Jacksonville Hotel Building Corp. v. Dunlap Hotel Co.

183 N.E. 397, 350 Ill. 451
CourtIllinois Supreme Court
DecidedOctober 22, 1932
DocketNo. 21282. Reversed and remanded.
StatusPublished
Cited by14 cases

This text of 183 N.E. 397 (Jacksonville Hotel Building Corp. v. Dunlap Hotel Co.) is published on Counsel Stack Legal Research, covering Illinois Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jacksonville Hotel Building Corp. v. Dunlap Hotel Co., 183 N.E. 397, 350 Ill. 451 (Ill. 1932).

Opinion

Mr. Chief Justice Heard

delivered the opinion of the court:

This cause is here upon a certificate of importance from the Appellate Court for the Third District for a review of its judgment reversing, on error, a decree of the circuit court of Sangamon county for the specific performance of a contract by appellee, the Dunlap Hotel Company, in favor of appellant, the Jacksonville Hotel Building Corporation.

M. F. Dunlap, a banker of Jacksonville, Illinois, recognizing the need of the city of Jacksonville for a modern hotel building, in 1922 called into conference several citizens and commenced the promotion of a building corporation to construct a hotel in that city. E. O. and E. S. Perry, operators of the New Leland Hotel at Springfield, Illinois, hearing of the proposed hotel, called upon Dunlap with reference to a lease of the building when completed and thereafter carried on negotiations in relation thereto. Preliminary plans of the proposed hotel were drawn by Jarvis Hunt, a Chicago architect, at the direction of Dunlap, and negotiations were carried on between the parties upon the basis of those plans. On June 11, 1924, Dunlap made a written proposition to the Perrys, which was on that date accepted in writing by them. This proposition, so far as here material, was in substance as follows:

“M. F. Dunlap, on behalf of Jacksonville Hotel Company, a corporation, with a capital stock of $200,000, fully subscribed, now in process of organization, makes the following proposal to E. O. Perry and E. S. Perry, of Springfield, Illinois: That said corporation will acquire a site in Jacksonville, Illinois, and erect thereon a hotel building, the site to be either on property lying east of the present Dunlap House and approximately as shown on a certain block plan prepared by T. C. MacVicar dated February 14, 1924, or on the site of the present Dunlap House and approximately as shown on the block plan prepared by T. C. Mac-Vicar and dated January 16, 1924; that the said hotel shall be of the approximate dimensions of one hundred and eighty (180) feet by eighty-eight (88) feet, and shall be five stories high, and of approximately one hundred and twenty (120) to one hundred and thirty (130) rooms’ capacity, and shall be constructed along the general lines of certain plans prepared by Jarvis Hunt, all dated January 16, 1924, except that of the first floor plan prepared by the same architect which is dated February 6, 1924, and also corresponding approximately to the elevation plan prepared by the same architect dated February 14, 1924, all of which plans have already been submitted to you and approved by you, it being expressly understood, however, that the final working plans as to matters of detail shall be subject to your approval if you accept the proposition; that said corporation will proceed with the erection of such hotel building with all reasonable dispatch; that said corporation will promptly, after securing its certificate of incorporation, enter into an agreement with you for a lease of the said premises to you, or, at your option, to the Perry-Rigby Hotel Company, or to a new hotel company to be organized by you for the purpose of operating the said hotel, provided said new company has at the time of taking such lease a net worth at least equal to the cost of furnishing said hotel, complete and ready to operate, in keeping with the character of hotel erected by the lessor corporation, said lease to be for the term of twenty years from the date said building is tendered to such lessee ready for occupancy, at a yearly rental of an amount equal to six and one-fourth per cent on the audited cost of said leased property, to be determined as hereinafter provided, payable in equal monthly installments in advance.”

The first completed plans for the hotel building are dated September 25, 1924, and E. S. Perry, after examining them, on October 29, 1924, approved the same in writing. The building, however, was not built in accordance with these plans. Bids were taken upon them which exceeded the maximum amount specified by Dunlap, and in his judgment it became necessary to reduce the cost, and to accomplish that result, J. B. French, the best bidder, was called in, and after discussion it was agreed between him and Dunlap’s representatives that he should proceed with the building with certain changes to be worked out by the architect, and such changes are shown by plans dated January 23, 1925. These plans of January 23 were not assented to by either of the Perrys, and it appears from the weight of the evidence that no revision or changes of plans and specifications were submitted to the Perrys. The architect’s representative in charge of the job testified that at no time did he consult the Perrys with reference to the changes in the bids or the plans of January 23, 1925. The erection of the building in accordance with the plans of January 23, 1925, proceeded, and in the late fall of 1925 the hotel building appeared to be nearing completion and all parties seemed anxious to have it opened before the holidays. In October, 1925, the Perrys caused the Dunlap Hotel Company to be incorporated and commenced buying equipment with which to furnish the hotel. Neither Edward S. nor E. O. Perry was an engineer or a builder, and from their testimony and the proofs in this case neither had knowledge of the change of plans in the construction of the building. Appellant notified appellee that the building would be ready for occupancy on November 30, 1925. Appellee moved into the building on December 1, 1925, before the building was completed. For some time there was talk about remitting one-half of a month’s rent, and on March- 1, 1926, appellee paid one and one-half month’s rent on the basis of interest on $400,000, but it was agreed by all parties that the cost of the building was not then known. No lease was ever signed by the Perrys or by appellee. In the organization of appellee the two Perrys and Gertrude S. Perry were the stockholders in the corporation. On January 9, 1926, S. W. Straus acquired a financial interest in the corporation and became a director, taking over the interest of Gertrude S. Perry. The record does not show the various corporate interests of these parties in appellee. Thereafter negotiations were had between Dunlap and the Perrys concerning the proposed lease from appellant to appellee, and on March 11, 1926, appellee’s attorney wrote Dunlap a letter with reference thereto, containing, among other things, the following: “An examination of the plans and the contract discloses such wide differences between the building contemplated and the building actually erected that a lease of the kind specified cannot be justly based upon the specifications for the payment of rents, the reason being that the lessee would get a hotel with fewer rooms, inferior construction which would result in greater expense of maintenance, excessive insurance charges, and general lack of compliance with the plans upon which the rental was to be based. * * * I wish you, however, to understand that my clients are ready and willing to enter into a lease and pay rents in accordance with the terms of the contract of June 11, 1924, if you or the hotel company will furnish them such a building as that contract obligates you and them to build, and I hereby offer for them to execute such a lease on such a building.”

On April io, 1926, the Jacksonville Hotel Building Corporation, by M. E.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Marriage of Sobieski
2013 IL App (2d) 111146 (Appellate Court of Illinois, 2013)
Dixon v. City of Monticello
585 N.E.2d 609 (Appellate Court of Illinois, 1991)
Intaglio Service Corp. v. J. L. Williams & Co.
420 N.E.2d 634 (Appellate Court of Illinois, 1981)
Franzen v. Dubinok
427 A.2d 1002 (Court of Appeals of Maryland, 1981)
Gras v. Clark
361 N.E.2d 316 (Appellate Court of Illinois, 1977)
Kane v. American National Bank & Trust Co.
316 N.E.2d 177 (Appellate Court of Illinois, 1974)
Alexander Lumber Co. v. Busboom
259 N.E.2d 76 (Appellate Court of Illinois, 1970)
Williams v. DeLay
395 P.2d 839 (Alaska Supreme Court, 1964)
Pinkstaff v. Pennsylvania Railroad
202 N.E.2d 512 (Illinois Supreme Court, 1964)
Kars v. Knauf
141 N.E.2d 410 (Appellate Court of Illinois, 1957)
Harris v. Clinton
112 A.2d 885 (Supreme Court of Connecticut, 1955)
Bismarck Hotel Co. v. Andalman
73 N.E.2d 786 (Appellate Court of Illinois, 1947)
Wloczewski v. Kozlowski
70 N.E.2d 560 (Illinois Supreme Court, 1946)
Davis v. Robinson
23 N.E.2d 816 (Appellate Court of Illinois, 1939)

Cite This Page — Counsel Stack

Bluebook (online)
183 N.E. 397, 350 Ill. 451, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jacksonville-hotel-building-corp-v-dunlap-hotel-co-ill-1932.