J. A. Tobin Construction Co. v. Kemp

718 P.2d 302, 239 Kan. 240, 1986 Kan. LEXIS 310
CourtSupreme Court of Kansas
DecidedMay 2, 1986
Docket58,497
StatusPublished
Cited by1 cases

This text of 718 P.2d 302 (J. A. Tobin Construction Co. v. Kemp) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J. A. Tobin Construction Co. v. Kemp, 718 P.2d 302, 239 Kan. 240, 1986 Kan. LEXIS 310 (kan 1986).

Opinion

The opinion of the court was delivered by

McFarland, J.:

This is a dispute between plaintiff J. A. Tobin Construction Co. and defendant Secretary of Transportation concerning which should bear the cost of corrective work on a defective concrete culvert.

Plaintiff was the general contractor on a highway construction project. As a part of its performance under the contract, plaintiff (through a subcontractor) constructed a concrete box culvert. The contract required that, prior to the pouring of the concrete, a Kansas Department of Transportation (KDOT) inspector was to inspect the work. One of the items to be inspected was the placement of the reinforcing steel (rebar). This inspection occurred in October of 1982 and was accomplished by two inspectors who were also present during the subsequent pouring of the concrete. Neither inspector noticed that the rebar had been *241 improperly placed. A year later, and prior to final acceptance of the project, a KDOT inspector observed cracks in the top concrete mat. An investigation revealed the cause was the improperly placed rebar. The cost of the corrective work was $21,501.00. Had the improper placement of the rebar been discovered prior to the pouring of the concrete, the corrective work would have cost $1,000.00. Plaintiff sought a KDOT change order before proceeding. Plaintiff s position (then and now) was that it was the fault of the inspectors that the error had not been discovered and hence it should only be held responsible for $1,000 of the cost. KDOT declined to issue a change order on the basis the work had not been formally accepted at the time of the discovery of the defect and the correction was, therefore, the contractor’s responsibility. Plaintiff exhausted its administrative remedies. Plaintiff did the corrective work and seeks, in this action, to recover $20,501.00 of the cost thereof. The district court entered summary judgment, on stipulated facts, in favor of KDOT and plaintiff appeals therefrom.

Pertinent portions of the contract and specifications are set forth as follows:

“104.01 INTENT OF CONTRACT — The intent of the Contract is to provide for the construction and completion in every detail of the work described. The Contractor shall furnish all labor, materials, equipment, tools, transportation and supplies required to complete the work in accordance with the plans, specifications and terms of the Contract.”
“105.11 DUTIES OF THE INSPECTOR — Inspectors employed by the Secretary shall be authorized to inspect all work done and materials furnished. Such inspection may extend to all or any part of the work and to the preparation, fabrication or manufacture of the materials to be used. The Inspector is not authorized to alter or waive the provisions of these specifications or the contract. The Inspector is not authorized to issue instructions contrary to the plans and specifications, or to act as foreman for the Contractor, however, he shall have the authority to reject work or materials until any questions at issue can be referred to and decided by the Engineer.” (Emphasis supplied.)
“105.12 INSPECTION OF WORK — All materials and each part of detail of the work shall be subject to inspection by the inspector and the Engineer. The Engineer shall be allowed access to all parts of the work and shall be furnished with such information and assistance by tire Contractor as is required to make a complete and detailed inspection.
“If the Engineer requests it, the Contractor, at any time before acceptance of the work, shall remove or uncover such portions of the finished work as may be directed. After examination, the Contractor shall restore said portions of the work to the standard required by the specifications. Should the work thus exposed or examined prove acceptable, the uncovering, or removing, and the replacing of *242 the covering or making good of the parts removed shall be paid for as extra work; but should the work so exposed or examined prove unacceptable, the uncovering, or removing, and the replacing of the covering or making good of the parts removed shall be at the Contractor’s expense.
“Any work done or materials used without supervision or inspection by an authorized Secretary’s representative may be ordered removed and replaced at the Contractor’s expense unless the Secretary’s representative failed to inspect after having been given reasonable notice in writing that the work was to be performed.”
“105.13 REMOVAL OF UNACCEPTABLE AND UNAUTHORIZED WORK — All work which does not conform to the requirements of the Contract shall be considered unacceptable, unless otherwise determined acceptable under the provisions in Subsection 105.03.
Unacceptable work, whether the result of poor workmanship, use of defective materials, damage through carelessness or any other cause, found to exist prior to the final acceptance of the work, shall be removed immediately and replaced in an acceptable manner. This clause shall have full effect regardless of the fact that the defective work may have been done or the defective materials used with the full knowledge of the Inspector. The fact that the Inspector in charge may have previously overlooked such defective work shall not constitute a,n acceptance of any part of it.” (Emphasis supplied.)
“105.17 ACCEPTANCE — (a). Partial Acceptance. If at any time during the prosecution of the project the Contractor substantially completes a unit or portion of the project, such as a structure, an interchange, or a section of road or pavement, he may request the Engineer to make final inspection of that unit. If the Engineer finds upon inspection that the unit has been substantially completed in compliance with the Contract he may accept that unit by notifying the Contractor in writing that the work is acceptable and the Contractor may be relieved of further responsibility for that unit specified by the .partial acceptance. Such partial acceptance shall in no way void or alter any of the terms of the Contract.”
“704.03 — CONSTRUCTION REQUIREMENTS — . ....
“(c) Placing, Supporting, and Fastening. All reinforcing steel shall be accurately placed and during the placing of concrete, firmly held by approved supports in the position shown on the Plans. Reinforcing bars shall be securely fastened together. Reinforcement placed in any member shall be inspected and approved before any concrete is placed.”
“107.16 CONTRACTOR’S RESPONSIBILITY FOR WORK — Until final written acceptance of the project work by the Engineer, the Contractor shall have the charge and care thereof and shall take every precaution against damage or loss to any part of the project work. The Contractor shall assume all risks of loss and damage to any portion of the project work occasioned by any cause which is within the control of the Contractor and of losses and damages resulting from the following occurrences: fire, lightning, windstorm, hail, vandalism, malicious mischief, falling objects, explosion, flood, freezing and thawing and faulty workmanship.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jarvis v. Jarvis
824 P.2d 213 (Court of Appeals of Kansas, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
718 P.2d 302, 239 Kan. 240, 1986 Kan. LEXIS 310, Counsel Stack Legal Research, https://law.counselstack.com/opinion/j-a-tobin-construction-co-v-kemp-kan-1986.