Jacques v. Goodson

2024 NY Slip Op 51889(U)
CourtNew York County Court, Saratoga County
DecidedJune 18, 2024
DocketIndex No. 2023679
StatusUnpublished
AuthorSchopf

This text of 2024 NY Slip Op 51889(U) (Jacques v. Goodson) is published on Counsel Stack Legal Research, covering New York County Court, Saratoga County primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jacques v. Goodson, 2024 NY Slip Op 51889(U) (N.Y. Super. Ct. 2024).

Opinion

Jacques v Goodson (2024 NY Slip Op 51889(U)) [*1]

Jacques v Goodson
2024 NY Slip Op 51889(U)
Decided on June 18, 2024
County Court, Saratoga County
Schopf, J.
Published by New York State Law Reporting Bureau pursuant to Judiciary Law § 431.
As corrected in part through December 31, 2025; it will not be published in the printed Official Reports.


Decided on June 18, 2024
County Court, Saratoga County


Jordan Jacques, Plaintiff,

against

Phil Goodson, Defendant.




Index No. 2023679

John Dowd, Esq.
Dreyer Boyajian, LLP
Attorney for the Plaintiff
75 Columbia Street
Albany, New York 12210

Mr. Phil Goodson, Sr.
Defendant, pro se Jonathan G. Schopf, J.

Plaintiff, Jordan Jacques, brought an action against defendant alleging damages of $9,720.00 due to defendant's breach of contract, negligence, and breaches of warranty concerning a remodeling job of the plaintiff's bathroom which was to be performed by the defendant. Defendant submitted a timely Answer to the Complaint and the Court will accept the Answer and the affirmative defenses contained therein as a general denial to the claims of the plaintiff and a counterclaim for payment on the outstanding sums contained within the subject contract. The parties appeared on May 30, 2024 for a trial of the within matter. Following which, the Court makes the following findings of fact and conclusions of law.

The parties, both of whom are licensed home inspectors by trade met at a home inspection instructional course and became friends prior to the occurrences which are the subject of the instant lawsuit. They entered into a written and valid contract via text (SMS) message on or about October 29, 2022 after the defendant sent a detailed text message of the work that he proposed to perform at the residence owned by the plaintiff (P Ex. 1 P-1000006). The contract was for the remodel of the plaintiff's bathroom. The total contract price for the gut and remodel [*2]bathroom renovation was $12,000.00 [FN1] to be paid in 1/3 installments in addition to materials, which plaintiff agreed to purchase. Although there is no affirmative text response consenting to the terms as drafted by the defendant, the parties testified that they so agreed and there is no dispute as to the existence of the contract.

The defendant began work on the project on or about November 2, 2022 at which time the plaintiff provided the defendant with a check in the amount of $6,000.00. During the course of the demolition portion of the project, on or about November 5, 2022 the water supply line from the disconnected toilet began to leak. Unfortunately, the main shutoff valve at the house supply was broken and the water was unable to be shut off. This caused damage to the ceiling of the dining room / kitchen area below the bathroom. Although it was not required under the terms of the contract, the defendant paid out of pocket for an on-call plumbing repair to the main house valve. The amount paid was $457.75 and the defendant verbally told the plaintiff that he would cover this cost as a good will gesture. In addition to this payment, the defendant testified that he hired a subcontractor to perform the demolition work at a cost to defendant of $1,090.00 and a second sub-contractor for the floor tile at a cost to defendant of $900.00.

On November 12, 2022, November 23, 2022, and December 7, 2022 the plaintiff transmitted funds in the amount of $1,577.00, $903.00, and $1,240.00 for a total of $3,720.00 to the defendant as payment for materials (P Ex. 3). These are supported by receipts received into evidence as plaintiff's Exhibit 4. Such receipts total $3,671.15, a difference of $48.85, for which the plaintiff overpaid.

On December 19, 2022, the plaintiff ordered the defendant off of the job site via a text message (P Ex. 13) citing that "the tile work is really bad in locations and this is taking too long..." Plaintiff then demanded a refund of $9,750.00. Defendant refused to refund the money demanded and made his own demand for payment in full of the remaining balance due him under the contract of $6,000.00 via a text message on December 21, 2022.

The plaintiff testified that he took photos of the progress of the work. These photos were admitted into evidence as Plaintiff's Exhibits 6, 9 and 15. He further testified that he observed the job on a day that the subcontractor was installing tile, when he came back to the home later in the day, the tiles were falling off the walls and there was an observation of minimal thin-set adhesive in place. He also observed that the floor tiling was "lipped" (uneven), that the shower pan was not correct, was out of plumb and that the shower niches were out of square. When these issues were discussed with the defendant, it was agreed that the work would be re-done and the subcontractor [FN2] who installed that tile would not be involved. The defendant removed and replaced the wall tile in the shower but did not renovate the floor tiling, asserting that this flooring was of sufficient quality and that any issues were aesthetic in nature and did not affect the functionality of the tile.

The plaintiff was still not happy with the quality of work, and he testified that there were numerous defects as he described when shown photographs number 1, 2, 3, 4, 5, 7, 10, 11, 15, 17,20, 21, 23, 26, 30, 33, 38, 43, 44, and 53 of Plaintiff's Exhibit 15. Due to these defects as-[*3]well-as the rate at which the work was being performed, the plaintiff elected to order the defendant off of the job and terminate the contract. Thereafter, the defendant arrived at the residence on December 20, 2022, picked up his tools and left the job site.

The defendant was permitted to testify on direct in the narrative. He testified in a truthful and honest manner throughout the trial. Defendant's legal position and defense, in essence, is that the plaintiff prevented him from finishing the job and that had he been able to finish, the end product would have been acceptable. Defendant avers that he should have had an opportunity to complete the project and that the plaintiff is not entitled to a refund of any money for labor or materials.

He also testified that many of the plaintiff's issues with the work were aesthetic in nature and that the workmanship was acceptable. The testimony given by defendant was that he is essentially a "do-it-yourself" handyman generalist who has completed a variety of tiling and remodeling projects for other satisfied customers in the past; he is not licensed or certified to install tile [FN3] ; that he continued to remind the plaintiff that the project would take longer, especially after the termination of the subcontractors; and that he had no idea the plaintiff was dissatisfied with the re-installation of the wall tile until he was terminated. He also testified that he believed the project to be at the 25-40% complete stage when he was terminated.

Plaintiff's Expert

Plaintiff called Chad Fabry as an expert witness who was qualified as such on stipulation of the parties. Mr. Fabry has an extensive background as it relates to floor tiling installation, structural systems and general construction methods. His qualifications are set forth in his disclosure admitted as part of Plaintiff's Exhibit 7 and his testimony before the Court. The Court finds him qualified and credible.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

WorldCom, Inc. v. Sandoval
182 Misc. 2d 1021 (New York Supreme Court, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
2024 NY Slip Op 51889(U), Counsel Stack Legal Research, https://law.counselstack.com/opinion/jacques-v-goodson-nysaratogactyct-2024.