J. A. Tobin Construction Co. v. State Highway Commission

630 S.W.2d 258, 1982 Mo. App. LEXIS 2741
CourtMissouri Court of Appeals
DecidedMarch 2, 1982
DocketNo. WD32371
StatusPublished
Cited by1 cases

This text of 630 S.W.2d 258 (J. A. Tobin Construction Co. v. State Highway Commission) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J. A. Tobin Construction Co. v. State Highway Commission, 630 S.W.2d 258, 1982 Mo. App. LEXIS 2741 (Mo. Ct. App. 1982).

Opinion

DIXON, Judge.

Plaintiff Tobin Construction Co. and defendant State Highway Commission appeal from orders of summary judgment in favor of Kansas City Power & Light Company (KCPL) on Count II of Tobin’s petition for breach of contract and on the Commission’s cross-claim for indemnity against KCPL. The trial court designated its order final and appealable on those summary judgments. There remains pending in the trial court Count I of Tobin’s petition directed against the Highway Commission as the sole defendant.

The issue with respect to the summary judgment against Tobin on Count II of its petition against KCPL involves the construction of the contract between KCPL and the Highway Commission. The issue with respect to the propriety of the summary judgment against the Highway Commis[259]*259sion on its cross-claim against KCPL turns on whether there remains a genuine issue of fact.

Tobin entered into a contract with State Highway Commission on July 12, 1968. Under the terms of that contract, Tobin agreed to perform construction work on Highway 435 in Jackson County. At the time the parties entered into the contract, utility facilities owned by KCPL were located within the project right of way in the vicinity of Truman Road and extended for a distance of approximately 5500 feet. This lawsuit stems from KCPL’s failure to remove its facilities from the right-of-way until May 15, 1969, one year beyond the date Tobin had anticipated completing the project.

The contract between Tobin and the Highway Commission included special provision “R” concerning the removal of the utility facilities:

SPECIAL PROVISIONS
R. WORK RESTRICTION (KANSAS CITY POWER & LIGHT EASEMENT)
The Contractor is advised that the Commission and the Kansas City Power & Light Company have an agreement executed November 7, 1966, for the relocation of the utility facilities which are on the right of way .... The Kansas City Power & Light Company has taken bids for the necessary relocation work and has advised the Commission that such work would begin about May 1,1968, and would be completed by October 1, 1968, and the company has been advised that this representation will appear in this contract. The Commission presently holds the necessary property rights under the overhead lines mentioned except for right of way tract No. 230, which is traversed by Skiles Avenue, where the fee ownership was in the Kansas City Power & Light Company subject to the agreement mentioned above. Skiles Avenue, being open, will permit the Contractor to traverse the right of way in this area until it is completely freed of the Kansas City Power & Light Company’s facilities. The bidder will be furnished, upon request, with the most recent information with respect to the progress of this relocation and is advised that the Commission has directed that said relocation be completed by October 1, 1968.
Until such time as the right of way is completely freed of the existing facilities, the Contractor will be required to conduct the work withing [s/e] the above defined limits in the manner necessary to insure that any facilities remaining in place at any time are properly protected from damage.
No additional compensation will be allowed for any delay, inconvenience, or added expense to the Contractor resulting from any restriction of operations which may be necessary to protect utility facilities prior to their removal from the right of way.

Tobin, in Count I, pled reliance on that provision in preparing its bid and alleged that the Commission thereby received a lower bid than it would have without the provision. Tobin further alleged that the Commission issued a “Notice to Proceed” [with construction] on August 12, 1968, requiring Tobin to complete its work within 260 working days and- Tobin was thereby subjected to the imposition of liquidated damages for its failure to complete the project within that time period.

The Commission asserted that Special Provision “R” did not give Tobin the right to assume the facilities would be removed by October 1, 1968. The provision was intended to notify plaintiff that until the facilities were removed, “plaintiff would be required to conduct the work within the area involved in a manner to insure that any remaining facilities in place would be properly protected from damage, and that no additional compensation would be allowed to plaintiff for any delays, inconvenience, or added expense” due to the presence of the facilities. The Commission admitted that Tobin was subjected to the imposition of liquidated damages, but asserted that working days were not counted against Tobin “during the time that utility facilities prohibited work by plaintiff.” The Com[260]*260mission further alleged that “plaintiff did not properly and satisfactorily coordinate the various stages of the work under the contract which could have and should have been performed prior to the relocation of the utility facilities and, therefore, plaintiff’s own operations delayed the final completion of the project.”

The Commission does not dispute that KCPL failed to remove its facilities and Tobin was delayed in gaining unrestricted access to the worksite. The Commission refers to provision 8.5.4 which was incorporated in the contract between Tobin and the Commission in denying liability. It is in relevant part as follows:

The Commission will not be responsible for any delay or inconvenience to the contractor resulting from the contractor’s required cooperation and the coordination of his work with the work of owners of utility facilities or other properties; nor for any inconvenience, delay or added expense to the contractor in working around utility facilities located on right-of-way; or for delay or added expense to the contractor resulting from the failure of the utility owners to remove or relocate utility facilities so that the contractor’s work may proceed on schedule. When the failure of the owners of utility facilities to cooperate and coordinate their work with that of the contractor results in actual delay to the contractor in the over-all completion of his work, such delay will be considered in the count of working days or date specified for completion, provided the contractor notifies the engineer in writing of the delay at the time it occurs, (emphasis supplied).

It is the Commission’s position in the pleadings that the situation at the worksite is specifically provided for by that provision.

Tobin denied that it is barred from recovery because of provision 8.5.4.

In Count II of its petition, Tobin reiterated the essential allegations of Count I. To-bin also asserted it was a third party beneficiary of a contract between the Commission and KCPL regarding the relocation and removal of the utility facilities. Tobin pled the existence of a contract between the Commission and KCPL, executed on July 1, 1966 in which KCPL agreed to remove its utility facilities from the project’s right of way. Under the terms of that agreement, according to Tobin, the Commission gave KCPL formal notice on November 14, 1966. KCPL agreed to begin the removal of its facilities about May 1, 1968 and to complete the removal by October 1, 1968. Tobin further alleged that KCPL was advised that the Commission would warrant to Tobin that the utility facilities would be removed from the right of way by October 1, 1968.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

J.A. Tobin Construction Co. v. State Highway Commission of Missouri
680 S.W.2d 183 (Missouri Court of Appeals, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
630 S.W.2d 258, 1982 Mo. App. LEXIS 2741, Counsel Stack Legal Research, https://law.counselstack.com/opinion/j-a-tobin-construction-co-v-state-highway-commission-moctapp-1982.