Javier Steel Corp. v. Central Bridge Co.

353 S.W.3d 356, 2011 Ky. App. LEXIS 6, 2011 WL 117657
CourtCourt of Appeals of Kentucky
DecidedJanuary 14, 2011
Docket2009-CA-002124-MR
StatusPublished
Cited by6 cases

This text of 353 S.W.3d 356 (Javier Steel Corp. v. Central Bridge Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Javier Steel Corp. v. Central Bridge Co., 353 S.W.3d 356, 2011 Ky. App. LEXIS 6, 2011 WL 117657 (Ky. Ct. App. 2011).

Opinion

OPINION

ACREE, Judge:

The appellant, Javier Steel Corporation (Javier), appeals from the judgment of the Jefferson Circuit Court which found Javier was unjustly enriched when appellee, Central Bridge Company, LLC (CBC), overpaid Javier; Javier was ordered to reimburse $402,423.26 to CBC. We affirm.

Facts

CBC is a bridge and road construction contractor and Javier is a steel subcontractor. Between 1999 and 2002, pursuant to highway contracts funded by the federal and state governments, CBC contracted with Javier to provide materials and labor for road works projects throughout the Commonwealth. The agreements at issue provided that Javier would provide labor and materials at each of seven locations and that CBC would pay Javier as follows:

Contract # l(Madison Co.) — $653,226.77
Contract # 2 (Scott Co.) — $136,003.40
Contract # 3 (Boone Co.) — $370,440.40
Contract # 4 (Lexington-Covington Road) — $117,683.12
Contract # 5 (Henry Clay Blvd.)— $107,802.73
*358 Contract # 6 (Paris-Covington Rd.)— $234,601.37
Contract # 7 (Lexington-Catlettsburg Rd.) — $391,809.88

These seven contracts allowed for alternative methods of assuring payment to third-party materials vendors. When Javier procured materials from third-party vendors, it was supposed to pay third-party vendors out of the amounts received under the contracts from CBC. Alternatively, the contracts authorized CBC to make arrangements with third-party vendors and pay them for the materials directly. If CBC paid vendors directly for materials, it was entitled to reduce the payments made to Javier by the amount paid to the third-party vendors.

When CBC made a change to its accounting software, this contract-payment flexibility resulted in mistaken overpay-ments to Javier. Three sets of circumstances that led to overpayments are outlined below.

The dispute concerning Contract # 1 arose because Javier simply was paid in excess of the amount contracted. The circuit court found CBC had paid Javier $16,517.26 over and above the agreed upon contract amount and that Javier had not performed any additional work to warrant the payment. Accordingly, the circuit court found that CBC was entitled to recover the overpayment from Javier.

The issue with Contract # 2 concerned a double payment by CBC to Javier for work that Javier had performed only once. The court found Javier had performed work according to the contract and had been fully paid under the contract. However, Javier mistakenly double-billed CBC and CBC paid the sum of $16,800.00 a second time for the same work for which it had already compensated Javier. Javier was therefore required to repay CBC the $16,800.00 overpayment.

With regard to the final five contracts, CBC made arrangements to pay certain third-party materials vendors directly yet still paid Javier the full payments due under the contracts (labor and materials) without deducting from the payments to Javier the amounts of the direct payments to third-party vendors. At trial, CBC presented evidence of the direct payments for materials to vendors and the concomitant double payment for the same materials to Javier. Javier produced no evidence that it had in fact paid the vendors for the materials out of the payments it received from CBC. The trial court concluded that Javier had retained the funds that were intended for the vendors and was therefore unjustly enriched. The overpayments for the five remaining contracts totaled $514,288.98.

The circuit court found that CBC’s over-payments to Javier totaled $547,606.54. Prior to trial, CBC had set off $145,183.28 of this amount against subsequent contract payments owed to Javier.

Procedural History

A bench trial was held over three days in July and August 2005. In September 2006, because there had been no activity in the file, the clerk of the court, apparently without determining that the case was under submission, sent the parties a Notice to Dismiss for Lack of Prosecution. In an effort to correct the clerk’s mistake, the parties made their way back before the circuit judge who, in a November 9, 2006 hearing, acknowledged that the Notice had been issued in error.

The parties waited another six months, anticipating a decision in the case. It then came to the parties’ attention that on November 9, 2006, the circuit judge had mistakenly signed the order dismissing the case for lack of prosecution but the clerk *359 had not noticed the parties. On May 9, 2007, CBC moved to vacate that order. A hearing was held and on May 14, 2007, the circuit court vacated the mistaken order of dismissal stating in the order that the court was relying on the authority of Kentucky Rules of Civil Procedure (CR) 60.01 and CR 60.02.

On March 17, 2008, the circuit court finally ruled on the merits of the case, issuing Findings of Fact and Conclusions of Law in accordance with CR 52.01. The judgment was in CBC’s favor. Javier timely filed a Motion to Alter, Amend or Vacate Judgment or for Judgment Notwithstanding the Verdict. This motion was denied by order entered October 15, 2009. Javier filed a timely Notice of Appeal to this Court.

In its appeal, Javier contends that CBC did not overpay it, and that it was paid according to the contract terms. Javier further asserts that CBC has unclean hands and that if CBC were allowed to recover from Javier, CBC would be violating federal law and committing a fraud against the state and federal governments to which CBC had made representations regarding payments to Javier. Javier also appealed the trial court’s vacating of its order to dismiss.

Standard of Review

This case was tried without a jury, the circuit judge acting as fact-finder. An appellate court will set aside a circuit court’s findings of fact only if those findings are clearly erroneous. CR 52.01. In sum, only if reasonable minds could not differ with Javier’s contention that it was not overpaid will we set aside the circuit court’s findings of fact on this point.

Legal conclusions, however, are subject to de novo appellate review. “Questions of law are reviewed anew by this Court.” Daniels v. CDB Bell, LLC, 300 S.W.3d 204, 210 (Ky.App.2009). The theory of unjust enrichment is an equitable doctrine, Dodson v. Key, 508 S.W.2d 586 (Ky.1974), and the application of an equitable doctrine to the facts of a case is a question of law. Daniels, 300 S.W.3d at 210. Therefore, the question as to whether Javier was unjustly enriched will be “reviewed anew by this Court.” Id. at 209.

Analysis

Order Vacating Order of Dismissal Was Not Error or Abuse of Discretion

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Russell Todd Thomas v. Deborah Elaine Thomas
Court of Appeals of Texas, 2023
Dewane Beasey v. Ford Motor Company
Court of Appeals of Kentucky, 2020
Arnold v. Liberty Mut. Ins. Co.
392 F. Supp. 3d 747 (E.D. Kentucky, 2019)
EQT Production Co. v. Magnum Hunter Production Co.
266 F. Supp. 3d 961 (E.D. Kentucky, 2017)
First Technology Capital, Inc. v. JPMorgan Chase Bank, N.A.
53 F. Supp. 3d 972 (E.D. Kentucky, 2014)
C.A.F. & Associates, LLC v. Portage, Inc.
913 F. Supp. 2d 333 (W.D. Kentucky, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
353 S.W.3d 356, 2011 Ky. App. LEXIS 6, 2011 WL 117657, Counsel Stack Legal Research, https://law.counselstack.com/opinion/javier-steel-corp-v-central-bridge-co-kyctapp-2011.