Jalbert v. Eagle Rigid Spans, Inc.

2017 ND 50, 891 N.W.2d 135, 2017 N.D. LEXIS 44, 2017 WL 900076
CourtNorth Dakota Supreme Court
DecidedMarch 7, 2017
Docket20160173
StatusPublished
Cited by10 cases

This text of 2017 ND 50 (Jalbert v. Eagle Rigid Spans, Inc.) is published on Counsel Stack Legal Research, covering North Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jalbert v. Eagle Rigid Spans, Inc., 2017 ND 50, 891 N.W.2d 135, 2017 N.D. LEXIS 44, 2017 WL 900076 (N.D. 2017).

Opinion

Crothers, Justice.

[¶ 1] Eagle Rigid Spans, Inc., (“ERS”) appeals an order denying its motion for new trial and an amended judgment entered after a jury found in favor of Brandon and Constance Jalbert and awarding them $650,000 plus interest, and costs and disbursements. ERS also appeals from the district court’s order overruling its objections to costs and disbursements. ERS argues irregularities in the proceeding of the jury trial prevented them from having a fair trial, the jury awarded excessive damages because of the influence of passion or prejudice, sufficient evidence did not exist to justify the verdict and the trial court erred in failing to reduce the Jalbert’s expert witness fees. We affirm.

I

[¶2] ERS contracted to build a multipurpose building for the Jalberts. The agreement stated a contract price of $374,879. During and after the construction of the building the Jalberts discovered problems with the structure. The Jalberts brought suit alleging breach of contract and breach of warranty.

[¶ 3] An initial trial resulted in a mistrial following a health complication suffered by ERS’s counsel. A second trial was held for two days. At trial Mrs. Jalbert testified she paid ERS $344,116.58 for the structure and paid $599,914.41 in total for the building. The total cost included payments to a plumbing company for $8,220, an electric door company for $14,842.25, an electric company for $87,806.20, a concrete company for $102,529.38 and $42,200 for in-floor electric heat. The jury heard testimony from the Jalbert’s expert indicating the building was not structurally sound under the International Building Code. The jury heard further testimony from a general contractor stating the building had structural deficiencies. The general contractor testified demolition of the building could cost between $48,000 and $80,000.

[¶ 4] The jury returned a verdict in favor of the Jalberts awarding them $650,000, plus interest and costs and disbursements for a total of $877,407.78. ERS objected to the costs and disbursements, arguing the Jalbert’s expert witness fees were unreasonable. The district court entered an amended judgment reducing the total costs and disbursements award from $125,045.48 to $123,519.23. ERS filed a *139 motion for a new trial. The district court denied their motion. ERS appeals.

II

[¶ 5] ERS argues the district court abused its discretion by denying a new trial because the district court erred in determining: (1) irregularities in the jury trial did not prevent it from having a fair trial; (2) the jury did not award excessive damages under the influence of passion or prejudice; and (3) sufficient evidence justified the verdict.

[¶ 6] Rule 59(b)(1), (5) and (6), N.D.R.Civ.P., provide:

“The court may, on motion of an aggrieved party, vacate the former verdict or decision and grant a new trial on any of the following grounds materially affecting the substantial rights of the party:
(1) irregularity in the proceedings of the court, jury, or adverse party, or any court order or abuse of discretion that prevented a party from having a fair trial;
(5) excessive damages appearing to have been awarded under the influence of passion or prejudice, but when a new trial is requested on this ground and it appears that the passion or prejudice affected only the amount of damages awarded and did not influence the jury’s findings on other issues in the case, the district court, on hearing the motion, and the supreme court, on appeal, may order a reduction of the verdict instead of a new trial or order that a new trial be had unless the prevailing party remits the excess damages;
(6) insufficient evidence to justify the verdict or other decision, or that the verdict is against the law[.]”

[¶ 7] When reviewing a district court’s decision to grant or deny a new trial, “[t]he decision to grant or deny a new trial rests entirely within the discretion of the trial court.” Bjorneby v. Nodak Mut. Ins. Co., 2016 ND 142, ¶ 13, 882 N.W.2d 232 (quoting Wilson v. General Motors Corp., 311 N.W.2d 10, 14 (N.D. 1981)). “Our standard of review on appeal from a denial of a motion for a new trial is limited to a determination of whether or not the trial court manifestly abused its discretion.” Id.

A.

[¶ 8] ERS asserts irregularities prevented it from having a fair trial. ERS claims the district court abused its discretion by scheduling the trial for two days instead of three and refusing to properly allocate enough time for each party to present its case. ERS further contends the trial court abused its discretion by cancelling a scheduled site visit.

1.

[¶ 9] ERS contends the district court abused its discretion by scheduling the trial for two days instead of three. “A district court has broad discretion over the presentation of evidence and the conduct of trial, but it must exercise its discretion in a manner that best comports with substantial justice.” Manning v. Manning, 2006 ND 67, ¶ 30, 711 N.W.2d 149. “In exercising that discretion, the court may impose reasonable restrictions upon the length of the trial or hearing and upon the number of witnesses allowed.” Hartleib v. Simes, 2009 ND 205, ¶ 15, 776 N.W.2d 217. A district court abuses its discretion if it acts in an arbitrary, unconscionable, or unreasonable manner, if its decision is not the product of a rational mental process or if it misinterprets or misapplies the laws. Id.

*140 [¶ 10] In Wahl v. Northern Imp. Co., a party argued the district court abused its discretion by scheduling trial for four days instead of five. 2011 ND 146, ¶ 6, 800 N.W.2d 700. The party never objected to the scheduling but at a pre-trial conference they expressed concern four days would not be enough time to properly present its case. Id. at ¶7-8. This Court held the district court did not abuse its discretion because the parties knew the scheduled number of days and had “ample time to plan their presentation of evidence accordingly.” Id. at ¶ 8.

[¶ 11] In the present case ERS, like the party in Wahl, did not object to the scheduling until expressing its concern at a pretrial conference indicating two days would be insufficient. The parties were put on notice ten months before the trial that it was scheduled for a two day trial. At the pre-trial conference counsel for ERS explained it erroneously believed the trial was scheduled for three days, but admits the prior scheduling orders reflect a two day trial. The district court did not abuse its discretion in scheduling the trial for two days instead of three.

2.

[¶ 12] ERS contends it was not given as much time as the Jalberts to present its case.

“The district court has broad discretion over the presentation of evidence and the conduct of a trial or hearing. E.g., Niemann v. Niemann, 2008 ND 54, ¶ 19, 746 N.W.2d 3; Burns v. Burns, 2007 ND 134, ¶ 7, 737 N.W.2d 243; Manning v. Manning, 2006 ND 67, ¶ 30, 711 N.W.2d 149; Gullickson [v. Kline], 2004 ND 76, ¶ 15, 678 N.W.2d 138.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Zander v. Morsette
2024 ND 80 (North Dakota Supreme Court, 2024)
Sherwood v. Sherwood
2024 ND 24 (North Dakota Supreme Court, 2024)
Asiama v. Asumeng
2023 ND 114 (North Dakota Supreme Court, 2023)
Rath v. Rath
2022 ND 105 (North Dakota Supreme Court, 2022)
Stevenson v. Biffert
2020 ND 42 (North Dakota Supreme Court, 2020)
Courtney Allen, Et Ano. v. Todd Zonis, Et Ano.
Court of Appeals of Washington, 2018
First Dakota National Bank v. Eco Energy, LLC
881 F.3d 615 (Eighth Circuit, 2018)
Motter v. Traill Rural Water District
2017 ND 267 (North Dakota Supreme Court, 2017)
Linstrom v. Normile
2017 ND 194 (North Dakota Supreme Court, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
2017 ND 50, 891 N.W.2d 135, 2017 N.D. LEXIS 44, 2017 WL 900076, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jalbert-v-eagle-rigid-spans-inc-nd-2017.