Jackson Contractor Group Inc v. Travelers Casualty and Surety Company of America

CourtDistrict Court, E.D. Washington
DecidedJanuary 5, 2024
Docket2:22-cv-00178
StatusUnknown

This text of Jackson Contractor Group Inc v. Travelers Casualty and Surety Company of America (Jackson Contractor Group Inc v. Travelers Casualty and Surety Company of America) is published on Counsel Stack Legal Research, covering District Court, E.D. Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jackson Contractor Group Inc v. Travelers Casualty and Surety Company of America, (E.D. Wash. 2024).

Opinion

1 2

3 4 5 UNITED STATES DISTRICT COURT EASTERN DISTRICT OF WASHINGTON 6

7 TRAVELERS CASUALTY AND SURETY COMPANY OF NO. 2:22-CV-0178-TOR 8 AMERICA, ORDER DENYING THIRD-PARTY 9 Third-Party Plaintiff, PLAINTIFF’S MOTION FOR SUMMARY JUDGMENT 10 v.

11 FLAWLESS WALLS LLC, a Washington Limited Liability 12 Company, MICHAEL BRADLEY, an individual, JEREMY BOUCHEY, an 13 individual, JAMIE GORE, an individual, PAUL CASSEL, an 14 individual, KORTNEY CASSEL, an individual, DELMAR, LLC, a 15 Washington limited liability company, JROTH, LLC, a 16 Washington limited liability company, CASSEL UNLIMITED, 17 LLC, a Washington limited liability company, 18 Third-Party Defendants. 19

20 BEFORE THE COURT is Third-Party Plaintiff’s Motion for Summary 1 Judgment (ECF No. 68). This matter was submitted for consideration without oral 2 argument. The Court has reviewed the record and files herein and is fully

3 informed. For the reasons discussed below, Third-Party Plaintiff’s Motion for 4 Summary Judgment (ECF No. 68) is DENIED. 5 BACKGROUND

6 This case involves indemnification of Third-Party Plaintiff Traveler’s 7 Casualty and Surety Company (“Travelers”) for settlement with Jackson 8 Contractor Group, Inc. (“Jackson”) on behalf of Flawless Walls, Inc (“Flawless”). 9 Third-Party Plaintiff Travelers, Defendant in the underlying lawsuit, is a

10 Connecticut corporation licensed for insurance in Washington State. ECF No. 17 11 at 2, ¶ 2. Third-Party Defendant Flawless is a Washington limited liability 12 company, Defendant Cassel Unlimited, LLC is a Washington limited liability

13 company, Defendant Delmer, LLC, is a Washington limited liability company, 14 Defendant JROTH, LLC is a Washington limited liability company, and each of 15 the named individual defendants are Washington State citizens. ECF No. 73 at 2– 16 3, ¶¶ 1–11. The Court has jurisdiction under 28 U.S.C. § 1332(a), as there is

17 complete diversity between Travelers and all Third-Party Defendants, and the 18 amount in controversy exceeds $75,000. 19 On February 9, 2021, Flawless entered in a subcontract with Jackson to

20 perform work on Schweitzer Mountain Hotel and Resort. ECF No. 1 at 3, ¶ 6. On 1 February 25, 2021, pursuant to the agreement, Flawless obtained a Payment Bond 2 and a Performance Bond from Travelers to cover payment and performance of the

3 subcontract work for Jackson in the amount of $618,187. ECF No. 69 at 3, ¶ 2. In 4 relevant part the surety bond provided that: 5 [T]he condition of this obligation is such that if the Principal shall perform the Construction Work to be done under the Subcontract, then 6 this obligation shall be null and void; otherwise to remain in full force and effect. The Surety’s obligation hereunder shall not arise unless 7 Principal is in default under the Subcontract for failing to perform the Construction Work, and has been declared by the Obligee to be in 8 default under the Subcontract for failing to perform the Construction Work; and the Obligee has performed its obligations under the 9 Subcontract.

10 ECF No. 40-1 at 2.

11 As a condition for surety, Third-Party Defendants were required to enter into 12 an indemnity agreement, in which they would “exonerate, indemnify and save 13 [Travelers] harmless from and against all Loss . . . Amounts due to [Travelers] 14 shall be payable on demand.” Id. at 3, ¶ 3. The agreement also contained a clause 15 regarding the settlement of claims: 16 Company shall have the right, in its sole discretion, to determine for itself, and Indemnitor whether any claim, demand or suit brought 17 against Company or any Indemnitor in connection with or relating to any Bond shall be paid, compromised, settled, tried, defended or 18 appealed, and its determination shall be final, binding and conclusive upon the Indemnitors. Company shall be entitled to immediate 19 reimbursement for any and all Loss incurred under the belief it was necessary or expedient to make such payments. 20 1 ECF No. 70-2 at 1–2, ¶ 4. 2 On May 11, 2021, Jackson provided Flawless with a Notice of

3 Supplementation of work due to what it characterized as Flawless’ inability to 4 meet the agreed upon schedule. ECF No. 1 at 4, ¶ 13. However, Flawless 5 maintains that any failure to meet deadlines was due to Jackson’s mismanagement

6 and changing of construction plans. ECF No. 42 at 4–5, ¶¶ 7, 8. On or about 7 August 26, 2021, the contractual agreement between Flawless and Jackson ceased 8 to exist. Within filings pursuant the underlying lawsuit, Jackson asserted that 9 Flawless gave notice that it was going out of business and ceased all work on the

10 Subcontract project. ECF No. 1 at 5, ¶ 16. Flawless asserts that the subcontract 11 was mutually dissolved on August 13, 2021, with the expectation that Flawless 12 would complete select remaining projects and the subcontract would be

13 extinguished. ECF No. 42 at 5, ¶ 7. Specifically, according to Defendants, the 14 renegotiated contract was mutually beneficial as the working relationship with 15 Jackson had broken down. ECF No. 78-1 at 5. As a condition for this agreement, 16 Flawless would not receive payment for the work completed pursuant to the

17 August 2021 payment application. ECF No. 42 at 6, ¶ 8. 18 On March 25, 2022, Jackson sent a demand for payment under the 19 performance bond to Travelers, claiming losses in the amount of $753.154.40,

20 which Travelers denied. ECF Nos. 69 at 4, ¶ 6, 40-4 at 2–9. The underlying 1 lawsuit commenced on July 26, 2022. ECF No. 1. On December 16, 2022, 2 Jackson brought a motion for partial summary judgment. ECF No. 26. The Parties

3 notified the Court on February 21, 2023, that Travelers reached a settlement with 4 Jackson for $325,000 in exchange for full release of the bonds, before a decision 5 was rendered on the motion for summary judgment. ECF No. 70-3 at 2, ¶ 2. The

6 settlement agreement, dated May 2, 2023, also contained a provision that released 7 any claims Flawless may raise in connection with the action, including the 8 underlying subcontract with Jackson. Id. at ¶ 4. 9 In the interim, Travelers asserted a third-party complaint against Defendants

10 to indemnify it for the loss incurred settling the bond with Jackson, plus attorney’s 11 fees and related costs. ECF Nos. 60, 73. As it relates to this third-party action, the 12 parties generally disagree as to whether Travelers was exposed to liability under

13 the surety agreement. Defendants assert that Flawless performed under the 14 subcontract, and that Travelers had agreed that Jackson’s claim lacked merit under 15 the performance bond. ECF No. 75 at 7. Travelers asserts that its settlement with 16 Jackson was within the bounds of the indemnity agreement and “necessary and

17 expedient to resolve [Jackson’s] claim.” ECF No. 69 at 5, ¶ 10. 18 Travelers filed this motion for summary judgment on November 2, 2023, 19 arguing that no issue of material fact remains because the language of the

20 agreement is clear in granting Travelers the ability to settle all claims it deems 1 necessary or expedient per the indemnity clause. ECF No. 68 at 7. Flawless 2 responded, arguing in part that Travelers breached its duty of good faith and fair

3 dealing in the settling of the underlying lawsuit, as evidence existed on the record 4 that Jackson’s claims had no merit, and therefore it was not “necessary or 5 expedient” to settle the claim. ECF No. 75 at 6–7.

6 DISCUSSION 7 I. Summary Judgment Standard 8 Summary judgment may be granted to a moving party who demonstrates 9 “that there is no genuine dispute as to any material fact and the movant is entitled

10 to judgment as a matter of law.” Fed. R. Civ. P.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Erie Railroad v. Tompkins
304 U.S. 64 (Supreme Court, 1938)
First Nat. Bank of Ariz. v. Cities Service Co.
391 U.S. 253 (Supreme Court, 1968)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Scott v. Harris
550 U.S. 372 (Supreme Court, 2007)
Lomont, Kent A. v. O'Neill, Paul H.
285 F.3d 9 (D.C. Circuit, 2002)
Jones v. Strom Construction Co.
527 P.2d 1115 (Washington Supreme Court, 1974)
Scott Galvanizing, Inc. v. Northwest EnviroServices, Inc.
844 P.2d 428 (Washington Supreme Court, 1993)
Pacific Gamble Robinson Co. v. Pay'n Save Drugs, Inc.
469 P.2d 571 (Court of Appeals of Washington, 1970)
Edmonson v. Popchoi
256 P.3d 1223 (Washington Supreme Court, 2011)
Poutre v. Saunders
143 P.2d 554 (Washington Supreme Court, 1943)
Rekhter v. Department of Social & Health Services
323 P.3d 1036 (Washington Supreme Court, 2014)
Colorado Structures, Inc. v. Insurance Co. of the West
161 Wash. 2d 577 (Washington Supreme Court, 2007)
Frank Coluccio Construction Co. v. King County
150 P.3d 1147 (Court of Appeals of Washington, 2007)
Bond Safeguard Insurance v. Wisteria Corp.
173 Wash. App. 1026 (Court of Appeals of Washington, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
Jackson Contractor Group Inc v. Travelers Casualty and Surety Company of America, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jackson-contractor-group-inc-v-travelers-casualty-and-surety-company-of-waed-2024.