Jeffrey M. Brown Associates, Inc. v. CRK Contracting of Suffolk, Inc.

124 F. Supp. 2d 895, 2000 U.S. Dist. LEXIS 17870, 2000 WL 1843780
District Court, E.D. Pennsylvania·Decided December 11, 2000·No. CIV. A. 99-5487·Published

Opinion

FINDINGS OF FACT AND CONCLUSIONS OF LAW

KATZ, Senior District Judge.

This case arises out of contract disputes with respect to three construction projects.

I.FINDINGS OF FACT

A. General Background

1. Plaintiff Jeffrey M. Brown, Associates, Inc., (“JMB”) is a general contractor. In general, a general contractor is hired by a building owner to manage the process of constructing the building. Defendant CRK Contracting of Suffolk, Inc. (“CRK”) is a company that specializes in the electrical components of a construction project.

2. The three construction projects at issue in this case are located in New York State, and are known as the “Flatbush” project, the “Glen Oaks” project, and the “Jericho” project. Each project involved the construction of a store that were eventually to be occupied by a merchant known commonly as Caldor.

3. With respect to each of these projects, JMB was responsible for negotiating and implementing individual subcontracts for different components of the construction work. In this capacity, JMB hired CRK as a subcontractor on each of the three projects to perform certain electrical work within certain time frames. JMB was also responsible to the project owner for providing proper supervision, coordination and overall organization of the various components of each project, so as to ensure the completion of the entire project within a specified time period required by the owner.

4. In this action, plaintiff JMB alleges that defendant CRK breached each of its three contracts by failing to perform its electrical work in a timely manner, which in turn caused delays in the construction of other components of the building. JMB seeks to recover certain monetary amounts from the CRK under specific contractual provisions that essentially track the common law of contracts in Pennsylvania, *897 which is the governing law by the express terms of the contracts. JMB’s claims largely involve expenditures incurred by it in hiring others to complete the electrical work within a time frame acceptable to the owners of the projects. Many of JMB’s claims are described as “back charges,” a term generally used in the construction field to describe such costs of completion.

5. Three witnesses offered live testimony in the course of this trial. Also submitted were transcripts of testimony given by six other witnesses at a previous trial, which also concerned contractual disputes with respect to these projects and which was conducted over the course of six weeks by the Supreme Court of New York (CivAct. No. 97-10678). Key witnesses in the trial before this court include Jeffrey M. Brown, Chief Executive Officer of plaintiff company JMB; A1 Sampson, the project superintendent for JMB on the Glen Oaks project; and Robert Kohlmeyer, the president of defendant company CRK. Voluminous exhibits from the previous trial were also submitted, as well as numerous additional exhibits generated specifically for this trial.

B. The Flatbush Project

6. In this action with respect to the Flat-bush project, JMB seeks to recover, on the basis of the alleged default by CRK, the actual costs of material and labor to complete CRK’s work, plus profit, attorney’s fees and costs of supervision. JMB also seeks to recover 26 back charges based upon numerous grounds, including CRK’s alleged failure to remove debris generated from CRK’s work and left at the site; overtime charges incurred by other subcontractors who allegedly could not perform their duties in a timely fashion because of delays in electrical work; damage allegedly done by CRK to other work on the building; and CRK’s alleged failure to provide certain equipment.

7. Work on the Flatbush project, including electrical work by CRK, was underway by the late fall of 1994.

8. On or about December 22, 1994, a precast concrete beam being lifted by a crane at the project site was dropped, and the appropriate government agency ordered the project to be shut down temporarily for safety reasons. Work reopened on January 6, 1995.

9. On January 13, 1995, there was another precast concrete accident, and the job was again shut down by the government. Work resumed on or about January 31,1995.

10. JMB declared CRK in default of its contract obligations by letter dated April 3, 1995 based on the alleged failure of CRK to perform its electrical work in accordance with the schedule as modified after the project shutdowns. At trial, CRK did not dispute that the entire project, including the electrical work, was behind schedule, but offered evidence that the delay of the entire project was due to circumstances beyond its control.

11. After CRK received the letter notifying that it was in default, CRK continued to work on the project. The electrical work was eventually completed to the satisfaction of the owner with the assistance of a second electrical subcontractor hired by JMB.

12. Mr. Brown testified at trial that the main blame for the delay in the completion of the project lay with CRK. Mr. Brown’s testimony, however, is not credible, as he took contrary positions at trial as to the status of progress on the job, undercutting the believability of his testimony.

13. The main reasons for the delay were the precast concrete accidents and other difficulties in scheduling, coor *898 dination, and conveying information. Mr. Brown correctly conceded at trial that the job delay was due to a large extent to the two shutdowns by the local government caused by the precast concrete accidents.

14. CRK’s electrical work was behind schedule for numerous other reasons as well. For example, the testimony of Mr. Kohlmeyer established that the drawings for the job were constantly being revised, including those required to install the site lighting and those required to implement the Energy Management System. These revisions interfered with the ability of CRK to timely perform its duties; in fact, before the electrical subcontractor had even received the final plans and specifications drawings necessary to complete its work, it received notice of its alleged “default.”

Free access — add to your briefcase to read the full text and ask questions with AI

Jeffrey M. Brown Associates, Inc. v. CRK Contracting of Suffolk, Inc., 124 F. Supp. 2d 895, 2000 U.S. Dist. LEXIS 17870, 2000 WL 1843780 (E.D. Pa. 2000).

124 F. Supp. 2d 895 (Jeffrey M. Brown Associates, Inc. v. CRK Contracting of Suffolk, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Craig Coal Mining Co. v. Romani
513 A.2d 437 (Supreme Court of Pennsylvania, 1986)