JAMES FLOOR COVERING CO., INC. v. TUTOR PERINI BUILDING CORPORATION

CourtDistrict Court, E.D. Pennsylvania
DecidedDecember 12, 2022
Docket2:22-cv-00123
StatusUnknown

This text of JAMES FLOOR COVERING CO., INC. v. TUTOR PERINI BUILDING CORPORATION (JAMES FLOOR COVERING CO., INC. v. TUTOR PERINI BUILDING CORPORATION) is published on Counsel Stack Legal Research, covering District Court, E.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
JAMES FLOOR COVERING CO., INC. v. TUTOR PERINI BUILDING CORPORATION, (E.D. Pa. 2022).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE EASTERN DISTRICT OF PENNSYLVANIA

JAMES FLOOR COVERING CO., INC. : : CIVIL ACTION Plaintiff, : : v. : : NO. 22-123 TUTOR PERINI BUILDING : CORPORATION : : Defendant. :

MEMORANDUM OPINION

Goldberg, J. December 12, 2022

Plaintiff James Floor Covering Co., Inc. has sued Defendant Tutor Perini Building Corporation for a breach of contract arising out of work performed by Plaintiff on a construction project in Philadelphia, Pennsylvania. Defendant has moved to dismiss the Complaint in its entirety. For the following reasons, I will grant the Motion. I. FACTUAL BACKGROUND A. Facts in the Complaint The following facts are set forth in the Complaint:1 The parties were both involved with a construction project to build the W/Element Hotel at 1441 Chestnut Street, Philadelphia, Pennsylvania (the “Project”). Defendant entered into a written agreement with the Project’s owner, Chestlen Development, L.P. (“Chestlen” or “Owner”), in which

1 In deciding a motion under Federal Rule of Civil Procedure 12, the court must accept all factual allegations in the complaint as true, construe the complaint in the light most favorable to the plaintiff, and determine whether, under any reasonable reading, the plaintiff may be entitled to relief. Atiyeh v. Nat’l Fire Ins. Co. of Hartford, 742 F. Supp. 2d 591, 596 (E.D. Pa. 2010). Defendant agreed to serve as the Project’s general contractor and provide all labor and materials necessary for the construction of the Project. (Compl. ¶¶ 6–7.) On July 5, 2016, Defendant entered into a written subcontract with Plaintiff (“Subcontract Agreement”) whereby Plaintiff agreed to furnish all labor, materials, tools, equipment, and insurance necessary to install flooring, stone, countertops, and tile at the Project. (Id. ¶ 8.) The Subcontract Agreement provides:

[Defendant] agrees to pay [Plaintiff] for his work from funds [Defendant] receives from Owner under the General Contract the sum of $222,825 . . . . Unless otherwise required by the General Contract, partial payment will be made to [Plaintiff] as the work progresses, on or before fourteen (14) days after [Defendant’s] receipt of payment from the Owner for [Plaintiff’s] work completed during the preceding estimate period, pursuant to estimates approves by the Owner. In making such partial estimates, there shall be retained 10.00% on the estimated amount until final completion and acceptance of all work covered by the General Contract and after final payment has been received by [Defendant] for [Plaintiff’s] scope of work.

(Id. ¶ 9.) In the event Defendant does not receive payment from the Owner for Plaintiff’s work, the Subcontract Agreement states: If [Defendant] does not receive full and final payment from Owner for work performed by [Plaintiff] within the time required by the General Contract or the law then [Defendant’s] obligation to make payment including any Subcontract retention shall not arise until two (2) months after [Defendant] has exhausted its efforts to collect payment from Owner in proceedings described in paragraph 2E herein and in this event, [Plaintiff]’s sole remedy and recourse against [Defendant] shall be to recover its pro-rata share of what [Defendant] has been able to collect from the Owner as set forth in paragraph 2E herein.

(Id. ¶ 10.) Finally, the Subcontract contains the following clause regarding disputes: All claims of Subcontractor [Plaintiff] arising out of acts or omissions by Owner [Chestlen] shall be presented to Owner by Contractor [Defendant] on behalf of Subcontractor . . . . All other claims and disputes between the parties shall be decided by the appropriate Pennsylvania State Court where venue is proper under the applicable law. Subcontractor shall not be entitled to recover damages from Contractor as a result of any act, omission or event without proof that it gave Contractor immediate written notice that it was being or would be damaged by such act, omission or event, but in no event later than 10 days after the first occurrence of the act, omission or event, or at such shorter time as may be required by the General Contract Documents.

(Id.) Defendant posits that where, as here, a subcontractor—such as Plaintiff—has disputes directly with Defendant, as General Contractor, those disputes constitute “other claims and disputes.” In turn, under the express language § 2.E, Defendant contends that such claims must be brought in the “appropriate Pennsylvania State Court.” Plaintiff and Defendant also executed ten (10) change orders (“Change Orders”) altering and/or adding to Plaintiff’s scope of work, costs, and/or other terms of the Subcontract Agreement throughout its work on the Project. (Id. ¶ 11.) Plaintiff claims that it duly and fully performed its scope of work on the Project as set forth in the Subcontract Agreement and Change Orders as requested by Defendant. Accordingly, it asserts that it is owed $344,862.01. Plaintiff notified Chestlen and Defendant of non-payment on the Project but has yet to receive any payment. (Id. ¶¶ 12–15.) On January 11, 2022, Plaintiff filed a federal complaint setting forth two claims. First, Plaintiff alleges that Defendant breached its Subcontract Agreement with Plaintiff by failing to pay Plaintiff the full amount due and owing on the Project. Second, Plaintiff asserts that Defendant violated the Pennsylvania Contract and Subcontractor Payment Act (“CASPA”), 73 P.S. § 501, et seq. B. Parallel State Court Proceedings The following are facts are taken from court docket entries in related cases:2 The Project is the subject of multiple other lawsuits, all of which are pending in the Philadelphia Court of Common Pleas, and eighteen of which have been consolidated into a single action, in the state court’s Commerce Program, under the caption, Chestlen Development LP v. Tutor Perini Building Corp., No. Jan. Term 2021, No. 645. (Def.’s Mot., Ex. 5.)

Among these cases is a suit brought by Defendant against Chestlen on December 8, 2020, seeking money owed to Defendant and its trade contractors, including Plaintiff, “for the construction costs, labor, materials, equipment, and other services that were supplied to [Chestlen] to construct [the Project].” (Def.’s Ex. 4 ¶ 1.) Defendant’s state lawsuit contends that Chestlen has not paid it since October 16, 2020, and that payment was for work dating back to May 2020. (Id. ¶ 21.) Defendant seeks compensation by Chestlen for the work its trade contractors performed on the Project and to collect on all unpaid invoices, extra work, and other contract costs. (Id. ¶ 3.) Chestlen denied Defendant’s allegations and contested liability. Additionally, Chestlen filed its own state court complaint against Defendant, on January 11, 2022, claiming entitlement to more than $30

million in liquidated damages arising out of alleged delays, defective work, and mismanagement by Defendant and its contractors. (Def.’s Ex. 7.) Aside from this case, numerous other trade contractors have filed suit in the Philadelphia Court of Common Pleas, either in the form of Mechanic’s Lien claims or other actions seeking

2 Federal Rule of Evidence 201(b) permits a district court to take judicial notice of facts that are “not subject to reasonable dispute” in that they are either (1) “generally known within the territorial jurisdiction of the trial court” or (2) “can be accurately and readily determined from sources whose accuracy cannot reasonably be questioned.” Fed. R. Evid. 201(b).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

The Bremen v. Zapata Off-Shore Co.
407 U.S. 1 (Supreme Court, 1972)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Mellon Bank, N.A. v. Aetna Business Credit, Inc.
619 F.2d 1001 (Third Circuit, 1980)
Peter Bistrian v. Troy Levi
696 F.3d 352 (Third Circuit, 2012)
Great American Insurance v. Norwin School District
544 F.3d 229 (Third Circuit, 2008)
MacE v. Atlantic Refining & Marketing Corp.
785 A.2d 491 (Supreme Court of Pennsylvania, 2001)
East Crossroads Center, Inc. v. Mellon-Stuart Co.
205 A.2d 865 (Supreme Court of Pennsylvania, 1965)
Murphy v. Duquesne University of Holy Ghost
777 A.2d 418 (Supreme Court of Pennsylvania, 2001)
Atiyeh v. National Fire Ins. Co. of Hartford
742 F. Supp. 2d 591 (E.D. Pennsylvania, 2010)
Union Steel America Co. v. M/V SANKO SPRUCE
14 F. Supp. 2d 682 (D. New Jersey, 1998)
Dolores Dawes v. Publish America LLLP
563 F. App'x 117 (Third Circuit, 2014)
Paul Rathblott v. Peoplestrategy Inc
685 F. App'x 107 (Third Circuit, 2017)
Ina Collins v. Mary Kay Inc
874 F.3d 176 (Third Circuit, 2017)
Reading Health System v. Bear Stearns Co Inc
900 F.3d 87 (Third Circuit, 2018)
SKF USA Inc. v. Okkerse
992 F. Supp. 2d 432 (E.D. Pennsylvania, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
JAMES FLOOR COVERING CO., INC. v. TUTOR PERINI BUILDING CORPORATION, Counsel Stack Legal Research, https://law.counselstack.com/opinion/james-floor-covering-co-inc-v-tutor-perini-building-corporation-paed-2022.