James Talcott, Inc. v. Jack Cole Company, Defendant-Third Party v. Rapistan Incorporated, Third Party

441 F.2d 325
CourtCourt of Appeals for the Third Circuit
DecidedMay 4, 1971
Docket29353
StatusPublished
Cited by3 cases

This text of 441 F.2d 325 (James Talcott, Inc. v. Jack Cole Company, Defendant-Third Party v. Rapistan Incorporated, Third Party) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
James Talcott, Inc. v. Jack Cole Company, Defendant-Third Party v. Rapistan Incorporated, Third Party, 441 F.2d 325 (3d Cir. 1971).

Opinion

RIVES, Circuit Judge:

Cole, a motor freight carrier, purchased from Rapistan an expensive and complicated conveyor system for handling freight across its dock at its main *326 terminal in Birmingham, Alabama, 1 and built a new dock wide enough to accommodate the conveyor. The conveyor was installed in a permanent fashion so as in effect to make it a part of the terminal. The cost of installation, $33,350.00, was to be paid directly by Cole to Rapistan. The agreed price of the conveyor system was $168,164.00, secured by a conditional sales contract assigned to Talcott upon Cole’s written assurance that it would not assert against Talcott any claim or defense that Cole might have against Rapistan. With the addition of finance charges, the total cost to Cole of the conveyor system installed was $235,500.00 plus the cost of building the new dock.

The initial action brought by Talcott against Cole has resulted in a judgment in favor of Talcott for $102,000.00, the balance of the purchase price. No issue is presented on this appeal as to that initial action, and that action did not involve any of the issues presented by the third party action.

The third party action brought by Cole against Rapistan was three-pronged. First, Cole claimed that on account of Rapistan’s breach of express and implied warranties, 2 Cole was entitled to rescind the contract of sale and recover from Rapistan the purchase price of the conveyor system. Second, if rescission was denied, Cole asserted that it was entitled to recover damages caused by Rapistan’s breach of warranties. 3 Third, Cole claimed that it was entitled to recover damages because of certain written misrepresentations of fact made by Rapistan in connection with the sale. 4

On a jury trial, at the close of Cole’s evidence, Rapistan also rested, and the district court granted Rapistan’s motion for a directed verdict upon holding: (1) *327 that Cole’s attempt to rescind was not made within a reasonable time; (2) that adequate notice of Cole’s claims for breach of warranty was not given to Rapistan within a reasonable time; and (3) that Cole’s claim for misrepresentations was not commenced within the limitation period of one year after Cole knew, or in the exercise of reasonable care should have known, that the representation was false. Tit. 7, § 42, Code of Ala. 1940.

On appeal Cole contends that each of the questions which the district court resolved against Cole as a matter of law was properly for the jury. Essentially on each of Cole’s claims, the critical question was what was a reasonable time under all of the circumstances of the ease. After carefully reading and considering the entire record, including the exhibits, in connection with the briefs and arguments of the attorneys, while we recognize ample room for differences of opinion and have great respect for the views of the learned district judge, we agree with Cole’s contentions that at the close of its evidence each of its claims was properly for the determination of the jury and that the court erred in directing a verdict for Rapistan. Accordingly, we reverse and remand.

Essentially our decision is prompted by the Seventh Amendment mandate to preserve the right of trial by jury in suits at common law; or more specifically by the standard prescribed by this Circuit’s en banc decision in Boeing v. Shipman, 1969, 411 F.2d 365, 374, 375:

“On motions for directed verdict and for judgment notwithstanding the verdict the Court should consider all of the evidence—not just that evidence which supports the nonmover’s case—but in the light and with all reasonable inferences most favorable to the party opposed to the motion. If the facts and inferences point so strongly and overwhelmingly in favor of one party that the Court believes that reasonable men could not arrive at a contrary verdict, granting of the motions is proper. On the other hand, if there is substantial evidence opposed to the motions, that is, evidence of such quality and weight that reasonable and fair-minded men in the exercise of impartial judgment might reach different conclusions, the motions should be denied, and the case submitted to the jury. A mere scintilla of evidence is insufficient to present a question for the jury. The motions for directed verdict and judgment n. o. v. should not be decided by which side has the better of the case, nor should they be granted only when there is a complete absence of probative facts to support a jury verdict. There must be a conflict in substantial evidence to create a jury question. However, it is the function of the jury as the traditional finder of the facts, and not the Court, to weigh conflicting evidence and inferences, and determine the credibility of witnesses.”

Since the decision turns on the facts, inferences and circumstances of this particular case, we shall endeavor to be brief, though the complexity of the situation makes brevity difficult if not impossible.

Cole had handled freight across its terminal dock in Birmingham with a manual push cart operation. The dock worker took the freight off a truck, placed it on a four-wheel push cart, kept the freight bill with the freight, pushed the cart across the dock and unloaded the freight into the trailer on which it was to be carried. As far back as 1962 or 1963, its President began considering the advisability of converting to some kind of mechanical, dragline, or conveyor operation. In February 1964, Rapistan studied Cole’s operation and submitted a report. Thereafter, the building of a new dock and conversion to a conveyor system was spurred by Cole’s acquisition of the business of another carrier, Dixie Highway Express, beginning in 1963 and completed in early 1965. In 1964 and 1965, Cole officials studied operations of terminals of other carriers in Dallas, Texas; Kalamazoo, Michigan; Cleveland, Ohio; and Memphis, Tennessee. *328 After the Kalamazoo study of a Rapistan conveyor system, a detailed report was prepared of the advantages and disadvantages of converting to a conveyor system. At a meeting in March 1965, Cole furnished to Rapistan the result of a survey it had conducted as to how much “conveyable” and how much “non-conveyable” freight it handled. On May 24, 1965, Rapistan submitted to Cole “our formal Proposal-Contract covering equipment for your Birmingham terminal” for acceptance by Cole on or before August 15, 1965. The contract was accepted by Cole on August 4 and approved by Rapistan on August 6, 1965. Installation was to be completed within 20 weeks, and tune-up thereafter when freight is being received into the system. Installation was completed and the conveyor system went into actual operation about January 4, 1966.

From the date of its installation, the conveyor system was not operated satisfactorily, though in many instances there is a serious question of fact as to whether the responsibility for the faulty or inefficient operation should be charged against the equipment furnished by Rapistan or the personnel furnished by Cole.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
441 F.2d 325, Counsel Stack Legal Research, https://law.counselstack.com/opinion/james-talcott-inc-v-jack-cole-company-defendant-third-party-v-rapistan-ca3-1971.