J.A.M. Builders, Inc. v. Alexis Herman

233 F.3d 1350
CourtCourt of Appeals for the Eleventh Circuit
DecidedNovember 22, 2000
Docket99-11917
StatusPublished

This text of 233 F.3d 1350 (J.A.M. Builders, Inc. v. Alexis Herman) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J.A.M. Builders, Inc. v. Alexis Herman, 233 F.3d 1350 (11th Cir. 2000).

Opinion

[PUBLISH]

IN THE UNITED STATES COURT OF APPEALS FILED FOR THE ELEVENTH CIRCUIT U.S. COURT OF APPEALS ELEVENTH CIRCUIT ________________________ NOV 22 2000 THOMAS K. KAHN CLERK No. 99-11917 ________________________

O.S.H.R.C. No. 98-00823

J.A.M. BUILDERS, INC.,

Petitioner,

versus

ALEXIS HERMAN, Secretary of Labor, and OCCUPATIONAL SAFETY AND HEALTH REVIEW COMMISSION,

Respondents. __________________________

Petition for Review of an Order of the Occupational Safety and Health Review Commission _________________________ (November 22, 2000)

Before CARNES and BARKETT, Circuit Judges, and POLLAK*, District Judge.

_______________________ *Honorable Louis H. Pollak, U.S. District Judge for the Eastern District of Pennsylvania, sitting by designation. BARKETT, Circuit Judge: J.A.M. Builders, Inc., (“J.A.M.”) petitions for review of a final decision of

the Occupational Safety and Health Review Commission (the “Commission”)

affirming the administrative law judge’s (“ALJ”) finding that it willfully violated a

safety regulation promulgated pursuant to the Occupational Safety and Health Act

(“OSHA”).

J.A.M. was a subcontractor at a construction site in Miami Beach, Florida,

where an ironworker was killed by electrocution. After an investigation into the

fatality, the Secretary of the Department of Labor (the “Secretary”) issued a

citation and notice of a proposed penalty against J.A.M., alleging various

violations of OSHA safety standards. One of the charges alleged that J.A.M.

willfully violated a construction industry safety standard that prohibits an employer

from permitting its employees to work in such proximity to electrical power

circuits that they could come into contact with them, without taking adequate

precautions to protect employees from the risk of electric shock.

On appeal, J.A.M. challenges the Commission’s decision that it willfully

violated this standard, arguing that the Commission’s decision is not supported by

substantial evidence and is not in accordance with the law. We review the

Commission’s findings of fact to determine whether they are supported by

substantial evidence on the record as a whole; if so, they are deemed conclusive.

2 See 29 U.S.C. § 660(a); Niemand Indus., Inc. v. Reich, 73 F.3d 1083, 1084 (11th

Cir. 1996). “Substantial evidence is more than a scintilla and is such relevant

evidence as a reasonable person would accept as adequate to support a

conclusion.” Lewis v. Callahan, 125 F.3d 1436, 1440 (11th Cir. 1997). We also

review whether the Commission’s order is “in accordance with the law.” Reich v.

Trinity Indus., Inc., 16 F.3d 1149, 1152 (11th Cir. 1994).

The safety standard at issue, 29 C.F.R. § 1926.416(a)(1), provides:

No employer shall permit an employee to work in such proximity to any part of an electric power circuit that the employee could contact the electric power circuit in the course of work, unless the employee is protected against electric shock by de-energizing the circuit and grounding it or by guarding it effectively by insulation or other means.

OSHA differentiates among violations of varying severity. J.A.M was charged

with the most severe offense, to wit, a “willful” violation pursuant to 29 U.S.C. §

666(a), which is subject to the greatest penalties under the Act: a fine not less than

$5,000 and up to $70,000, and the possibility of imprisonment if the willful

violation causes an employee’s death. See 29 U.S.C. § 666(a), (e). See also

United States v. Ladish Malting Co., 135 F.3d 484, 490 (7th Cir. 1998)

(differentiating various offenses under 29 U.S.C. § 666).

The ALJ upheld the citation, finding that J.A.M. failed to adequately protect

its employees working in proximity to energized electrical lines on November 5th

3 through the 7th. The administrative record upon which the ALJ based his decision

reflects the following. J.A.M. Builders was hired by Brodson Construction

Company, the general contractor, to construct the shell of a three-story building.

The new structure, measuring 85 feet long by 17 feet wide, was an addition to an

existing building. At the time of the fatality, the structure stood approximately 20

feet tall.1 During the relevant time period, three energized, high-voltage electrical

lines, or primary conductors, carrying 7,620 volts of electricity each, ran parallel to

the building’s east side approximately 8-12 feet above the structure. These lines

were not insulated and were held up by one pole located at the northeast corner of

the building, 19 inches away from the east wall, and by another pole at the

southeast corner.

After J.A.M. began its work on the building, company employees orally

informed Brodson that the high-voltage lines needed to be rerouted. Five days

before J.A.M. began working with steel on the third floor, J.A.M.’s project

manager additionally wrote Brodson that a Florida Power & Light Co. (“FP&L”)

representative had instructed J.A.M. that work would not be allowed to continue in

proximity to the lines unless they were moved, and requested Brodson to

1 The structure was located on a corner lot: the south side abutted the existing building, the west side abutted another building, the east side faced an alley (across from which were several buildings), and the north side faced the street.

4 “coordinate with [FP&L] to have these lines moved.” Before the ALJ, J.A.M.

took the position that notwithstanding its letter to Brodson, J.A.M. had fabricated

this story in order to shift blame to FP&L for any project delays.2 However,

Canute Lobean, a compliance officer for the Secretary, and John Jacob, an FP&L

claims agent, testified that the FP&L representative, Diego Borges, told them that

he had warned J.A.M. about working in proximity to the energized lines.

On November 5, 1997, when J.A.M. began working with steel on the third

floor, the energized lines along the building’s east side had not been de-energized,

rerouted, moved, or insulated. Nonetheless, ironworkers working for J.A.M. began

hoisting narrow bars of reinforcing steel (“rebar”), measuring between 16-20 feet

long, from the ground level to the third floor, passing it through a second-floor

window and then through a four-foot by four-foot hole located between the second

and the third floors. The rebar was passed up length-wise, and was angled at a

forty-five degree angle opposite from the building’s east wall and away from the

energized lines, although it was tall enough that it could have touched the

energized lines had it been stood up and/or leaned toward the east wall. After the

rebar was lifted through the hole in the third floor, it was tied together on a 16-inch

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Niemand Industries, Inc. v. Reich
73 F.3d 1083 (Eleventh Circuit, 1996)
Lewis v. Callahan
125 F.3d 1436 (Eleventh Circuit, 1997)
Richardson v. Perales
402 U.S. 389 (Supreme Court, 1971)
Larry Bonner v. City of Prichard, Alabama
661 F.2d 1206 (Eleventh Circuit, 1981)
United States v. Ladish Malting Co.
135 F.3d 484 (Seventh Circuit, 1998)
U. S. Pipe & Foundry Co. v. Webb
595 F.2d 264 (Fifth Circuit, 1979)
Georgia Electric Co. v. Marshall
595 F.2d 309 (Fifth Circuit, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
233 F.3d 1350, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jam-builders-inc-v-alexis-herman-ca11-2000.