J. E. Work, Inc. v. Lovell

433 P.2d 896, 72 Wash. 2d 516, 1967 Wash. LEXIS 825
Washington Supreme Court·Decided November 16, 1967·No. 38721·Published·Cited by 6 cases

Opinion

Ott, J.

J. E. Work, Inc., was awarded a construction contract for a part of the Randle-Yakima highway with the *517 United States Bureau of Public Roads, Department of Commerce. On December 21, 1962, R. H. Lovell and Evan D. LaRue, partners, doing business as the Olympic Construction Company, were awarded a subcontract to perform some of the bid items of the prime contract. The subcontractor was to be paid the full unit price of the bid items it contracted to perform. The subcontractor’s performance bond was furnished by Fidelity & Deposit Company of Maryland. (The partnership will hereafter be referred to as the Olympic Construction Company.)

After the work had commenced bid items 102(4) and 105(3) of the subcontract were deleted by mutual agreement. As the construction work progressed it became apparent that the Olympic Construction Company would not be able to perform its part of the subcontract within the time periods specified by the government’s progress schedule. Thereupon, performance of the subcontract was continued according to the' terms and conditions explained in a letter quoted as follows:

July 11,1963
Olympic Construction Co.
P. O. Box 308
Port Angeles, Wash.
Re: Randle Yakima Hwy.
Gentlemen:
This will confirm our conversation on procedures to be followed on the Randle-Yakima Highway following the inspection made by Mr. J. E. Work and J. P. Lally of this company on July 1,1963.
It has been apparent that Olympic Construction Co. will not be able to complete the work on this job as agreed to under subcontract to J. E. Work, Inc. This is borne out by a letter from the Bureau of Public Roads Resident Engineer dated July 5,1963.
On July 1, 1963, Mr. Larue [sic] and Mr. Lovell of your firm requested that J. E. Work, Inc. move men and equipment on that portion of the job which is being worked on by Olympic Construction. Company, in order to try to complete the work within the time limit specified in the basic contract. Mr. Lovell and Mr. Larue [sic] stated that Olympic Construction Co. could not possibly *518 complete the work with their forces. It was requested that J. E. Work, Inc. work on any and all items included under the Olympic Construction Co. subcontract in order that they could be completed. Payment by Olympic Construction Co. would be on the basis of time and material charges.
It was pointed out at that time and still is the position of J. E. Work, Inc., that we do not necessarily wish to perform work contracted by Olympic Construction Co. and would rather have Olympic Construction Co. complete the work themselves within the allotted time limit, or arrange to have it done. Olympic Const. Company, however, stated they preferred to have J. E. Work, Inc. equipment and men on the job as they are available at the site.
Therefore, J. E. Work, Inc. will furnish to Olympic Const. Co. all of its available equipment and personnel in the Packwood area to be used on any portion of Olympic contract that must be completed. Payment for this work will be as specified above. This will in no way relieve Olympic Const. Co. of its responsibility of completing the subcontract as agreed, and, should more equipment or men be needed, it will be the responsibility of Olympic Construction Co. to furnish it.
Very truly yours,
J. E. Work, Inc.
/s/ J. P. Lally
J. P. Lally, Sec’y-
/s/ R. H. Lovell
Olympic Construction Co.

J. E. Work, Inc., thereafter submitted daily reports of their man hours, equipment and materials furnished. Olympic Construction Company acknowledged in writing each day the receipt of the reports until near the completion of the contract. Each month J. E. Work, Inc., sent to Olympic Construction Company an itemized statement of the labor and manned equipment furnished by J. E. Work, Inc., and the amount it had charged Olympic Construction Company for the services rendered. The Olympic Construction Company received from J. E. Work, Inc., monthly payments and/or credits in the amount of the difference be *519 tween the sum due under its subcontract and the amount J. E. Work, Inc., claimed for services performed. The Olympic Construction Company kept its crew and equipment working until approximately September 15.

Upon the completion of the construction project and its acceptance by the government in October 1963, an alleged outstanding credit balance existed in favor of J. E. Work, Inc. J. E. Work, Inc., commenced this action to recover from Olympic Construction Company and the surety company the sum of $28,547.49 which it alleged was due and owing for materials, labor and equipment furnished.

The cause was tried to the court which awarded J. E. Work, Inc., a judgment against the Olympic Construction Company and the Fidelity & Deposit Company of Maryland the sum of $27,248.28. From the entry of the judgment Olympic Construction Company has appealed.

Appellant first asserts that the cause of action was prematurely commenced for the reason that there was a pending claim with the government for additional compensation alleged due appellant for work performed on pay items attributable to its subcontract. Appellant’s pending claim with the government is for the sum of $22,048.02. At a pretrial hearing the appellant moved to strike the cause from the trial calendar. The record before us establishes that the respondent disclaimed any interest in the appellant’s claim with the government prior to trial. During the trial when the question was again raised, respondent, in writing, relinquished any and all interest in the claim. We agree with the trial court that appellant’s claim is unrelated to any issue here presented. Boespflug v. Wilson, 58 Wn.2d 333, 335, 362 P.2d 747 (1961).

Appellant assigns error to the trial court’s findings that the rates charged for labor and equipment supplied by respondent were reasonable. The appellant was apprised on a monthly statement the amount of the charges. No objection was made by appellant to the amount of the charges (except for one item which was thereafter settled by mutual agreement). The respondent’s evidence established *520 that the rates were those customarily charged by the industry for like work and services rendered in the area. There is substantial evidence to support the trial court’s factual finding in this regard and we will not disturb it. Sigman v. Stevens-Norton, Inc., 70 Wn.2d 915, 919, 425 P.2d 891 (1967).

Free access — add to your briefcase to read the full text and ask questions with AI

J. E. Work, Inc. v. Lovell, 433 P.2d 896, 72 Wash. 2d 516, 1967 Wash. LEXIS 825 (Wash. 1967).

433 P.2d 896 (J. E. Work, Inc. v. Lovell) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

LaBarge v. Zebco
1988 OK 147 (Supreme Court of Oklahoma, 1988)
Northwest Television Club, Inc. v. Gross Seattle, Inc.
640 P.2d 710 (Washington Supreme Court, 1982)
Malott v. Randall
502 P.2d 1249 (Court of Appeals of Washington, 1972)
Bank of California v. First Mortgage Co.
495 P.2d 1057 (Court of Appeals of Washington, 1972)