J. A. Laporte Corp. v. Pennsylvania-Dixie Cement Corp.

165 A. 195, 164 Md. 642, 108 A.L.R. 1474, 1933 Md. LEXIS 43
CourtCourt of Appeals of Maryland
DecidedMarch 21, 1933
Docket[No. 24, January Term, 1933.]
StatusPublished
Cited by28 cases

This text of 165 A. 195 (J. A. Laporte Corp. v. Pennsylvania-Dixie Cement Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J. A. Laporte Corp. v. Pennsylvania-Dixie Cement Corp., 165 A. 195, 164 Md. 642, 108 A.L.R. 1474, 1933 Md. LEXIS 43 (Md. 1933).

Opinion

*644 Bond, O. J.,

delivered the opinion of the Oonrt.

A buyer of cement from a manufacturer repudiated its contract before any of tbe cement had been delivered or called for, and tbe seller, treating tbe whole contract as broken, recovered judgment for damages from tbe breach measured by tbe difference between tbe cost of production and tbe contract price, in so far as it was found feasible to estimate damages; and on tbe buyer’s appeal tbe question chiefly argued is whether this was tbe correct measure of damages under tbe facts shown.

The Laporte Corporation, having a contract for tbe construction of a dam on Gunpowder River and Pretty-Boy Creek in Baltimore County, to impound water for part of tbe water supply of Baltimore City, entered into a written contract on March 24th, 1931, with tbe Pennsylvania-Dixie Corporation, a manufacturer of cement, for all tbe Portland cement required' for tbe work, estimated at 200,000 barrels, to be delivered at Parkton, Maryland, prior to December 31st, 1931. Tbe price stated in tbe contract was $2.25 a barrel, in cloth sacks; and it was stipulated that tbe seller should reduce tbe price to meet any subsequent reductions by it in market price. Testimony on behalf of both parties, however, established tbe fact that tbe price actually agreed upon was less than $2.25 a barrel; that, in order to offset a disadvantage of longer transportation for deliveries from this seller than would be necessary for a competitor nearer tbe work, fifteen cents a barrel should be deducted from that price. 'Whether tbe agreement went further, and required that tbe same deduction should be made from any subsequently reduced market price, was a question in dispute. Tbe agreement-on tbe actual price was not reduced to writing.

Tbe seller is a large manufacturer and seller of cement, having in all, about tbe country, eight factories, with a total production capacity of 12,200,000 barrels a year; and its nearest factories, numbered four and six, from which cement for this contract would have been shipped, bad a total capacity of 3,700,000 barrels. Tbe total production capacity of tbe seller, according to its testimony, was of a larger amount *645 than conld be marketed at any price, however low, and the amount that could be marketed depended largely on the extent of the success or failure of efforts of its salesmen in competition with salesmen of other sellers. Under the conditions existing in 1931, the plants worked to only forty-eight per cent, of their full capacity. 3 On March 31st, 1931, a week after the making of the present contract, the seller had on hand, at its plants numbered four and six, 577,000 barrels of cement made up, and had commitments or orders amounting to 1,037,000 barrels excluding this order. On December 31st, 1931, the date specified for concluding deliveries on the contract, it had on hand 404,000 barrels, and commitments for 1,190,000 barrels. During the year 1931 its total production at those two plants amounted to 2,613,350 barrels, and its total shipments, filling orders, amounted to 2,595,000 barrels. Erom a third plant in the same nearby region, and from which shipments on this contract might have been made, it shipped on other orders 75,000 barrels, but produced none during that year.

Within a short time after entering into the Contract, the buyer gave notice that it would not consider it binding, and made a contract with another seller and manufacturer; and it is not denied that in doing so it was guilty of a breach of its contract with the appellee.

The buyer raises on appeal a question whether the contract, lacking as it does a writing of the essential element of the price actually agreed upon, is unenforceable under the statute of frauds, as embodied in the Code, art. 83, sec. 25. Browne, Statute of Frauds (5th Ed.), sec. 376; Woods, Statute of Frauds, sec. 351; 1 Williston, Sales, sec. 103; Goodman v. Griffiths, 1 Hurl. & N. 574; 1 Uniform Laws Annot. 64. This is a question which does not appear to have been raised below, and for that reason seems foreclosed as possible ground of reversal on appeal. Code, art. 5, sec. 10. There was testimony that a writing on the actual price was lacking, but in no place does it appear to have been suggested that this affected the enforceability of the contract. The defendant prayed generally that a verdict be rendered in its favor be *646 cause there was no evidence legally sufficient to entitle the plaintiff to recover, and a ruling on the question could, perhaps, have been made on that prayer, but it has long since been decided that a prayer sufficiently general in terms to afford ground for ruling on a defense raised does not meet the requirement that the defense must plainly appear to have been raised. Tyson v. Shueey, 5 Md. 540, 552. A reading of the record indicates rather clearly that it was not raised in this instance.

The rules for measuring damages from a buyer’s anticipatory breach of a contract of sale embodied in the Sales Act, Code, art. 83, sec. 85, are broadly stated, for they were intended to leave latitude for adaptation to the circumstances of particular cases in pursuing the effort to restore to the seller all that he might lose by loss of the sale. See Amer. Law Inst., Restatement Contracts, sec. 329, Comment; Dimmick v. Hendley, 117 Md. 464, 470, 84 A. 171; Kahn v. Carl Schoen Silk Corp., 147 Md. 516, 128 A. 359; Maryland Fert. & Mfg. Co. v. Lorentz, 44 Md. 218, 235; Ontario Co. v. Hamilton Co., 27 Ont. App. 346, 351. No one measure is fixed upon as the ordinary or preferred measure. The comprehensive principle is stated in subsection 2: “The measure of damages is the estimated loss directly and naturally resulting, in the ordinary course of events, from the buyer’s breach of contract”; and the ensuing subsections, providing for more particular applications of that principle, are broad and elastic in form. The precedents in decided cases which have applied one measure and another to similar contracts are in great abundance; and not in agreement. Opposite conclusions have been reached on hardly distinguishable facts. See review in 44 A. L. R. 258.

The question which finally tests the appropriateness of a given measure in a case of a breach of contract of sale of goods by a manufacturer seems to be not merely whether the contract in a particular case was one for manufacture as well as for sale; the inquiry goes closer to the effect of breach on the seller, and to the position in which it has left him. If he should be left with goods on hand for the sale, and so with *647 their market value iu his possession and available on a market, his loss would be only the further amount of the difference between the market value and the contract price; and that difference would be the appropriate measure of damages.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lovell Land, Inc. v. State Highway Administration
952 A.2d 414 (Court of Special Appeals of Maryland, 2008)
Bennett v. Wright
892 A.2d 1164 (Court of Special Appeals of Maryland, 2006)
Dove v. White
126 A.2d 835 (Court of Appeals of Maryland, 2001)
Schmitt v. State
779 A.2d 1004 (Court of Special Appeals of Maryland, 2001)
Todd v. Ferrell
130 A.2d 581 (Court of Appeals of Maryland, 1988)
Cavalier Mobile Homes, Inc. v. Liberty Homes, Inc.
454 A.2d 367 (Court of Special Appeals of Maryland, 1983)
Reemsnyder v. State
416 A.2d 767 (Court of Special Appeals of Maryland, 1980)
Lewis v. Hughes
346 A.2d 231 (Court of Appeals of Maryland, 1975)
In Re Sales & Use Tax Determination by St. Tax Com'r
225 N.W.2d 571 (North Dakota Supreme Court, 1974)
Ace Mud Service, Inc. v. State Tax Commissioner
225 N.W.2d 571 (North Dakota Supreme Court, 1974)
Robinson v. State
302 A.2d 659 (Court of Special Appeals of Maryland, 1973)
MacKe Co. v. Pizza of Gaithersburg, Inc.
270 A.2d 645 (Court of Appeals of Maryland, 1970)
Friedman v. Clark
248 A.2d 867 (Court of Appeals of Maryland, 1969)
Stuart Kitchens, Inc. v. Stevens
234 A.2d 749 (Court of Appeals of Maryland, 1967)
Smith v. Jones
203 A.2d 865 (Court of Appeals of Maryland, 1964)
Fairchild Stratos Corporation v. Lear Siegler, Inc.
337 F.2d 785 (Fourth Circuit, 1964)
Fairchild Stratos Corp. v. Siegler Corp.
225 F. Supp. 135 (D. Maryland, 1963)
Coos Lumber Co. v. Builders Lumber & Supply Co.
188 A.2d 330 (Supreme Court of New Hampshire, 1963)
M & R Contractors & Builders, Inc. v. Michael
138 A.2d 350 (Court of Appeals of Maryland, 1958)
Rosenberg v. Rolling Inn, Inc.
129 A.2d 924 (Court of Appeals of Maryland, 1957)

Cite This Page — Counsel Stack

Bluebook (online)
165 A. 195, 164 Md. 642, 108 A.L.R. 1474, 1933 Md. LEXIS 43, Counsel Stack Legal Research, https://law.counselstack.com/opinion/j-a-laporte-corp-v-pennsylvania-dixie-cement-corp-md-1933.