse the award of expert fees and deposition costs because no evidence supports the statutory-fraud finding. We remand the case for relitigation of attorney’s fees. Because some of the jury’s findings were made in response to erroneous questions in the charge, the plaintiff on remand may elect between (1) judgment based on the remaining favorable findings that were not successfully challenged in this appeal; or (2) a new trial of the claims asserted by or against the appellants, as explained below.

I. Factual And PROCEDURAL Background 1

Glen Graves owned a three-story retail-sales building in Galveston known as the Peanut Butter Warehouse, and he intended to add a fourth story, continue using the first floor for retail sales, and convert most of the remainder of the building to condominiums. After expending his own available funds and an additional $500,000 from a bank loan on the renovations, Graves needed more money to complete the work. He began discussions with potential investors.

Graves ultimately entered into multiple partnership agreements with appellant Jerry Starkey or with two of Starkey’s companies—PBW Development Corporation (“the General Partner”) and TBDL, L.P. We refer to Starkey and the two companies collectively as “the Starkey parties.” Starkey is an attorney, a CPA, and the principal of a company that owns a parking lot near the building. Graves testified that Starkey was the attorney for all parties involved in the partnership, including Graves; Starkey testified that he was the attorney for all of those parties except Graves. Starkey’s wife Elizabeth is also a CPA and was the bookkeeper for the partnership, TBDL, and the General Partner.

Of the three partnership agreements alleged to have been executed—one in October 2006, one in January 2007, and one in April 2008—only the 2007 and 2008 agree *94 ments were produced at trial. 2 Starkey testified that there was no 2006 agreement, and that Graves signed the 2007 and 2008 agreements. Graves testified that he did not sign the 2007 agreement, and that Starkey must have attached the signature page from the 2006 agreement to the 2007 agreement, and then destroyed the 2006 agreement. The jury was not asked to resolve this factual dispute. Instead, Graves ultimately asked the trial court to submit breach-of-contract questions to the jury about each of the three agreements, and the jury found that all three were breached. We therefore refer to all three agreements as if each were executed by the parties.

A. The October 2006 Agreement

The jury found that in October 2006, Starkey and Graves agreed to a written partnership agreement in which Starkey and Graves were “co-general partners.” Graves was to contribute the building to the partnership, “oversee the project,” and ‘ receive a gross salary of $1,500 per week, which is $78,000 per year. Starkey was to provide parking and “borrowing power with the banks for necessary' loans.” Through the General Partner and TBDL, Starkey also was to invest $500,000 in the project. The trial court incorporated these findings in the judgment.

As for the performance of this contract, Graves testified that at the same time he signed this partnership agreement, he executed a separate document transferring some or all of the building’s ownership to the partnership or to Starkey. 3 It is unclear whether Graves was paid anything in 2006, but he presented evidence that he was paid between $47,000 and $57,000 through the end of 2007; 4 that he was not paid again until April 2008; and that after he was paid a further $14,000, payments were stopped again and never resumed. During the time between the execution of the 2006 and -2007 agreements, Starkey made no capital contributions to the partnership. Although the partnership applied for a bank loan of $1.7 million in November 2006, the loan did not close until after the 2007 partnership agreement was executed.

B. The January 2007 Agreement

In January 2007, Graves, TBDL and the General Partner entered into a written partnership agreement. Under the terms of this agreement, Graves was a limited partner, and the contract specified that limited partners had no right of control or management over the partnership’s business and affairs. Graves was to contribute the building and have a 49% share of the partnership; TBDL was to contribute $470,000 and have a 49% share; and the General Partner was to contribute $20,000 and have a 2% share. The agreement provides that the General Partner will “re *95 ceive an annual guaranteed fee, initially in the amount of $78,000 to offset the salary of a General Manager.” Unlike the 2006 agreement, parking is not mentioned.

C. The April 2008 Agreement

Before the end of March 2008, Starkey told Graves that the partnership needed more than $300,000 in additional capital contributions and insisted that Graves contribute the entire amount. Graves refused, and he testified that Starkey demanded that Graves sign an amended partnership agreement as follows:

[Starkey] said to sign this or you will be in jail tomorrow morning. And while you’re in jail, I’m going to go down and have this thing foreclosed on and I have already made arrangements with the banker for him to come in and buy it directly from the bank and exclude me completely.
In other words, everything that I own would just simply be gone.

As for the grounds for having Graves jailed, Graves testified that Starkey “said he was an attorney and he knew how to do it.” Graves signed the agreement.

The relevant terms of the 2008 agreement are the same as those of the 2007 agreement, except that the General Partner and TBDL together contributed an additional $300,000, and a 19% share of the partnership effectively was transferred to them from Graves. 5 After this, the relationship between Starkey and Graves continued to deteriorate until Starkey had Graves locked out the building.

D. The Jury’s Liability Findings

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ronald J. Marchiani v. Dale Shadle
Court of Appeals of Texas, 2024
Antero Resources v. Kawcak
85 F.4th 741 (Fifth Circuit, 2023)
SwiftAir v. Southwest Airlines
California Court of Appeal, 2022
SwiftAir v. Southwest Airlines CA2/7
California Court of Appeal, 2022
in the Interest of M.P., a Child
Court of Appeals of Texas, 2021
Gator Gone Safety Pilots v. Garry W. Holt
Court of Appeals of Texas, 2021
Linda S. Nowlin v. Lori Keaton
Court of Appeals of Texas, 2019
Turman v. POS Partners, LLC
541 S.W.3d 895 (Court of Appeals of Texas, 2018)
Gulshan Enterprises, Inc. v. Zafar, Inc.
530 S.W.3d 298 (Court of Appeals of Texas, 2017)
Guerrero-McDonald v. Nassour
516 S.W.3d 198 (Court of Appeals of Texas, 2017)
Eric Randle v. Clint Sanders
Court of Appeals of Texas, 2016
Zaidi v. Shah
502 S.W.3d 434 (Court of Appeals of Texas, 2016)
MJS & Associates, L.L.C. v. Master
501 S.W.3d 751 (Court of Appeals of Texas, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
448 S.W.3d 88, 2014 Tex. App. LEXIS 10210, 2014 WL 4459113, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jerry-l-starkey-tbdl-lp-and-pbw-development-corporation-v-glen-texapp-2014.