Jeffrey M. Brown Associates, Inc. v. CRK Contracting of Suffolk, Inc.

100 F. Supp. 2d 323, 2000 U.S. Dist. LEXIS 8222, 2000 WL 772820
CourtDistrict Court, E.D. Pennsylvania
DecidedJune 14, 2000
DocketCIV. A. 99-5487
StatusPublished

This text of 100 F. Supp. 2d 323 (Jeffrey M. Brown Associates, Inc. v. CRK Contracting of Suffolk, Inc.) is published on Counsel Stack Legal Research, covering District Court, E.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jeffrey M. Brown Associates, Inc. v. CRK Contracting of Suffolk, Inc., 100 F. Supp. 2d 323, 2000 U.S. Dist. LEXIS 8222, 2000 WL 772820 (E.D. Pa. 2000).

Opinion

MEMORANDUM & ORDER

KATZ, Senior District Judge.

Before the court are plaintiffs motion for partial summary judgment on defendant’s counterclaims and defendant’s motion for sanctions and for partial summary judgment.

I. Background

Plaintiff Jeffrey M. Brown Associates, Inc. (JMB) provides construction management services. In 1994 and 1995, JMB entered into three contracts with three different owners to construct Caldor department stores. These three projects have come to be known as the Flatbush Project, the Glen Oaks Project, and the Jericho Project. JMB, in turn, entered into three subcontracts with the defendant, CRK Contracting of Suffolk, Inc. (CRK).

These prosaic beginnings led to a Dickensian series of lawsuits. The first suit, known as the Hartford Action, began in 1996 in New York state court, when CRK sued Hartford Insurance Company, JMB’s payment bond.surety, seeking to recover $505,335 for electrical work it had allegedly performed on the Flatbush Project but for which it had allegedly not been paid. JMB was not a party to this action. On July 3, 1997, the jury found that CRK was not entitled to recover any monies under the terms of the subcontract with JMB, and a defense verdict was entered in favor of Hartford. This decision was affirmed on appeal.

A second lawsuit, known as the Forest City Action, commenced in September 1997, also in a New York state court. In this action, CRK sued, inter alia, JMB; Forest City, the owner of the Flatbush Project; the law firm and an attorney that represented JMB; Jeffrey Brown, JMB’s principal; and Robert Beyea, a JMB employee. This litigation stemmed from a settlement by which JMB and Forest City ended their own lawsuit. The settlement established a trust fund to pay licensees and future lienors. CRK again asserted various claims pertaining to the Flatbush Project, alleging that it was a beneficiary of the settlement and entitled to payment under its terms. On April 12, 1998, the state court granted summary judgment in favor of the defendants based on res judi- *325 cata and collateral estoppel. This decision was also affirmed on appeal.

A third group of lawsuits have also been dismissed. In June 1996, JMB sued CRK in this district alleging deficient performance on the Flatbush Project. Meanwhile, CRK had already filed two lawsuits pertaining to the Glen Oaks and Jericho Projects in the New York state courts. 1 At the time these three actions were pending, the Forest City and Hartford Actions were on appeal. CRK and JMB entered into an agreement entitled the Settlement and Standstill Agreement (Standstill Agreement), see Def. Ex. G, that provided in part that the pending actions would be dismissed without prejudice. If CRK did not prevail on appeal on either the Hartford or Forest City Action, JMB was to commence suit against CRK in this court, and CRK was to allege its counterclaims. CRK did not, in fact, prevail, and JMB brought this lawsuit as a plaintiff.

JMB’s complaint contains three counts seeking breach of contract damages for the Flatbush, Glen Oaks, and Jericho Projects. CRK’s first six counterclaims seek payment for each of the same projects, and the final two counterclaims make claims for the Flatbush Project based on the JMB Forest City settlement.

II. Discussion

Plaintiffs motion for partial summary judgment argues that res judicata and/or collateral estoppel principles bar CRK’s first, second, seventh, and eighth counterclaims pertaining to the Flatbush Project. Defendant’s motion seeks to strike the complaint under Federal Rules of Civil Procedure 11 and 37 as a sanction for alleged violations of this court’s orders and for alleged efforts to mislead the court; it also requests partial summary regarding monies owed for the Jericho Project.

A. Res Judicata and Collateral Estop-pel 2

The Full Faith and Credit statute, 28 U.S.C. § 1738, requires that this court give a “prior state judgment the same effect as would the adjudicating state.” Gregory v. Chehi, 843 F.2d 111, 116 (3d Cir.1988). As the Hartford and Forest City Actions were decided by New York state courts applying New York state law, this court will look to New York’s res judicata and collateral estoppel law.

1. Standards

Under New York’s transactional approach, res judicata, or claim preclusion, bars the litigation of a later claim finally decided on the merits arising out of the same facts as an earlier action, even if the later claim is based on different legal theories or seeks different relief. See Burgos v. Hopkins, 14 F.3d 787, 790 (2d Cir.1994); Vega v. University of N.Y., 67 F.Supp.2d 324, 333 (S.D.N.Y.1999); see also Jacobson v. Fireman’s Fund Ins. Co., 111 F.3d 261, 265 (2d Cir.1997) (noting that res judicata applies to privies as well as to parties to original action). Res judicata will not bar a later action if the first forum “did not have the power to award the full measure of relief sought in the later litigation” or if the party was prevented, whether by statute or otherwise, from advancing a particu *326 lar legal theory. Burgos, 14 F.3d at 790 (citations omitted). However, if the party could have advanced a particular claim but did not do so, res judicata will apply. See id.; Parker v. Corbisiero, 825 F.Supp. 49, 54 (S.D.N.Y.1993); see also Ferris v. Cuevas, 118 F.3d 122, 126 (2d Cir.1997) (finding that res judicata barred subsequent action based on constitutional theory when earlier action did not raise that theory but was based on same transaction). Put another way, res judicata will bar later claims based on the same “factual grouping” if: “(1) the claims could have been raised in the initial forum, and (2) the initial forum had the power to award the full measure of relief sought in the later litigation.” Parker, 825 F.Supp. at 54 (citations omitted); see also Jacobson, 111 F.3d at 265 (noting same).

Collateral estoppel, or issue preclusion, “precludes a party from relitigating in a subsequent action or proceeding an issue clearly raised in a prior action or proceeding and decided against that party or those in privity, whether or not the tribunals or causes of action are the same.” Burgos, 14 F.3d at 792 (citations omitted).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Parker v. Corbisiero
825 F. Supp. 49 (S.D. New York, 1993)
Wallace v. 600 Partners Co.
658 N.E.2d 715 (New York Court of Appeals, 1995)
County of Suffolk v. Long Island Lighting Co.
87 F. Supp. 2d 187 (E.D. New York, 2000)
Space Imaging Europe, Ltd. v. Space Imaging L.P.
38 F. Supp. 2d 326 (S.D. New York, 1999)
Vega v. State University of New York Board of Trustees
67 F. Supp. 2d 324 (S.D. New York, 1999)
B. R. DeWitt, Inc. v. Hall
225 N.E.2d 195 (New York Court of Appeals, 1967)
Trane Co. v. N. Robinson Construction, Inc.
61 A.D.2d 360 (Appellate Division of the Supreme Court of New York, 1978)
New Paltz Central School District v. Reliance Insurance
97 A.D.2d 566 (Appellate Division of the Supreme Court of New York, 1983)
Corto v. Lefrak
203 A.D.2d 94 (Appellate Division of the Supreme Court of New York, 1994)
Kitson v. Atlantic Refining & Marketing Corp.
227 A.D.2d 971 (Appellate Division of the Supreme Court of New York, 1996)
Reda v. Eastman Kodak Co.
233 A.D.2d 914 (Appellate Division of the Supreme Court of New York, 1996)
Reda v. Eastman Kodak Co.
233 A.D.2d 914 (Appellate Division of the Supreme Court of New York, 1996)
Gerol v. G & H Energy Maintenance Co.
239 A.D.2d 387 (Appellate Division of the Supreme Court of New York, 1997)
CRK Contracting of Suffolk, Inc. v. Hartford Fire Insurance
260 A.D.2d 529 (Appellate Division of the Supreme Court of New York, 1999)
CRK Contracting of Suffolk, Inc. v. Jeffrey M. Brown & Associates, Inc.
260 A.D.2d 530 (Appellate Division of the Supreme Court of New York, 1999)
Burgos v. Hopkins
14 F.3d 787 (Second Circuit, 1994)
Ferris v. Cuevas
118 F.3d 122 (Second Circuit, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
100 F. Supp. 2d 323, 2000 U.S. Dist. LEXIS 8222, 2000 WL 772820, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jeffrey-m-brown-associates-inc-v-crk-contracting-of-suffolk-inc-paed-2000.