J. Caldarera & Company, Inc. Versus Triumph Construction Company, LLC. and Atain Specialty Insurance Company

Louisiana Court of Appeal·Decided December 18, 2024·No. 24-C-451·Unknown

Opinion

J. CALDARERA & COMPANY, INC. NO. 24-C-451 VERSUS FIFTH CIRCUIT

TRIUMPH CONSTRUCTION COMPANY, COURT OF APPEAL LLC. AND ATAIN SPECIALTY INSURANCE COMPANY STATE OF LOUISIANA

ON APPLICATION FOR SUPERVISORY REVIEW FROM THE FORTIETH JUDICIAL DISTRICT COURT

PARISH OF ST. JOHN THE BAPTIST, STATE OF LOUISIANA NO. 70,409, DIVISION "B"

HONORABLE NGHANA LEWIS, JUDGE PRESIDING

December 18, 2024

STEPHEN J. WINDHORST

JUDGE

Panel composed of Judges Susan M. Chehardy, Fredericka Homberg Wicker, and Stephen J. Windhorst

REVERSED AND REMANDED; STAY ORDERED SJW SMC FHW

COUNSEL FOR PLAINTIFF/RELATOR, J. CALDARERA & CO., INC.

John W. Waters, Jr.

COUNSEL FOR DEFENDANT/RESPONDENT, TRIUMPH CONSTRUCTION COMPANY, LLC Gregory S. Webb

WINDHORST, J.

Relator, J. Caldarera & Company, Inc., seeks review of the trial court’s denial of its motion to compel arbitration. For the following reasons, we reverse the trial court’s ruling, grant Caldarera’s motion to compel arbitration, order a stay, and remand for further proceedings consistent with this disposition. BACKGROUND Caldarera contracted with the St. Tammany Parish School Board to construct Fontainebleau Junior High School. On May 4, 2015, Caldarera and Triumph Construction Co., LLC entered into a Subcontract Agreement relative to some of the work for the project, including the furnishing of labor and other services necessary for the construction and installation of concrete foundation and site pavement work.

A concrete pour was scheduled for Saturday, April 30, 2016, in advance of on-coming inclement weather. In preparation for the concrete pour, Caldarera dug and formed below grade trenches and arranged for the concrete delivery. Triumph’s workers, however, did not appear for the scheduled concrete pour. Rain destroyed the pre-dug trenches and caused cave-ins of earthen excavations. Triumph did not return to the construction project.

On March 8, 2017, Caldarera filed a petition for damages, asserting breach of contract and negligence claims, including failing to show up for the concrete pour. Caldarera alleged Triumph’s caused it damages, including cost of overhead, cost of project completion, cost to redo work and repair other parts of the project damaged by Triumph, and cost of acceleration.

Since Caldarera filed the original petition in 2017, the parties have litigated this case in the trial court by conducting discovery, engaging in motion practice, and appellate review involving the dismissal of one defendant. Trial has been continued multiple times. Because this case has been pending for seven years, recently, in July

24-C-451 1 2024, Caldarera filed a motion to compel arbitration based on a clause in the Subcontractor Agreement. The relevant clause regarding dispute procedure states:

25.2 All matters in controversy between Contractor and Subcontractor arising out of or related to his Subcontract, or the performance or breach of thereof ... shall by decided by arbitration . . . OR litigated in court in the 40th JDC at the option of the Contractor ....

After a hearing on August 2, 2024, the trial court denied Caldarera’s motion to compel arbitration. Caldarera seeks review of the denial of its motion to compel arbitration. LAW and ANALYSIS Because the relevant facts are not in dispute, this case presents a question of law subject to de novo review. FIA Card Services, N.A. v. Weaver, 10-1372 (La. 3/15/11), 62 So.3d 709, 712.

The Louisiana Legislature has indicated by statute that arbitration is favored.

La. R.S. 9:4201 states:

A provision in any written contract to settle by arbitration a controversy thereafter arising out of the contract, or out of the refusal to perform the whole or any part thereof, or an agreement in writing between two or more persons to submit to arbitration any controversy existing between them at the time of the agreement to submit, shall be valid, irrevocable, and enforceable, save upon such grounds as exist at law or in equity for the revocation of any contract.

The United States Supreme Court has also long recognized and enforced a “liberal

federal policy favoring arbitration agreements.” Howsam v. Dean Witter Reynolds, Inc., 537 U.S. 79, 83, 123 S. Ct. 588, 591, 154 L. Ed. 2d 491 (2002). The Louisiana Supreme Court has held that even when the scope of an arbitration clause is fairly debatable or reasonably in doubt, the court should construe the clause in favor of arbitration. Aguillard v. Auction Mgmt. Corp., 04-2804 (La. 6/29/05), 908 So.2d 1, 18. The presumption is heavy and arbitration should not be denied unless it can be said with positive assurance that an arbitration clause is not susceptible of an interpretation that could cover the dispute at issue. Id.

24-C-451 2

According to La. R.S. 9:4202, when there is a valid arbitration clause, the trial court “shall” stay the trial of the action until arbitration is had unless the applicant is in default in proceeding with the arbitration. Specifically, La. R.S. 9:4202 states:

If any suit or proceedings be brought upon any issue referable to arbitration under an agreement in writing for arbitration, the court in which suit is pending, upon being satisfied that the issue involved in the suit or proceedings is referable to arbitration under such an agreement, shall on application of one of the parties stay the trial of the action until an arbitration has been had in accordance with the terms of the agreement, providing the applicant for the stay is not in default in proceeding with the arbitration.

The Louisiana Supreme Court has held that La. R.S. 9:4202 allows a trial court to ascertain only two basic facts before ordering arbitration: (1) whether there is a dispute as to the making of the agreement and (2) whether a party has failed to comply with the agreement. International River Center. v. Johns-Manville Sales Corp., 02-3060 (La. 12/3/03), 861 So.2d 139, 140-42.

Louisiana courts have specifically held the arbitration statute does not allow the trial court to determine waiver issues. Id. at 144; Bartley, Inc. v. Jefferson Par. Sch. Bd., 302 So.2d 280, 283 (La. 1974); Nelson v. H20 Hair, Inc., 19-193 (La. App. 5 Cir. 5/22/19), 274 So.3d 747, 749 (issue of whether employer waived its right to arbitration could only be addressed by arbitrator); Arkel Constructors, Inc. v. Duplantier & Meric, Architects, L.L.C., 2006-1950 (La. App. 1 Cir. 7/25/07), 965 So.2d 455, 460 (the presumption is that the arbitrator should decide allegations of waiver, delay, or a like defense to arbitrability).

Guided by jurisprudence from both the United States Supreme Court and the Louisiana Supreme Court, we find the arbitration panel must decide the waiver issue in this case. Howsam, 537 U.S. at 84, 123 S.Ct. at 592; International River Center, 861 So.2d at 144; Arkel Constructors, Inc, 965 So.2d at 460. We therefore reverse the trial court’s ruling denying the motion to compel and grant that motion.

24-C-451 3

DECREE For the foregoing reasons, we reverse the trial court’s ruling denying the motion to compel arbitration, grant that motion, and order a stay of the trial court proceedings until arbitration has been had in accordance with La. R.S. 9:4202. We therefore remand this case to the trial court for disposition consistent with this opinion.

REVERSED AND REMANDED;

STAY ORDERED

24-C-451 4

SUSAN M. CHEHARDY CURTIS B. PURSELL CHIEF JUDGE CLERK OF COURT

SUSAN S. BUCHHOLZ

FREDERICKA H. WICKER CHIEF DEPUTY CLERK

JUDE G. GRAVOIS MARC E. JOHNSON STEPHEN J. WINDHORST LINDA M. WISEMAN JOHN J. MOLAISON, JR.

FIRST DEPUTY CLERK

SCOTT U. SCHLEGEL TIMOTHY S. MARCEL FIFTH CIRCUIT MELISSA C. LEDET

JUDGES 101 DERBIGNY STREET (70053)

DIRECTOR OF CENTRAL STAFF POST OFFICE BOX 489

GRETNA, LOUISIANA 70054 (504) 376-1400

(504) 376-1498 FAX

www.fifthcircuit.org

Free access — add to your briefcase to read the full text and ask questions with AI

J. Caldarera & Company, Inc. Versus Triumph Construction Company, LLC. and Atain Specialty Insurance Company, (La. Ct. App. 2024).

J. Caldarera & Company, Inc. Versus Triumph Construction Company, LLC. and Atain Specialty Insurance Company (J. Caldarera & Company, Inc. Versus Triumph Construction Company, LLC. and Atain Specialty Insurance Company) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Howsam v. Dean Witter Reynolds, Inc.
537 U.S. 79 (Supreme Court, 2002)
Arkel Constructors v. Duplantier & Meric
965 So. 2d 455 (Louisiana Court of Appeal, 2007)
Intern. River Ctr. v. Johns-Manville Sales
861 So. 2d 139 (Supreme Court of Louisiana, 2003)
Aguillard v. Auction Management Corp.
908 So. 2d 1 (Supreme Court of Louisiana, 2005)
Bartley, Inc. v. Jefferson Parish School Board
302 So. 2d 280 (Supreme Court of Louisiana, 1974)
FIA Card Services, N.A. v. Weaver
62 So. 3d 709 (Supreme Court of Louisiana, 2011)