JD JAMES CONSTRUCTION, LLC VS. PDP LANDSCAPING, LLC (L-2404-16, BURLINGTON COUNTY AND STATEWIDE)

CourtNew Jersey Superior Court Appellate Division
DecidedSeptember 18, 2020
DocketA-4903-18T3
StatusUnpublished

This text of JD JAMES CONSTRUCTION, LLC VS. PDP LANDSCAPING, LLC (L-2404-16, BURLINGTON COUNTY AND STATEWIDE) (JD JAMES CONSTRUCTION, LLC VS. PDP LANDSCAPING, LLC (L-2404-16, BURLINGTON COUNTY AND STATEWIDE)) is published on Counsel Stack Legal Research, covering New Jersey Superior Court Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
JD JAMES CONSTRUCTION, LLC VS. PDP LANDSCAPING, LLC (L-2404-16, BURLINGTON COUNTY AND STATEWIDE), (N.J. Ct. App. 2020).

Opinion

NOT FOR PUBLICATION WITHOUT THE APPROVAL OF THE APPELLATE DIVISION This opinion shall not "constitute precedent or be binding upon any court ." Although it is posted on the internet, this opinion is binding only on the parties in the case and its use in other cases is limited. R. 1:36-3.

SUPERIOR COURT OF NEW JERSEY APPELLATE DIVISION DOCKET NO. A-4903-18T3

JD JAMES CONSTRUCTION, LLC,

Plaintiff-Respondent,

v.

PDP LANDSCAPING, LLC,

Defendant,

and

BDP EXCAVATING, INC., PHILIP CALABRESE, JR., PHILIP CALABRESE, III, and PERRY DORTONE,

Defendants-Appellants. ____________________________

Submitted August 25, 2020 – Decided September 18, 2020

Before Judges Alvarez and Gooden Brown.

On appeal from the Superior Court of New Jersey, Law Division, Burlington County, Docket No. L-2404-16. Steven A. Berkowitz & Associates, PC, attorneys for appellants (Steven A. Berkowitz, on the briefs).

Hyland, Levin, Shapiro, LLP, attorneys for respondent (Daniella Gordon, on the brief).

PER CURIAM

Defendants BDP Excavating, Inc. (BDP), Philip Calabrese, Jr., Philip

Calabrese, III, and Perry Dortone appeal from the June 27, 2019 judgment

entered in favor of plaintiff JD James Construction, LLC, following a bench

trial. Pursuant to the judgment, defendants were held jointly and severally liable

for $94,848.78, and assessed $10,000 in attorney's fees against BDP only. We

affirm.

We derive the following facts from the trial record, adopting by reference

the "factual conclusions reached by the trial court because we are mindful of,

and readily observe, the principle that our scope of review of a judgmen t in a

non-jury case is extremely limited." Nordstrom v. Lyon, 424 N.J. Super. 80, 86

(App. Div. 2012) (citing Seidman v. Clifton Sav. Bank, S.L.A., 205 N.J. 150,

169 (2011)).

On November 18, 2015, PDP Landscaping, LLC (PDP) entered into a

written agreement with Warfel Construction Company (the Warfel contract) for

PDP to perform work as a subcontractor for a commercial construction project

A-4903-18T3 2 in Maple Shade for which Warfel had been hired as the general contractor (the

project). Signatories on behalf of PDP for the Warfel contract included

Calabrese, III, as PDP's "Executive," his father, Calabrese, Jr., as the

"Subcontractor Safety Director," and Dortone, as the "Project Manager."

Thereafter PDP's principals, acting under the entity names of BDP and

"PDP Enterprises,"1 hired plaintiff to perform concrete construction work for the

project, by virtue of which the entities executed a written agreement dated

February 29, 2016 (the subcontract). The subcontract provided that plaintiff was

to install "[c]oncrete curbing[,] . . . concrete sidewalks[,] and associated concrete

flat work" with payment due to plaintiff "within [thirty] days of completion" of

the agreed upon work. Calabrese, Jr. and Dortone signed the subcontract on

behalf of defendants under the titles "President PDP" and "Vice [P]resident of

sales/project manager," respectively, and David Peluse signed on behalf of

plaintiff as its "President" and sole principal.

Throughout 2016, after completing work on the project as required under

the subcontract, plaintiff submitted three invoices to Dortone for payment as

1 Calabrese, Jr. testified that BDP, which had not done business since 2005, and PDP both operated out of his house, shared the same phone number, and shared the same e-mail address. He also acknowledged that BDP's Facebook page posted pictures of PDP's jobs, including pictures of the project. A-4903-18T3 3 follows: (1) June 10, 2016 for $55,568; (2) July 16, 2016 for $30,268; and (3)

August 17, 2016 for $49,588. The August 17 invoice, which was the final

invoice submitted upon completion of the work in full, indicated the total

amount of $135,424 was "past due." Peluse testified that none of the "invoices

[were] ever rejected" by defendants either orally or in writing, and no deficiency

in the performance of the work was ever reported. Nonetheless, Peluse never

received payment for any of the work performed. According to Peluse, when

the invoices were not timely paid, he "sent . . . emails to . . . Dortone" and "called

. . . Dortone with no results." He also "went to the site to personally talk to

[Calabrese, Jr.]" about the unpaid invoices. However, Calabrese, Jr. denied

having any conversations with Peluse regarding non-payment.

Under the Warfel contract, Warfel required PDP to "insure that all sub-

subcontractors . . . [were] paid all amounts due in connection with the

performance of th[e] subcontract." PDP also agreed to submit to Warfel with

their payment applications, claim releases and lien waivers certifying "that all

amounts owed in connection with performance of th[e] subcontract [were] paid."

Following receipt of plaintiff's first two invoices, PDP submitted corresponding

payment applications and accompanying lien waivers to Warfel on June 21 and

July 22, 2016. In those payment applications, in addition to listing various other

A-4903-18T3 4 incurred expenses, Dortone "certif[ied]" that the "[c]urb" work had been

performed.

Although PDP was paid over half a million dollars by Warfel over the

course of the project,2 including funds received in direct response to the payment

applications certifying that the curb work had been performed, it was undisputed

that PDP failed to make any payments to plaintiff and instead used the funds for

other business purposes. Peluse testified that when he told Calabrese, Jr. he had

"done everything . . . asked of [him] and . . . [had not] received a penny[,]"

Calabrese, Jr. responded that defendants "ha[d not] received any money" from

Warfel. Prior to this conversation, however, Peluse had spoken "to

representatives through Warfel" who confirmed "through scheduled

documentation" that PDP had "already billed for [plaintiff's] services." 3

According to Calabrese, Jr., PDP was not paid a balance of over $268,000

remaining on the Warfel contract, inferring that plaintiff's funds were included

in the unpaid balance.

2 The July 22, 2016 lien waiver specified that PDP had "been paid $568,986.89" by Warfel for all work performed through June 1, 2016. 3 We note that the judge "indicate[d] for the record that [he] underst[oo]d the hearsay aspect of [Peluse's testimony]" and remarked that these statements were "just being offered as an explanation."

A-4903-18T3 5 On July 5, 2018, plaintiff filed an amended complaint against PDP and

BDP alleging breach of contract, unjust enrichment, and violation of the New

Jersey Prompt Payment Act, N.J.S.A. 2A:30A-1 to -2 (NJPPA). By seeking to

pierce each entity's corporate veil, the complaint also alleged fraud against

Calabrese, Jr., Calabrese, III, and Dortone, in their individual capacities as well

as against each entity. PDP filed for bankruptcy on August 31, 2018, in the

United States Bankruptcy Court for the Eastern District of Pennsylvania

(bankruptcy court), and plaintiff was listed among the creditors in PDP's

bankruptcy filing. Pursuant to the automatic stay instituted by the bankruptcy

court, plaintiff's breach of contract, unjust enrichment, and NJPPA claims

against defendants were no longer viable, leaving only the veil-piercing and

fraud claims.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cristen M. Gleason v. Norwest Mortgage, Inc
243 F.3d 130 (Third Circuit, 2001)
Jewish Center of Sussex Cty. v. Whale
432 A.2d 521 (Supreme Court of New Jersey, 1981)
Ocean Cape Hotel Corp. v. Masefield Corp.
164 A.2d 607 (New Jersey Superior Court App Division, 1960)
Mountain Hill, LLC v. Tp. of Middletown
945 A.2d 59 (New Jersey Superior Court App Division, 2008)
Stochastic Decisions v. DiDomenico
565 A.2d 1133 (New Jersey Superior Court App Division, 1989)
Lo Bosco v. Kure Engineering Ltd.
891 F. Supp. 1020 (D. New Jersey, 1995)
Weil v. Express Container Corp.
824 A.2d 174 (New Jersey Superior Court App Division, 2003)
Cesare v. Cesare
713 A.2d 390 (Supreme Court of New Jersey, 1998)
Albright v. Burns
503 A.2d 386 (New Jersey Superior Court App Division, 1986)
Matter of Trust Created by Agreement Dated December 20, 1961
944 A.2d 588 (Supreme Court of New Jersey, 2008)
Alloway v. General Marine Industries, L.P.
695 A.2d 264 (Supreme Court of New Jersey, 1997)
Township of West Windsor v. Nierenberg
695 A.2d 1344 (Supreme Court of New Jersey, 1997)
Nolan v. Lee Ho
577 A.2d 143 (Supreme Court of New Jersey, 1990)
Lipsit v. Leonard
315 A.2d 25 (Supreme Court of New Jersey, 1974)
Van Dam Egg Co. v. Allendale Farms, Inc.
489 A.2d 1209 (New Jersey Superior Court App Division, 1985)
Spring Motors Distributors, Inc. v. Ford Motor Co.
489 A.2d 660 (Supreme Court of New Jersey, 1985)
Saltiel v. GSI Consultants, Inc.
788 A.2d 268 (Supreme Court of New Jersey, 2002)
New Mea Const. Corp. v. Harper
497 A.2d 534 (New Jersey Superior Court App Division, 1985)
Broadway Maintenance Corp. v. Rutgers
447 A.2d 906 (Supreme Court of New Jersey, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
JD JAMES CONSTRUCTION, LLC VS. PDP LANDSCAPING, LLC (L-2404-16, BURLINGTON COUNTY AND STATEWIDE), Counsel Stack Legal Research, https://law.counselstack.com/opinion/jd-james-construction-llc-vs-pdp-landscaping-llc-l-2404-16-burlington-njsuperctappdiv-2020.