Ivy H. Smith Co. v. Warffemius

93 A.2d 764, 201 Md. 367
CourtCourt of Appeals of Maryland
DecidedOctober 1, 1965
Docket[No. 65, October Term, 1952.]
StatusPublished
Cited by8 cases

This text of 93 A.2d 764 (Ivy H. Smith Co. v. Warffemius) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ivy H. Smith Co. v. Warffemius, 93 A.2d 764, 201 Md. 367 (Md. 1965).

Opinion

Hammond, J.,

delivered the opinion of the Court.

This appeal involves the liability for trespass of the Ivy H. Smith Company, Inc., the appellant, a contractor which under written contract undertook to prepare a right of way and erect a high tension line for an electrical cooperative, and, in the course of its work, entered on the lana of the appellees, and cleared a swath 100 feet wide by 300 feet long of trees and shrubs.

The Southern Maryland Electric Co-operative,, Inc., having determined to construct a high voltage transmission line in Southern Maryland, negotiated with property owners along the proposed right of way and secured easements for the construction and maintenance of the line. On August 30, 1950, it obtained a written authorization, signed, sealed, and acknowledged by the appellees, Theodore Warffemius and Eleanor A. Warffemius, his wife,, granting unto the Co-operative, “and to its sue *370 cessors or assigns”, the right to enter upon their land described in the writing, and to “construct, operate and maintain on the above described lands an electric transmission line of (sic.) system in the pole locations as staked by the Cooperative’s Engineer, and to cut and trim trees and shrubbery to the extent necessary to keep them clear of said electric line or system at least 50 feet on each side.” The Co-operative agreed to pay fifteen dollars for privileges granted and for crossing woodland located within the described boundaries.

On September 5, 1950, the Co-operative entered into a contract with the appellant, under the terms of which the Smith company, referred to as the “Contractor”, was to clear the easement right of way and to build the transmission line. The Contractor agreed to clear and build “in strict accordance with the plans, specifications and construction drawings therefor, attached hereto and made a part hereof”.

Another provision of the contract was that:

“The contractor shall not proceed with the cutting of trees or clearing of right-of-way without written notification from the engineer that the proper authorization has been received from the owner of the property, and the contractor shall promptly notify the engineer of whenever any landowner objects to the trimming or felling of any trees or the performance of any work on his land in connection with the project and shall obtain the consent in writing of the engineer before proceeding in any such case”.

The Co-operative was obliged to furnish blueprints of the right of way and to stake off the line, locating the stakes in the center so that the line would be cleared 50 feet on each side, making a 100 foot right of way. The stakes were numbered and the corresponding numbers appeared on the blueprints. The staking and preparation of the blueprints was done for the Co-operative by the B. O. Vannort Engineers, Inc., generally referred to in the papers and by the parties as the “Engineer”, *371 which generally had charge of the engineering phases of the work. Before Mr. and Mrs. Warffemius signed the easement, they had caused the proposed line to be moved away from their house and down near the corner of their property. The Engineer surveyed and staked this agreed line and prepared the blue prints accordingly. However, after this had been done, and because one of a number of co-owners of the tract of land adjoining that of the Warffemiuses, either could not be found or would not sign an easement agreement, the Co-operative decided not to wait to obtain this signature, but to prepare a new line. The new line ran to the East of and was entirely off the Warffemius property. The Engineer left in the line of stakes over the Southwest corner of the Warffemius property — the line agreed to and authorized as the easement line.

The new line was not desired by the Co-operative and the change cost thousands of dollars. At any time before the poles were actually in the air, the Co-operative would have reverted by preference to the original line over the Warffemius property and the adjacent properties if the necessary owners’ signatures could have been had.

The Contractor began work shortly after the signing of the contract and, using several crews, had cleared from the Hughesville end of the line to the Warffemius property by November 26, 1950. On that day and the next, it cleared a swath 100 feet by 300 feet on the Warffemius property along the easement line. It is conceded that all the cutting was done within the area covered and authorized by the easement agreement. On the first day of the cutting, Mrs. Warffemius asked the foreman of the crew if there was not a mistake, but made no objection to the cutting, nor any effort to stop it. Indeed, she, in substance, repeated that immortal plea “Woodman, spare that tree!”, and asked that an oak not be cut. This wish was respected. She called her husband to ask what, if anything, could be done, and was told by him, “Nothing, I think.” Mr. Warffemius *372 had conversations with the foreman of the crew as to the size of the logs which the felled trees were to be cut. The agreement with the Co-operative had provided that the trees were to be cut into logs of specified size and left on the property, and this was done in accordance with that agreement and Mr. Warffemius’ wishes.

On the second day of the cutting, the crew, as they put it, ran out of stakes, and was put on notice that something was wrong. This was confirmed at lunch, when the foreman was told by a neighboring landowner that the line had been relocated. It was about this time also that Mr. Warffemius ordered the men to stop cutting. Mr. Whitley, Superintendent of the Smith Company, in charge of the work, and Mr. Taylor, the foreman, then went to Mr. Shull, Resident Engineer of the Vannort Company, and were given new blueprints covering the relocated line. It was the unvarying practice of the Contractor to cut from the stakes, after verifying the numbers with those corresponding on the blueprints. If land was not to be cut over, the blueprints were marked with a red pencil as to the prohibited areas. There was no such warning as to the stakes and stations on the Warffemius property.

In May, 1951, the appellees filed suit against the Smith Company for trespass. On motion of the defendant, the Co-operative was brought in as a third party-defendant, and a complaint filed against it by the Smith Company. At the close of the trial, the court granted the Co-operative’s motion for a directed verdict as to it. The court then instructed the jury “as a matter of law that from all the evidence in this case the plaintiffs are entitled to recover a verdict at your hands”. The only question left to the jury was that of damages. Its attention was directed to Section 365 of Article 66C of the 1951 Code. This provides that persons “who shall wilfully, negligently, recklessly, wrongfully * * * and without the permission or authority of the owners * * * cut, burn or otherwise injure and destroy * * * any merchantable trees or timber”, shall be liable to the *373 persons injured or aggrieved, in an amount double the value of the trees. On the testimony of Mr. Warffemius that the merchantable trees cut had a value to him of fifteen hundred dollars, and the transplantable holly and other decorative shrubs or trees, a value to him

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vestal v. Oden
500 So. 2d 954 (Mississippi Supreme Court, 1986)
Maryland Commission on Human Relations v. Malakoff
329 A.2d 8 (Court of Appeals of Maryland, 1974)
Mayfair Fabrics v. HENLEY
244 A.2d 344 (New Jersey Superior Court App Division, 1968)
Wood v. Mississippi Power Co.
146 So. 2d 546 (Mississippi Supreme Court, 1962)
Krawill MacHinery Corp. v. Robert C. Herd & Co.
145 F. Supp. 554 (D. Maryland, 1956)

Cite This Page — Counsel Stack

Bluebook (online)
93 A.2d 764, 201 Md. 367, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ivy-h-smith-co-v-warffemius-md-1965.