JC Trahan Drilling Contractor, Inc. v. Cockrell

225 So. 2d 599, 34 Oil & Gas Rep. 384, 1969 La. App. LEXIS 5819
CourtLouisiana Court of Appeal
DecidedJuly 2, 1969
Docket7737
StatusPublished
Cited by7 cases

This text of 225 So. 2d 599 (JC Trahan Drilling Contractor, Inc. v. Cockrell) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
JC Trahan Drilling Contractor, Inc. v. Cockrell, 225 So. 2d 599, 34 Oil & Gas Rep. 384, 1969 La. App. LEXIS 5819 (La. Ct. App. 1969).

Opinion

225 So.2d 599 (1969)

J. C. TRAHAN DRILLING CONTRACTOR, INC.
v.
E. COCKRELL, Jr.

No. 7737.

Court of Appeal of Louisiana, First Circuit.

July 2, 1969.
Rehearing Denied August 28, 1969.

*600 J. C. Smith and Robert K. Mayo, Shreveport, Aycock, Horne, Caldwell & Coleman, by Jack C. Caldwell, Franklin, Breazeale, Sachse & Wilson, by Victor A. Sachse, Baton Rouge, for appellant.

O'Neal, Waitz & Henderson, by Joseph L. Waitz, Houma, for appellee.

Before LANDRY, SARTAIN and MARCUS, JJ.

*601 PAUL B. LANDRY, Jr., Judge.

J. C. Trahan Drilling Contractor, Inc. (Contractor) instituted this action against defendant E. Cockrell, Jr., a mineral lease owner (Owner), to recover a large sum of money for expenses incurred in the drilling of an oil well pursuant to a written drilling contract between the parties. The principal claim is for the expense of "fishing operations" required to extricate lodged drill pipe. Plaintiff also seeks to recover the cost of reaming the hole upon defendant's alleged arbitrary and capricious demand and for the cost of leveling the derrick, said latter item reputedly being the owner's obligation under the terms of the contract. The trial court rejected plaintiff's claims and plaintiff has appealed. We find no error in the judgment rendered by the trial court and affirm its decision.

The primary dispute between the parties concerns the use at defendant's suggestion, of a product known as Protectomagic as an additive to the drilling mud required for the boring involved. In substance, Contractor maintains use of Protectomagic caused the drill pipe to stick in the hole thereby necessitating five separate costly fishing operations. Defendant denies the Protectomagic caused the pipe to stick but contends the pipe lodged due to a condition known as differential pressure sticking. Defendant third partied Oil Base, Incorporated, manufacturer of Protectomagic, and has, out of an abundance of precaution appealed the judgment of the trial court dismissing its demand against said third party defendant.

Although the fundamental contentions of the parties are easily put as above noted, an understanding of the premises on which the opposing views are based requires relation of certain undisputed engineering principles and customs prevailing in the oil well drilling industry.

On November 30, 1965, Contractor entered into an agreement with Owner to drill a well near Patterson, St. Mary Parish. In essence the agreement provided for a "turnkey job" at a unit price of $.94 per foot to a depth of 13,500 feet. Below 13,500 feet payment for drilling services was to be on a daily basis. It is conceded plaintiff has been paid this price in full. Drilling apparently began shortly after the contract date and seemingly progressed without incident until late December, 1965, at which time it was determined the rate of penetration should be increased. After some discussion among the work representatives of both parties, it was decided, primarily by Cockrell's drilling superintendent who was in charge of the mud program, that the product known as Protectomagic be introduced into the mud mixture to accelerate penetration. Accordingly, on December 20th, a quantity of Protectomagic was added to the mud compound. Subsequently, the first difficulty was encountered at approximately 5:00 A.M., December 25, when in attempting to raise the drill pipe out of the hole, the pipe became lodged to such extent special operations were required to set it free. These procedures, commonly referred to in the industry as "fishing", involve considerable expense. Efforts to dislodge the pipe were not completed until January 10, 1966, at which time drilling resumed.

Plaintiff seeks recovery of $48,435.51 spent in dislodging the pipe, $10,606.35, representing the cost of reaming the well, and $827.50 expended to level the derrick when the fishing and remaining procedures were completed. Appellant makes three basic contentions, namely: (1) Defendant is liable under the contract since defendant retained control of the mud program; (2) Defendant is liable in tort in that the use of Protectomagic amounted to negligence because the Protectomagic reacted chemically to the clay content of the mud solution thus preventing the mud from performing its intended and desired function, and (3) the doctrine of res ipsa loquitur is applicable herein and defendant has failed to refute the presumption of negligence arising therefrom.

The contract is essentially in the standard form prepared by the American Association of Oilwell Drilling Contractors. With certain *602 inconsequential exceptions, it provided in effect that performance of the drilling and the costs and risks incident thereto were plaintiff's responsibility to a depth of 13,500 feet. It is undisputed that appellant undertook to drill and deliver a well down to the aforementioned depth, suitable for the setting of casing.

Unquestionably the terms of the agreement concerning the mud program imposed considerable responsibility on Owner. This phase of the agreement, dealing with the mixtures of clay, water and other materials which serve as a lubricant and coating substance for the drilling equipment and bore hole, provided in part as follows:

"Contractor will insure that mud, adequate in type and quantity, is on hand at all times for the operations contemplated; Contractor agrees to maintain the mud program designed by Owner; and Contractor shall be obligated to advise Owner and make recommendations to him in writing when, in Contractor's opinion, the mud program should be revised." (Paragraph 10)

An addendum to the contract entitled SPECIFICATIONS AND SPECIAL PROVISIONS, sets forth in paragraph two thereof, the complete initial mud control program and concludes with the following:

"Oil will be added if required to increase rate of penetration."

It is conceded by all parties that in the course of the drilling process "mud" is employed both as a lubricant to assist the drilling process and also to form a "filter cake" on the walls of the bore hole. It suffices to relate that "mud" as known to the trade, is generally a fluid mixture of clay, water, diesel oil and various other chemical additives depending upon the nature of the formation in which the well is being drilled. Diesel oil is added to increase penetration because it lubricates the drill bit and readily emulsifies to form a desirable "wall cake" or "filter cake", the purpose of which is hereinafter explained. Diesel oil, being inert, produces no undesirable chemical reaction with the clay particles in the mud, thus producing reduced water loss, a factor essential to a desirable and well functioning wall cake. Complete emulsification at all times is essential which result is best achieved by mixing additives such as Protectomagic in a hopper with emulsifying agents before addition to the mud formula. The mud in the tank is kept in a state of emulsification by agitators which can be used to stir the mixture when necessary or desirable.

By a process not made entirely clear in the record, the fluid mud is introduced into the well bore during the drilling process. A portion of the mud is recovered in the process of drilling and is returned to the mud tank for reuse. It is both customary and necessary that a constant check be made of the mud supply to insure its continued suitability in the light of the nature of the formation encountered.

The function of the wall cake or filter cake is to create a seal between the drill pipe and the formation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Winans v. Rockwell International Corp.
705 F.2d 1449 (Fifth Circuit, 1983)
Par-Co Drilling, Inc. v. Franks Petroleum Inc.
360 So. 2d 642 (Louisiana Court of Appeal, 1978)
LeJeune v. Liberty Mutual Insurance Company
261 So. 2d 280 (Louisiana Court of Appeal, 1972)
Palmer v. Turner
252 So. 2d 700 (Louisiana Court of Appeal, 1971)
Hargis v. Travelers Indemnity Company
248 So. 2d 613 (Louisiana Court of Appeal, 1971)
J. C. Trahan Drilling, Contractor, Inc. v. Cockrell
228 So. 2d 482 (Supreme Court of Louisiana, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
225 So. 2d 599, 34 Oil & Gas Rep. 384, 1969 La. App. LEXIS 5819, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jc-trahan-drilling-contractor-inc-v-cockrell-lactapp-1969.