J. C. Mahan Motor Co. v. Lyle

67 S.W.2d 745, 167 Tenn. 193, 3 Beeler 193, 1933 Tenn. LEXIS 25
CourtTennessee Supreme Court
DecidedJanuary 31, 1934
StatusPublished
Cited by9 cases

This text of 67 S.W.2d 745 (J. C. Mahan Motor Co. v. Lyle) is published on Counsel Stack Legal Research, covering Tennessee Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J. C. Mahan Motor Co. v. Lyle, 67 S.W.2d 745, 167 Tenn. 193, 3 Beeler 193, 1933 Tenn. LEXIS 25 (Tenn. 1934).

Opinion

Mr. Justice Chambliss

delivered the opinion of the Court.

A contract was awarded Lyle by the city of Knoxville, on July 21, 1932, to furnish all labor and materials and paint a school building, under which Lyle was to be paid for the work $1,396. The contractor was required, not only to do the work properly, but to save the city harmless from the results of any negligence of the contractor, his agents or employees, and this specific provision was incorporated in the contract:

“All bills for labor, material and supplies shall be promptly paid by the contractor, and in event of failure so to do, the City may, at its election, withhold the re-tainage, or any estimate or part thereof, and apply same on such bills.”

Contemporaneously with the execution of this contract, Lyle executed a bond, with National Surety Company, as surety, for the faithful performance thereof, expressly in- *195 eluding the obligation of the contractor to “promptly pay for all labor and material used in the work.” As a part of his application for the surety bond, he assigned to the surety all the moneys to become due to him as the work progressed or was completed.

August 8th, pending the performance of the work, and the day before he began it, Mahan Motor Company, who had obtained a decree for $500' against Lyle in this cause, on a claim independent of it, had a garnishment served on the city. It is conceded that at this time no amount was owing by the city to Lyle under the contract, but on the later date of the filing of the answer of the garnishee, August 26th, the work had so far progressed that there had been earned under the contract the sum of $500, and the answer of the garnishee so showed. It was also shown by the answer that J. M. Dunn & Son had served notice on the city (the date of this notice, as otherwise appears, being August 18th), of a claim for labor and materials furnished by them on said work in the sum of $508.03, and asserting a lien therefor; and the city submitted to the court the validity of this claim and prayed the instruction of the court “as to whom the amount held by it should be paid. ’ ’

Following a motion by Mahan & Company, for judgment against the garnishee, City of Knoxville, answers and intervening petitions and exhibits thereto were filed by Dunn & Company, the contractor Lyle, and the surety company, together with stipulations, setting forth all the pertinent facts, and the contentions and alleged rights of the parties to the fund in the hands of the city, and, on consideration thereof, the chancellor entered a decree dismissing the garnishment and directing payment of the fund to the intervening petitioners, J. M. Dunn & Son and *196 the surety company. The complainant creditor, J. C. Mahan & Company, appeals and insists that it is entitled to a judgment against the garnishee for this fund under its garnishment process.

It is plausibly argued that the fund involved was impressed with a trust in favor (a) of the laborers and furnishers, whose labor and materials “produced it,” and (b) of the surety, obligated to pay these claims unless otherwise discharged. Many authorities recognize an equitable lien in favor of the claimants, or the surety, or both, and a right of subrogation on the part of the surety to (a) the equitable rights of the furnishers and laborers, even where no lien exists, to the fund produced by them, or (b) to the reserved right of the owner or builder to pay off these claims, as equitable, even though, as in case of a municipality or county, not legal liens. Moreover, since it appears that, in making application for the bond, the contractor assigned to the surety all his rights to the proceeds of his contract, it may plausibly be contended, despite want of notice of the" assignment to the city, required by the Tennessee rule to insure priority against attachment or transfer to innocent purchasers, that the surety- — in view of the holdings hereinafter qiroted of this court that a garnishment claimant occupies no higher ground than does his judgment debtor — acquired rights, not only against the contractor, but also superior to those of the garnishment creditor.

However, we find it unnecessary to adjudicate these questions. The true test of the right of a creditor under a garnishment to a judgment against the garnishment defendant debtor is the existence of an indebtedness owing by the debtor, in this case the city, to the judgment debtor, in this case contractor Lyle. It is ad- *197 mittecl that no such indebtedness existed 'on the 8th of August, when the garnishment was servedno work had then been done on the contract; but, conceding that the test is to be related to the return or answer day, August 26th, and that by that time sufficient work had been performed to justify a payment under the contract of $500', was the chancellor in error in failing to give judgment therefor, under the garnishment against the city, the garnishee?

The amount in controversy being less than $1,000, the answer of the garnishee is not conclusive. Code 1932, section 8962. The proper practice is to summon the garnishee before the court for examination. Wyler, Ackerland & Co. v. Blevins, 113 Tenn., 528, 82 S. W., 829. The chancellor properly considered the facts before him, submitted by the pleadings and exhibits interposed, and the stipulations.

It is well established that the garnishee’s liability must clearly appear, to warrant judgment against him. This liability may not be determined by “surmises and inferences.” Moses v. McMullen, 4 Cold., 244; Moore v. Green, 4 Humph., 299; Pickler v. Rainey, 4 Heisk., 339. It may not be rested on a mere contingency, dependent on the will of the debtor. “Doubt must be resolved in favor of the garnishee, for if it be doubtful whether the garnishee owes the debtor, there can be no judgment.” Mayor, etc., of City of Nashville v. Potomac Ins. Co., 2 Baxt., 303. As said in Van Vleet v. Stratton, 91 Tenn., 474, 19 S. W., 428, 429, “it must clearly and obviously appear that the garnishees were indebted to the debtor,” and by ‘ ‘ debts ’ ’ which may be reached under our statute is not meant “an intangible expectancy, depending on the'will of the debtor.”

*198 In concluding Ms able opinion, in Capital City Bank v. Anderson Transfer Co. et al., 36 S. W., 964, 967 (Court of Tenn. Ch. App.), concurred in by Neil, J., and Wilson, J., and affirmed by tliis court, Barton, J., tbus summarizes tbe rule by saying that it must appear that there is a debt “existing in favor of the debtor, which (the garnishment aside) the debtor could sue the garnishee for and recover.” This is the ultimate test, so recognized in all jurisdictions. In 28 Corpus Juris, p.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tullahoma Industries, LLC v. Navajo Air, LLC
Court of Appeals of Tennessee, 2021
Coke v. Coke
560 S.W.2d 631 (Court of Appeals of Tennessee, 1977)
Sundberg v. Boeing Airplane Co.
328 P.2d 692 (Washington Supreme Court, 1958)
Rucker v. Aymett
219 S.W.2d 181 (Tennessee Supreme Court, 1949)
Rowland v. Quarles
100 S.W.2d 991 (Court of Appeals of Tennessee, 1936)
Grannis-Blair Audit Co. v. Maddux
69 S.W.2d 238 (Tennessee Supreme Court, 1934)

Cite This Page — Counsel Stack

Bluebook (online)
67 S.W.2d 745, 167 Tenn. 193, 3 Beeler 193, 1933 Tenn. LEXIS 25, Counsel Stack Legal Research, https://law.counselstack.com/opinion/j-c-mahan-motor-co-v-lyle-tenn-1934.