JAL Construction, Inc. v. Friedman

83 P.3d 332, 191 Or. App. 492, 2004 Ore. App. LEXIS 38
CourtCourt of Appeals of Oregon
DecidedJanuary 21, 2004
Docket01CV0231ST; A117311
StatusPublished
Cited by1 cases

This text of 83 P.3d 332 (JAL Construction, Inc. v. Friedman) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
JAL Construction, Inc. v. Friedman, 83 P.3d 332, 191 Or. App. 492, 2004 Ore. App. LEXIS 38 (Or. Ct. App. 2004).

Opinion

LINDER, J.

This is an action under ORS 279.067 brought by JAL Construction (JAL), which was an unsuccessful bidder on a City of Bend (the city) public contract. On cross-motions for summary judgment, the trial court granted summary judgment in favor of JAL and awarded it damages. The sole issue on appeal is whether the city unlawfully awarded the contract to bidder Hap Taylor & Sons (HTS). That issue, in turn, depends on whether HTS substantially complied with all prescribed public bidding procedures and requirements. Contrary to the trial court’s ruling, we conclude that HTS did substantially comply and that the city therefore lawfully awarded the contract to HTS as the lowest responsible bidder. We reverse and remand for entry of summary judgment in the city’s favor.

The material facts are undisputed and arose out of the award of a public contract for a street improvement project in Bend. The city invited bids for a project entitled “Olney Avenue Realignment Phase III.” In the written “invitation for bids,” the city gave notice that sealed bids would be “accepted at the City of Bend Public Works Department Training Room by Bob Griffith, Purchasing Manager, 1375 NE Forbes Road, Bend, Oregon” until 11:00 a.m. on March 9, 2001.1 The invitation for bids directed that bids be submitted under seal and marked with the title of the project. The invitation for bids also specified that the project was subject to ORS chapter 279, to the city’s municipal code, and to the Attorney General’s Model Public Contract Rules. Finally, the invitation for bids recited that the city “may reject any bid not in compliance with all prescribed procedures and requirements [.] ”

Attached to the invitation for bids was, among other documents, a set of “Instructions to Bidders.” The instructions identified grounds for rejection or disqualification of a bid. Specifically, the instructions told bidders that the failure to submit the required security with the bid “shall be cause

[495]*495HTS submitted the bid that led to this dispute. HTS addressed its bid envelope to “City of Bend Public Works, Bob Griffith Purchasing MGR, 1375 NE Forbes Rd, Bend, Or[.]” An HTS representative took the bid to Bend City Hall, which is about 1.5 miles from the Public Works Building, where he spoke with Barbara Harriman, an administrative assistant. The HTS representative stated that he was not certain he was in the right place for delivery of bids. Harriman, noting that the bid was for the Olney Street Project, said that she would put the HTS bid in Griffith’s mailbox at City Hall, which he checks daily. She then marked the date (March 9) and time (9:57 a.m.) on HTS’s envelope, wrote her initials next to those markings, and immediately placed the bid in Griffith’s mailbox. Griffith went to City Hall before the 11:00 a.m. deadline and picked up his mail, including HTS’s unopened bid. He then took the envelope to his office at the Public Works Department, where it remained in his personal possession until the bids were publicly opened at 3:00 p.m.

A total of five contractors submitted bids on the project. The other four bidders — which included JAL — delivered their bids to the Public Works Department. None of them delivered their bids to Griffith personally or to the Training Room of the Public Works Department. Instead, they all gave the bids to one of two clerks. In each instance, the clerk initialed and stamped the outside of the envelope with the time and date of receipt.

Before opening the bids, Griffith disclosed the circumstances of his receipt of the HTS bid. JAL did not have a representative present, but one of the other bidders was there and objected to Griffith’s acceptance of the HTS bid. Because Griffith believed that delivery of the bid to his City [496]*496Hall mailbox sufficed, he opened the bid along with the others. HTS’s bid was the lowest among the five, so the city awarded the project to HTS.

JAL filed this action pursuant to ORS 279.067,2 alleging that, because HTS had delivered its bid to Griffith’s mailbox at City Hall rather than to the Public Works Building, the city should not have awarded the contract to HTS. JAL sought damages for the cost of preparing its bid and attorney fees.3 Both parties moved for summary judgment, agreeing that HTS delivered its bid to City Hall rather than to the Public Works Building. The parties’ motions thus presented the trial court with a purely legal question: whether the city legally awarded the contract to HTS.4 The trial court concluded that the award was unlawful and therefore granted JAL’s motion and denied the city’s. We review the rulings on the cross-motions for summary judgment to determine which party, if either, is entitled to judgment as a matter of law. Powell v. Bunn, 185 Or App 334, 340, 59 P3d 559 (2002), rev den, 336 Or 60 (2003).

The process for awarding public contracts through competitive bidding is governed by ORS chapter 279 and model rules promulgated by the Oregon Attorney General. See ORS 279.049.5 In general, and as pertinent to this case, [497]*497the procedures for awarding public contracts can be divided into four categories of activities: (1) advertisement of the fact that the agency will accept bids for a public works contract; (2) a written “invitation for bids” that provides information about the project and the procedures for submitting bids;6 (3) the preparation and submission of bids; and (4) the consideration of bids and the award of the contract by the public entity. The first two activities are informational in nature— that is, they concern the information that the government must provide to potentially interested bidders. The latter two have to do with the actual process by which bids are submitted and the successful bidder is selected.

Relatively few of the extensive provisions governing the public contracting process are concerned specifically with the delivery of bids. By statute, the information given to the public — i.e., the advertisement and the written invitation— must include the “name and title of the person designated for receipt of bids[.]” ORS 279.025(2)(f); ORS 279.027(1)(f). The model rules have the same requirement, but supplement it by requiring the official’s address to be listed. In particular, the advertisement must state the “address of the Agency person authorized to receive” bids. OAR 137-030-0015(2)(d)(E). The invitation for bids must include “[instructions and information concerning submission requirements including the address of the office to which [bids] must be delivered and any other special information * * OAR 137-030-0010(3)(a)(D).

Nothing in the statutes or model rules governing the actual submission of bids requires delivery to be to a particular site or physical location. The model rules require only that bids be submitted in accordance with the invitation to [498]*498bid. OAR 137-030-0020(1).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dental v. City of Salem
103 P.3d 1150 (Court of Appeals of Oregon, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
83 P.3d 332, 191 Or. App. 492, 2004 Ore. App. LEXIS 38, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jal-construction-inc-v-friedman-orctapp-2004.