Jensen v. Thornell

District Court, D. Arizona·Decided April 23, 2020·No. 2:12-cv-00601·Unknown

Opinion

1 WO 2 3 4 5 6 IN THE UNITED STATES DISTRICT COURT 7 FOR THE DISTRICT OF ARIZONA

9 Victor Antonio Parsons, et al., No. CV-12-00601-PHX-ROS

10 Plaintiffs, ORDER

11 v.

12 David Shinn, et al.,

13 Defendants. 14 15 Plaintiffs request the Court find Defendants substantially noncompliant with a total 16 of eleven Performance Measures (“PMs”) at various complexes. (Doc. 3492). Defendants 17 agree that one PM is substantially noncompliant but argue the other ten should not be found 18 substantially noncompliant at this time. It is undisputed that most of the ten PMs have, in 19 the past, met the long-established criteria to be deemed substantially noncompliant. It is 20 also undisputed, however, that many of those PMs have been compliant in recent months. 21 Given those recent performance levels, Defendants argue Plaintiffs should be required to 22 pursue informal dispute resolution steps again before the Court deems the ten PMs 23 substantially noncompliant. The Stipulation, however, does not require repetitive attempts 24 at informal resolution. Therefore, the ten PMs will be declared substantially noncompliant. 25 Defendants will be required to submit remediation plans for any of those PMs that were 26 not compliant in the most recent data and will be required to submit remediation plans for 27 any currently compliant PMs that, in the future, become noncompliant. 28 A. Background 1 As of 2018, the Stipulation required Defendants to achieve an 85% compliance rate 2 for every PM at every complex. (Doc. 1185 at 4). The Stipulation sets forth a multistep 3 process for the parties to follow in the event Defendants “fail to substantially comply in 4 some significant respect with [the] Stipulation.” (Doc. 1185 at 13). If Plaintiffs believe 5 Defendants have not “substantially compl[ied],” Plaintiffs must first provide Defendants a 6 “written statement describing the alleged non-compliance.” (Doc. 1185 at 13). Defendants 7 must then provide a written response, after which the parties are required to “meet and 8 confer in a good faith effort to resolve their dispute informally.” If they are unable to 9 resolve their dispute, the parties must proceed to mediation before a Magistrate Judge. If 10 that mediation fails, Plaintiffs can file a motion with the Court. Assuming the Court agrees 11 that Defendants have not “substantially compl[ied],” the Court must “require Defendants 12 to submit a plan approved by the Court to remedy the deficiencies identified by the Court.” 13 (Doc. 1185 at 14). Then, if Defendants’ remediation plan “did not remedy the 14 deficiencies,” the Court gains the power to enforce the Stipulation “through all remedies 15 provided by law.” (Doc. 1185 at 14). 16 After the Stipulation went into effect, the parties could not agree on what would 17 qualify as “substantial noncompliance” to trigger the enforcement process. In February 18 2018, Magistrate Judge Duncan ruled Defendants will be “substantially non-compliant” 19 with the Stipulation whenever a PM falls below 85% for more than six months within any 20 24-month period or if a PM falls below 85% for three consecutive months. (Doc. 2644). 21 In establishing these parameters, Magistrate Judge Duncan recognized “that there will be 22 PM/locations where the more recent history has been consistently compliant and so a 23 finding of noncompliance may not require the immediate imposition of a remediation 24 plan.” (Doc. 2644 at 2). In other words, given the very lengthy process necessary for the 25 Court to even be in the position to require a remediation plan, it is possible a particular PM 26 will have improved such that, by the time the Court is empowered to take action, a 27 remediation plan is not immediately necessary based on the most recent numbers. 28 In February 2020, Plaintiffs filed a motion to enforce the Stipulation. (Doc. 3492). 1 That motion claims the parties have completed the multi-step process regarding eleven 2 PMs such that the Court should now order Defendants to produce a remediation plan 3 regarding those PMs.1 The eleven PMs can be divided into three groups based on their 4 history and the arguments the parties make. 5 B. PMs 23, 24, 40, 44, and 52 6 1. History 7 On January 2, 2019, Plaintiffs sent Defendants a written notice stating Defendants 8 were substantially noncompliant regarding, among others, the following PMs and 9 locations: 10 PM 23: Lewis; 11 PM 24: Eyman, Florence, Phoenix, Yuma; 12 PM 40: Florence; 13 PM 44: Phoenix, Tucson; 14 PM 52: Lewis. 15 (Doc. 3493-1 at 3). Defendants’ response to that statement conceded they were 16 substantially noncompliant with these PMs. (Doc. 3493-1 at 7). The parties then 17 proceeded to mediation before a Magistrate Judge in August 2019. That mediation failed. 18 Plaintiffs now seek a finding of substantial noncompliance regarding these nine 19 PMs. Defendants concede that PM 40 at Florence is substantially noncompliant and 20 Defendants state they “will identify the deficiencies and develop a remedial plan to correct 21 them.” (Doc. 3515 at 4). But Defendants argue the remaining eight PMs have become 22 compliant. Thus, Defendants believe there is no need to find those eight PMs substantially 23 noncompliant and require submission of a remediation plan. 24 2. Analysis 25 The informal process that must precede any motion to enforce the Stipulation is 26 lengthy. That process begins with monitoring data compiled by Defendants that, by the 27

28 1 The motion originally identified twelve PMs but Plaintiffs have conceded PM 19 at Tucson is no longer at issue. 1 time the data is produced, is two months old. Once the data is produced, Plaintiffs must 2 send written notice to Defendants of noncompliance and Defendants have thirty days to 3 respond. Then, the parties have to confer within 30 days. (Doc. 1185 at 13). If they cannot 4 reach an agreement, they must pursue mediation, which the Stipulation anticipates taking 5 as long as sixty days. Only if mediation fails can Plaintiffs seek a finding of substantial 6 noncompliance from the Court. In other words, if Defendants became substantially 7 noncompliant with a particular PM in December 2018, that fact would first be reflected in 8 data produced in February 2019. If Plaintiffs immediately sent written notice, Defendants 9 would have until March 2019 to respond and the parties would have until April 2019 to 10 confer. If they could not reach an agreement, the parties would have until June 2019 to 11 pursue mediation. And only after that mediation failed could Plaintiffs seek a finding of 12 substantial noncompliance. Thus, noncompliance in December 2018 could not be raised 13 with the Court until July 2019, at least seven months later. 14 Given the lengthy dispute resolution process required by the Stipulation, a finding 15 of substantial noncompliance will always be premised on old data. Moreover, it is entirely 16 possible that by the time Plaintiffs seek a finding of substantial noncompliance Defendants 17 will have identified and remedied a particular failure such that the more recent data shows 18 Defendants are no longer noncompliant. 19 According to Defendants, if the noncompliance was too long ago, the Court cannot 20 make a finding of substantial noncompliance. Alternatively, Defendants argue that if they 21 have become compliant by the time Plaintiffs file their motion, the Court should not make 22 a finding of substantial noncompliance. Nothing in the Stipulation supports the theory that 23 stale data should prevent a finding of substantial noncompliance or that the noncompliance 24 must exist at the moment Plaintiffs seek relief from the Court.

Free access — add to your briefcase to read the full text and ask questions with AI

Jensen v. Thornell, (D. Ariz. 2020).

Jensen v. Thornell (Jensen v. Thornell) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Employers Mutual Casualty Co. v. DGG & Car, Inc.
183 P.3d 513 (Arizona Supreme Court, 2008)