Jay Township Authority v. Cummins

773 A.2d 828, 2001 Pa. Commw. LEXIS 263
CourtCommonwealth Court of Pennsylvania
DecidedApril 24, 2001
StatusPublished
Cited by6 cases

This text of 773 A.2d 828 (Jay Township Authority v. Cummins) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jay Township Authority v. Cummins, 773 A.2d 828, 2001 Pa. Commw. LEXIS 263 (Pa. Ct. App. 2001).

Opinion

LEADBETTER, Judge.

Robert Cummins (d/b/a Bob Cummins Construction Co.) and Mid-State Surety Corp. appeal from the order of the Court of Common Pleas of the 59th Judicial District (Elk County Branch), which awarded the Jay Township Authority (Authority) $10,760.00, the amount of Cummins’ bid bond. The issue presented for review is whether the Authority properly awarded a project contract to Cummins thereby entitling it to the bid security when Cummins subsequently failed to execute the contract documents.

The Authority solicited bids for a sludge dewatering system for its sewage treatment plant, requiring each submission to be accompanied by a bid bond in the amount of 10% of the bid price. Cummins submitted a bid for the project in the *830 amount of $107,600.00, which was accompanied by the required bid security, naming Cummins as principal and Mid State as surety. Cummins’ bid was opened on September 17, 1996, and it was the lowest bid received. On January 15, the Authority issued a Notice of Award to Cummins; the Notice was faxed and sent by certified mail on that same date. The facsimile transmission contained the notation that “certified copy to follow via mail.” In addition, on January 15, the Authority’s engineers separately mailed to Cummins for signature (via regular mail) three copies of the contract documents, including the Agreement (contract documents).

Cummins received the Notice of Award sent by mail and the contract documents within one week of January 15. Cummins did not execute the contract documents or return them to the Authority and, on January 30, he notified the Authority that he would not work on the project because of the rising cost of materials and the expiration of the period for award notification. Thereafter, on February 10, the Authority sent Cummins a Notice of Annulment for failure to execute and deliver the contract documents within 15 days of receiving the Notice of Award and further advised Cum-mins that it had forfeited its bid security.

In July 1997, the Authority filed its complaint against Cummins and Mid State (hereinafter Cummins), seeking payment on the bid bond. In response, Cummins averred that the Notice of Award was untimely and insufficient. Following a non-jury trial, common pleas concluded that the Notice of Award was untimely and entered an Award in favor of Cummins and against the Authority. Following post-trial motions, however, common pleas concluded that it had erred in ruling on the timeliness issue; the court reversed its earlier award and awarded the Authority $10,760.00, the amount of the bid bond, plus interest and costs of suit. 1 The present appeal followed.

We begin by noting several basic concepts underlying the area of public contracts. First, a contractor’s bid in response to an invitation constitutes an offer, and a binding contract is formed when the public entity accepts the bid. Muncy Area Sch. Dist. v. Gardner, 91 Pa.Cmwlth. 406, 497 A.2d 683, 686 (1985). “A public contract has its inception in the award as distinguished from the formal signing of the contract, and is binding from that time on.” Id. Second, the prerequisites to bond forfeiture, which are included in the Instructions, form a material part of the contract between the parties. Travelers Indem. Co. v. Susquehanna County Comm’rs, 17 Pa.Cmwlth. 209, 331 A.2d 918, 920 (1975). Therefore, compliance with the specified prerequisites is necessary for the enforcement of rights and obligations arising thereunder. Id. In the present case, the Instructions provided in pertinent part:

ARTICLE 7 — BID SECURITY
7.2 The Bid security of Successful Bidder will be retained until such Bidder has executed the Agreement and furnished acceptable Contract bonds and insurance certificate, whereupon the Bid security will be returned. If the Successful Bidder fails to execute and deliver the Agreement and furnish acceptable Contract bonds and insurance certificate within 15 days after the Notice of Award, Owner may annul the Notice of *831 Award and the full amount of the Bid Security of that Bidder will be forfeited.
ARTICLE 17 — AWARD OF CONTRACT
17.6. If the Contract is to be awarded, Owner will give the apparent Successful Bidder a Notice of Award within the time limits prescribed....
ARTICLE 19 — SIGNING OF AGREEMENT
19.1 When Owner gives a Notice of Award to the apparent Successful Bidder, it will be accompanied by the required number of unsigned counterparts of the Agreement, with all other written attachments and Bond forms. Within fifteen days thereafter, apparent Successful Bidder shall sign and deliver the required number of counterparts of the Agreement with the required Bonds and attachments.

R.R. 322a-326a (emphasis added).

In addition to the Instructions to Bidders, the Standard General Conditions of the Construction Contract (General Conditions) governed the formation of an agreement between the parties. Article 17.1 of the General Conditions states:

Giving Notice:
17.1 Whenever any provision of the Contract Documents requires the giving of written notice, it will be deemed to have been validly given if delivered in person to the individual or to a member of the firm or to an officer of the corporation for whom it is intended, or if delivered at or sent by registered or certified mail, postage prepaid....

R.R. 479a. 2

On appeal, Cummins argues that the Authority’s failure to provide the Agreement and other contract documents with the Notice of Award as required by Section 19.1 of the Instructions precludes forfeiture of the bid bond. In conjunction with this argument, Cummins contends that the Authority’s failure to send the contract documents by certified mail defeats forfeiture. The Authority contends on the other hand that Article 17 of the Instructions and not Article 19 governs the formation of a contract between the parties. According to the Authority, issuance of the Notice of Award binds the parties, not the provision of the unsigned contract documents. The Authority maintains that Article 19 merely addresses the procedural steps that are to occur after contract formation.

Here, the Authority satisfied Article 17.1 of the General Conditions by sending the Notice by certified mail. The Instructions, however, also required the Authority to provide the necessary contract documents at the same time as the Notice.

Webster’s Third New International Dictionary (1993) defines the term “accompany” as “to add or join to often incidentally or casually[;] to exist or occur in conjunction or association with.” Id. at 12.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
773 A.2d 828, 2001 Pa. Commw. LEXIS 263, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jay-township-authority-v-cummins-pacommwct-2001.