Jensen v. Intermountain Power Agency

1999 UT 10, 977 P.2d 474, 362 Utah Adv. Rep. 3, 1999 Utah LEXIS 11, 1999 WL 45189
CourtUtah Supreme Court
DecidedFebruary 2, 1999
Docket950464
StatusPublished
Cited by52 cases

This text of 1999 UT 10 (Jensen v. Intermountain Power Agency) is published on Counsel Stack Legal Research, covering Utah Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jensen v. Intermountain Power Agency, 1999 UT 10, 977 P.2d 474, 362 Utah Adv. Rep. 3, 1999 Utah LEXIS 11, 1999 WL 45189 (Utah 1999).

Opinion

ZIMMERMAN, Justice:

¶ 1 This case involves a negligence claim relating to damage caused by flooding of the Sevier Bridge Reservoir in 1983 and 1984 and an unrelated claim concerning certain water rights located under the reservoir. As to the disputed water rights, the trial court concluded, as a matter of law, that defendants had an easement to store water in the reservoir and that plaintiffs land and water rights were subject to the terms of that easement. As to claims that defendants’ negligence resulted in the flooding of plaintiffs land, a jury found that defendants were not negligent. We affirm on both issues.

¶ 2 Defendants in this case, Delta Canal Co., Melville Irrigation Co., Abraham Irrigation Co., Deseret Irrigation Co., Central Utah Water Co., and Intermountain Power Agency 1 (collectively “IPA”), have appropriation rights in water from the Sevier River and storage easements in the Sevier Bridge Reservoir (“the reservoir”). 2 These easements give IPA the right to store water up to the level of the reservoir’s capacity of 80 feet, the height of the reservoir’s spillway. Plaintiff L. Carl Jensen owns certain property, some parcels of which straddle the reservoir’s 80-foot contour and some parcels of which lie completely below the contour.

¶ 3 In June of both 1983 and 1984, runoff flows were at unprecedentedly high levels and caused portions of Jensen’s land to flood. Jensen claims that this flooding damaged his property straddling the contour by damaging fences, corrals, and roads and by leaving silt, alkali, and debris deposits. Jensen also claims that this flooding caused damage to his land lying below the contour and thereby interfered with his stock operation. 3 Jensen filed an action against IPA, claiming that it was negligent in failing to adequately prepare for the excessive runoff. Jensen sought injunctive relief and damages in excess of twelve million dollars. Jensen also filed a quiet title action, alleging water rights in both water appurtenant to the reservoir and appropriated water from the reservoir. 4 Jensen also sought damages for IPA’s and its predecessor’s expropriation and conversion of his water.

¶ 4 On February 2, 1994, the trial court granted a partial summary judgment in *476 IPA’s favor and dismissed Jensen’s easement and water rights claims. The trial court conducted a jury trial on the flooding issues. The jury found that IPA was not negligent, and the court dismissed. the remainder of Jensen’s claims. Jensen moved for a judgment notwithstanding the verdict and for a new trial. The court denied both motions and entered a final judgment on August 10, 1995. Jensen appealed.

¶ 5 In his brief before this court, Jensen challenges the partial summary judgment disposing of his easement and water rights claims. He also attacks the jury verdict, arguing that the trial court committed several errors in instructing the jury, abused its discretion in allowing IPA to present statistical evidence related to the severity of the 1983 and 1984 flooding of the Sevier River, and abused its discretion in allowing the introductioñ of a video depicting the collapse of another dam downstream from the dam associated with the reservoir.' During the appellate briefing process, IPA moved for summary disposition or, alternatively, to limit the scope of the appeal. It argues that this court does not have jurisdiction to review the partial summary judgment because Jensen did not appeal from the judgment finalizing it. We address this jurisdictional question first.

116 Jensen’s notice of appeal states that he appeals from “the jury verdict entered ... on July 14, 1995,” and the trial court’s “denial of his Rule 50 and Rule 59 motion, which denial was entered ... on October 10, 1995.” Jensen did not state in his notice that he was appealing either the February 2, 1994, judgment granting IPA partial summary judgment or the August 10, 1995, final judgment concerning both the jury verdict and the partial summary judgment. Thus, neither of the judgments Jensen .listed in his notice deals with the partial summary judgment.

¶ 7 Rule 3(d) of the Utah Rules of Appellate Procedure requires that “[t]he notice of appeal shall ... designate the judgment or order, or part thereof, appealed from.” Utah R.App. P. 3(d). This court has held that rule 3(d)’s requirement is jurisdictional. In Nunley v. Stan Katz Real Estate, Inc., 15 Utah 2d 126, 388 P.2d 798 (1964), we emphasized that “the object of a notice of appeal is to advise the opposite party that ah appeal has been taken from a specific judgment in a particular case. Respondent is entitled to know specifically which judgment is being appealed.” Id. at 800; see also Smith v. Barry, 502 U.S. 244, 248, 112 S.Ct. 678, 116 L.Ed.2d 678 (1992) (stating that requirements of rule 3 “are jurisdictional in nature, and their satisfaction is a prerequisite to appellate review”). Jensen contends that his appeal of the court’s denial of his rule 50 motion for a j.n.o.v. and rule 59 motion for a new trial is sufficient to encompass the partial summary judgment. Jensen reasons that because a party cannot appeal the denial of a motion for a new trial, courts have treated appeals designated as being from such rulings as appeals from the final judgment. He cites Price v. Western Loan & Savings, 35 Utah 379, 100 P. 677 (1909), in which this court denied a motion to dismiss an appeal, finding that the party’s appeal from a motion denying a new trial really was an appeal from the final judgment.

¶ 8 We find Price distinguishable. There, this court found that the notice of appeal sufficiently identified the final judgment at issue, even though it purported to be from the denial of a new trial. Moreover, Price allowed the appeal to proceed only because the respondent was not prejudiced by the failure to properly notice the appeal. In contrast, here, Jensen’s motion for a new trial was addressed only to those claims that went to the jury, which did not include the water rights claims. In addition, IPA was prejudiced by Jensen’s oversight. After Jensen failed to notice an appeal from any judgment related to the partial summary judgment on the water rights issue, IPA elected not to proceed with cross-appeals against certain third-party defendants whom the court had dismissed years earlier by granting them summary judgment. IPA did not receive Jensen’s docketing statement, which first indicated that Jensen was attempting to obtain review of the grant of partial summary judgment, until at least five days after the date on which IPA’s time for cross-appeal expired. Thus, Jensen’s faulty notice of *477 appeal precluded IPA from cross-appealing against those who might share responsibility for the water rights claims.

¶ 9 For the foregoing reasons, we hold that we do not have jurisdiction to review Jensen’s claims relating to the partial summary judgment. We, therefore, grant IPA’s motion to limit the scope of this appeal and do not address Jensen’s easement or water rights arguments.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State of Utah v. Ralph Leroy Menzies
2025 UT 52 (Utah Supreme Court, 2025)
State v. Menzies
2025 UT 38 (Utah Supreme Court, 2025)
Metropolitan Water v. Sorf
2023 UT App 146 (Court of Appeals of Utah, 2023)
11500 Space Center v. Private Capital Group
2022 UT App 92 (Court of Appeals of Utah, 2022)
Zion Village Resort v. Pro Curb USA
2020 UT App 167 (Court of Appeals of Utah, 2020)
In re Adoption of B.B.
2020 UT 53 (Utah Supreme Court, 2020)
Wilson v. Sanders
2019 UT App 126 (Court of Appeals of Utah, 2019)
Pulham v. Kirsling
443 P.3d 1217 (Utah Supreme Court, 2019)
State v. Hernandez
2018 UT 41 (Utah Supreme Court, 2018)
Pulham v. Kirsling
2018 UT App 65 (Court of Appeals of Utah, 2018)
State v. Johnson
2017 UT 70 (Utah Supreme Court, 2017)
Adoption B.B. v. R.K.B.
2017 UT 59 (Utah Supreme Court, 2017)
CDC Restoration & Construction, LC v. Tradesmen Contractors, LLC
2016 UT App 43 (Court of Appeals of Utah, 2016)
Bad Ass Coffee Co. of Hawaii v. Royal Aloha International, LLC
2015 UT App 303 (Court of Appeals of Utah, 2015)
State v. Nelson
2015 UT 62 (Utah Supreme Court, 2015)
Wisan v. City of Hildale
2014 UT 20 (Utah Supreme Court, 2014)
Harris v. ShopKo
2013 UT 34 (Utah Supreme Court, 2013)
Harris v. Shopko Stores, Inc.
2013 UT 34 (Utah Supreme Court, 2013)
Express Recovery Services v. Wall
2012 UT App 138 (Court of Appeals of Utah, 2012)
EXPRESS RECOVERY SERVICES, INC. v. Wall
2012 UT App 138 (Court of Appeals of Utah, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
1999 UT 10, 977 P.2d 474, 362 Utah Adv. Rep. 3, 1999 Utah LEXIS 11, 1999 WL 45189, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jensen-v-intermountain-power-agency-utah-1999.