Jeffery Lake Dev. v. Central Neb. Pub. Power

CourtNebraska Court of Appeals
DecidedJune 7, 2016
DocketA-15-277
StatusUnpublished

This text of Jeffery Lake Dev. v. Central Neb. Pub. Power (Jeffery Lake Dev. v. Central Neb. Pub. Power) is published on Counsel Stack Legal Research, covering Nebraska Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jeffery Lake Dev. v. Central Neb. Pub. Power, (Neb. Ct. App. 2016).

Opinion

IN THE NEBRASKA COURT OF APPEALS

MEMORANDUM OPINION AND JUDGMENT ON APPEAL (Memorandum Web Opinion)

JEFFREY LAKE DEV. V. CENTRAL NEB. PUB. POWER

NOTICE: THIS OPINION IS NOT DESIGNATED FOR PERMANENT PUBLICATION AND MAY NOT BE CITED EXCEPT AS PROVIDED BY NEB. CT. R. APP. P. § 2-102(E).

JEFFREY LAKE DEVELOPMENT, INC., A NEBRASKA NONPROFIT CORPORATION, AND MIDWAY WILDLIFE & RECREATION CLUB, A NEBRASKA NONPROFIT CORPORATION, ET AL., APPELLANTS AND CROSS-APPELLEES.

V.

CENTRAL NEBRASKA PUBLIC POWER AND IRRIGATION DISTRICT, A NEBRASKA PUBLIC CORPORATION, APPELLEE AND CROSS-APPELLANT.

Filed June 7, 2016. No. A-15-277.

Appeal from the District Court for Lincoln County: RICHARD A. BIRCH, Judge. Affirmed. Steve Windrum, of Malcom, Nelsen & Windrum, L.L.C., for appellants. David J.A. Bargen, of Rembolt Ludtke, L.L.P., for appellee.

MOORE, Chief Judge, and INBODY and RIEDMANN, Judges. RIEDMANN, Judge. INTRODUCTION This case involves lakeside land owned by the Central Nebraska Public Power and Irrigation District (Central) that lies adjacent to hydroelectric power projects. Central leased portions of this lakeside to Jeffrey Lake Development, Inc. (Jeffrey) and Midway Wildlife & Recreation Club (Midway) for development of private recreational cabins. These leases have been the subject of significant litigation over the past 20 years. The primary issue of the current appeal is the meaning of contractual language setting elevation restrictions for certain types of construction on the leased land. The district court interpreted the language of the lease to prohibit construction of cabins, including subterranean support structures, below stated elevation levels.

-1- However, the district court also construed our holdings from prior appeals to allow repair or replacement of nonconforming structures that were the subject of a prior injunction against lease enforcement. Following our review of the record and the parties’ arguments, we affirm the judgment of the district court. BACKGROUND The leases at issue in this case have been the subject of considerable litigation, reaching the Court of Appeals or the Nebraska Supreme Court at least 6 prior times. We most recently considered the leases between the parties in Jeffrey Lake Dev., Inc. v. Cent. Nebraska Pub. Power & Irrigation Dist., No. A-09-996, 2010 WL 2990040 (Neb. App. July 27, 2010) (hereinafter “Jeffrey VI”). We briefly recount the background of this appeal here, and will discuss additional details of the leases and prior litigation in the analysis section below as needed. Central entered into leases with Jeffrey and Midway in 1980 and 1981, respectively. The leases are similar, with many identical provisions, and provide for Jeffrey and Midway to lease residential cabin areas and lots above the shorelines of each lake. The leases extend for a primary term of 31 years and contain an automatic renewal provision. In Jeffrey VI, Central attempted to terminate both leases based in part upon alleged elevation violations of various structures. We determined that because Central had not previously enforced those violations, it was enjoined from declaring a forfeiture of either lease based on any of the alleged violations on which it adduced evidence at trial. Jeffrey Lake Dev., Inc. v. Cent. Nebraska Pub. Power & Irrigation Dist., No. A-09-996, 2010 WL 2990040 (Neb. App. July 27, 2010). However, we determined that Central could enforce future lease violations. Id. The parties now dispute the meaning of the elevation requirements in the leases, as well as the extent of the injunction outlined in Jeffrey VI. Both leases prohibit some types of construction at elevations below a specified “freeboard elevation” -- that is, an elevation somewhat above the high water level of the lakes. This restriction is intended to prevent flood damage that would harm structures and the hydroelectric project. At trial, Jeffrey and Midway submitted testimony from several of their sublessees to whom Central has denied building permits based on its interpretation of the leases’ elevation restrictions. Timothy Dilley testified that he is a sub-leaseholder on Jeffrey Lake. He entered into his sublease in 2010 with the hope of building a retirement home on the property. When Dilley executed the sublease for his lot, the lot contained a garage, an electrical service, a septic system, a well, several hydrants, and a concrete pad approximately 9′ wide by 20′ long. The lot had previously contained a smaller modular home, but that home had been destroyed and removed from the premises before Dilley obtained his sublease. Dilley submitted a permit application to Central for retaining walls, a driveway, and a larger septic system to support the house he hoped to build. The proposed septic system would replace the existing, smaller septic system in approximately the same location. Central denied the septic system application because the subterranean tank and drain field proposed by Dilley extend below the Jeffrey Lake lease’s freeboard elevation of 2,764 feet above sea level. The Dilleys’ permit for a driveway was initially denied, then approved provided that Dilley use fill dirt to raise the elevation of the driveway to 2,764 feet. Central informed Dilley that retaining wall footings also had to be above 2,764 feet in elevation. Central invited Dilley to re-submit conceptual

-2- drawings of the retaining walls, driveway, house, and septic tank, stating that it believed there was a “good chance” everything would be approved, so long as the septic tank and drain field were modified to be constructed entirely above 2,764 feet in elevation. Central employees testified that they believed that alternative locations or alternative septic system types would have met Central’s requirements and allowed the Dilleys to build the size of septic system they desired. Central suggested that an above-ground holding tank system recently installed on a lot at Midway Lake might provide an example of a system that would meet elevation and setback requirements. However, Dilley and his sewage contractor testified to their belief that alternative sewage system locations were not feasible and that an above-ground holding tank system would require more frequent pumping and be more susceptible to freezing. Dilley did not submit an amended application to Central. Dell Shepherd testified that he is a sub-leaseholder at Jeffrey Lake and has been since 1981. In 2013, Shepherd submitted an application for an addition to his cabin and modification of his sewage, heating, and air conditioning systems. His applications were initially approved subject to an elevation inspection. After inspection, Central informed Shepherd that he could not build as proposed because of elevation restrictions in the Central-Jeffrey lease. Central suggested an above-ground holding tank instead of a septic tank to avoid elevation issues. Central also suggested that a slab foundation rather than a block foundation “might be a possibility” for his cabin addition. Shepherd’s contractor felt that a slab foundation would be inappropriate because the rest of the cabin was block foundation. Shepherd testified that he was uninterested in submitting a re-application after the denials. Evidence in the record also reflects that in 2013 Central denied another Jeffrey Lake sub-leaseholder a permit to demolish and replace a home on her lot because of elevation requirements in the lease as well as horizontal setback-from-the-shoreline requirements contained in Central’s permitting procedures. We note that the validity of the horizontal setbacks in the permitting procedures are not at issue on this appeal. Evidence in the record also reflects that at least one sub-leaseholder’s application to construct an underground sprinkler system was denied because of elevation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vlach v. Vlach
835 N.W.2d 72 (Nebraska Supreme Court, 2013)
Abboud v. Lakeview, Inc.
466 N.W.2d 442 (Nebraska Supreme Court, 1991)
Spanish Oaks, Inc. v. Hy-Vee, Inc.
655 N.W.2d 390 (Nebraska Supreme Court, 2003)
Lambert v. Holmberg
712 N.W.2d 268 (Nebraska Supreme Court, 2006)
Leseberg v. Meints
399 N.W.2d 784 (Nebraska Supreme Court, 1987)
Evertson v. City of Kimball
767 N.W.2d 751 (Nebraska Supreme Court, 2009)
Donaldson v. Farm Bureau Life Insurance
440 N.W.2d 187 (Nebraska Supreme Court, 1989)
Hogelin v. City of Columbus
741 N.W.2d 617 (Nebraska Supreme Court, 2007)
Wetovick v. County of Nance
782 N.W.2d 298 (Nebraska Supreme Court, 2010)
In re Rolf H. Brennemann Testamentary Trust
288 Neb. 389 (Nebraska Supreme Court, 2014)
Labenz v. Labenz
291 Neb. 455 (Nebraska Supreme Court, 2015)
Facilities Cost Mgmt. Group v. Otoe Cty. Sch. Dist.
291 Neb. 642 (Nebraska Supreme Court, 2015)
Stekr v. Beecham
291 Neb. 883 (Nebraska Supreme Court, 2015)
Omaha Police Union Local 101 v. City of Omaha
292 Neb. 381 (Nebraska Supreme Court, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
Jeffery Lake Dev. v. Central Neb. Pub. Power, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jeffery-lake-dev-v-central-neb-pub-power-nebctapp-2016.