J. Lee Milligan, Inc. v. CIC Frontier, Inc.

289 F. App'x 786
CourtCourt of Appeals for the Fifth Circuit
DecidedAugust 19, 2008
Docket07-11048
StatusUnpublished
Cited by1 cases

This text of 289 F. App'x 786 (J. Lee Milligan, Inc. v. CIC Frontier, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J. Lee Milligan, Inc. v. CIC Frontier, Inc., 289 F. App'x 786 (5th Cir. 2008).

Opinion

PER CURIAM: *

A jury found in favor of J. Lee Milligan, Inc. (“Milligan”) in a breach of contract suit brought by Milligan against CIC Frontier, Inc. (“CIC”). CIC appeals on numerous grounds from the final judgment entered against it by the United States District Court for the Northern District of Texas. CIC’s arguments on appeal do not warrant reversal, so we AFFIRM, except that because Milligan is the prevailing party on appeal, we VACATE the portion of the district court’s order failing to award appellate attorneys’ fees and REMAND for the limited purpose of having the district court calculate Milligan’s appellate attorneys’ fees. We retain jurisdiction of this appeal pending the district court’s compliance with our limited remand.

I. BACKGROUND

Milligan is a highway construction contractor. CIC is an asphalt supplier. The parties had never done business together until the disputed transactions at issue in this suit. On November 1, 2005, Milligan and CIC entered into two contracts, Sales Order 1347 and Sales Order 1348. Under Sales Order 1347, CIC agreed to supply asphalt to Milligan at a fixed price of $375 per ton for a Texas Department of Transportation (“TxDOT”) project in Gray *788 County, Texas. Under Sales Order 1348, CIC agreed to supply asphalt to Milligan at a fixed price of $375 per' ton for a TxDOT project in Armstrong County, Texas.

Each Sales Order consisted of four pages. The front page included in relevant part a payment term of “Net 10 Days,” and a delivery term of “FOB MUSKOGEE.” The last three pages of each contract contained general terms and conditions, including a provision for attorneys’ fees. Both were prepared on CIC’s standard sales order form.

On June 28, 2006, Milligan began drawing asphalt under Sales Order 1347. The charge for the initial shipment was $9,041.25. CIC delivered seven asphalt shipments under Sales Order 1347 totaling $64,372.50. CIC mailed Milligan an invoice dated June 30, 2006, requesting payment from Milligan for CIC’s initial asphalt shipment. On July 10, 2006, Milligan mailed a check to CIC at its Muskogee office for $9,041.25. CIC received the check on July 12, 2006.

Milligan received a letter from CIC dated July 6, 2006, canceling Sales Order 1348 and informing Milligan that it would not supply the asphalt for the Armstrong County project. On July 11, 2006, Milligan received another letter from CIC invoking the force majeure clauses of both Sales Orders, and “canceling all contracts and deliveries of [asphalt].” Milligan’s counsel advised CIC that Milligan intended to treat CIC’s actions as a breach of both Sales Orders, and that Milligan would offset payments it owed to CIC against the damages it sustained as a result of CIC’s breach. Milligan also stopped payment on its check to CIC in the amount of $9,041,25 for the initial asphalt shipment under Sales Order 1347.

Milligan immediately began searching for another asphalt supplier for both TxDOT projects. Due to rapidly escalating asphalt prices, however, Milligan could not find a supplier that would agree to provide the asphalt at a fixed price. Milligan had to contract with Valero Marketing and Supply Company (‘Valero”) to supply asphalt for both TxDOT projects at “rack price,” which fluctuates depending on market conditions. Milligan paid Valero $495 per ton for the asphalt necessary to complete the Gray County project that was originally the subject of Sales Order 1347. 1 Milligan had not yet needed asphalt for the Armstrong County project, originally the subject of Sales Order 1348, when this case went to trial.

Milligan filed suit against CIC on August 4, 2006, alleging breach of contract under both Sales Orders. CIC denied breaching either Sales Order, and it counterclaimed for the unpaid amounts on the asphalt delivered under Sales Order 1347. The parties stipulated that Oklahoma law applied. After Milligan finished putting on its case-in-chief, CIC moved for judgment as a matter of law and demanded that Milligan take nothing. The district court denied CIC’s motion. The jury returned a verdict in favor of Milligan, and awarded Milligan $205,474.57 in damages for breach of Sales Order 1347 and $129,937.50 2 in damages for breach of Sales Order 1348. *789 The district court also awarded Milligan $118,124.50 in attorneys’ fees and $5,042.12 in costs. CIC appeals the final judgment entered against it, totaling $458,560.69. CIC raises numerous issues on appeal, only some of which warrant any discussion and, accordingly, they are addressed below.

II. DISCUSSION

A. “Net 10 Days” and Sales Order 1347

CIC argues that, as a matter of law, it was justified in canceling Sales Order 1347 because Milligan failed to comply with the payment term “Net 10 Days.” CIC contends that “Net 10 Days” was neither ambiguous nor in need of explanation; rather, the term clearly required Milligan to have payment in Muskogee, Oklahoma ten days after the date of the invoice. Consequently, according the district court erred by admitting what CIC termed extrinsic evidence to explain the meaning of “Net 10 Days,” and by denying CIC’s motion for judgment as a matter of law concerning its alleged breach of Sales Order 1347.

Whether a contract is ambiguous is a conclusion of law that this court reviews de novo. Ham Marine, Inc. v. Dresser Indus., Inc., 72 F.3d 454, 458 (5th Cir.1995). A contract term is ambiguous if “ ‘it is reasonably susceptible to at least two different constructions’ such that ‘reasonably intelligent men[] on reading the contract would honestly differ as to its meaning.’ ” Otis Elevator Co. v. Midland Red Oak Realty, Inc., 483 F.3d 1095, 1102 (10th Cir.2007) (applying Oklahoma law) (quoting Piteo Prod. Co. v. Chaparral Energy, Inc., 63 P.3d 541, 545-46 & n. 19 (Okla. 2003)). In the present case, the term “Net 10 Days” was neither defined in nor explained by the terms of Sales Order 1347, leaving it reasonably susceptible to varying interpretations. Thus, we conclude that “Net 10 Days,” as used in Sales Order 1347, is an ambiguous term. When a contract term is ambiguous, the contract’s meaning may be determined in light of all extrinsic evidence. See Okla. Stat. Ann. tit. 12A § 2-202 (2007); see also Paragon Res., Inc. v. Nat’l Fuel Gas Distrib. Corp., 695 F.2d 991, 996 (5th Cir.1983). 3 Accordingly, the district court properly admitted extrinsic evidence to explain the meaning of the term “Net 10 Days.” 4

In light of the properly admitted extrinsic evidence, we turn to the issue of whether the district court properly denied CIC’s motion for judgment as a matter of law. We review de novo a district court’s ruling on judgment as a matter of law. Jordan v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

J. Lee Milligan, Inc. v. CIC Frontier, Inc.
291 F. App'x 655 (Fifth Circuit, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
289 F. App'x 786, Counsel Stack Legal Research, https://law.counselstack.com/opinion/j-lee-milligan-inc-v-cic-frontier-inc-ca5-2008.