Islander East Pipeline Co., LLC v. Blumenthal

478 F. Supp. 2d 289, 167 Oil & Gas Rep. 253, 2007 U.S. Dist. LEXIS 20737, 2007 WL 861187
CourtDistrict Court, D. Connecticut
DecidedMarch 22, 2007
Docket06cv725 (JBA)
StatusPublished
Cited by3 cases

This text of 478 F. Supp. 2d 289 (Islander East Pipeline Co., LLC v. Blumenthal) is published on Counsel Stack Legal Research, covering District Court, D. Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Islander East Pipeline Co., LLC v. Blumenthal, 478 F. Supp. 2d 289, 167 Oil & Gas Rep. 253, 2007 U.S. Dist. LEXIS 20737, 2007 WL 861187 (D. Conn. 2007).

Opinion

RULING ON PLAINTIFF’S MOTION FOR SUMMARY JUDGMENT [DOC. #33]

ARTERTON, District Judge.

Plaintiff Islander East Pipeline Company, L.L.C. (“Islander East”) seeks declaratory and injunctive relief from the defendants’ requirement that it obtain a state permit under Connecticut’s Structures, Dredging and Fill Act (“SDF”), Conn. Gen.Stat. § 22a-359 et seq., in order to lawfully carry out its activities related to construction of an interstate natural gas pipeline connecting New England and Eastern Long Island, including pre-con-struction core sampling. The action is brought against defendants Connecticut Attorney General Richard Blumenthal (“CT AG”), the State of Connecticut, the Connecticut Department of Environmental Protection (“CT DEP”) and its Commissioner Gina McCarthy, and the Town of Branford and its First Selectwoman Cheryl Morris, and is in essence the mirror image of litigation commenced by defen *291 dant McCarthy to enjoin plaintiff from such construction until it obtains a state SDF permit. See McCarthy v. Islander East, No. 06cv756 (JBA) (D.Conn.). Plaintiff now moves for summary judgment, principally on the grounds that the Natural Gas Act (“NGA”), 15 U.S.C. § 717 et seq., and orders, of the Federal Energy Regulatory Commission (“FERC”) preempt the CT DEP’s authority to require plaintiff to submit to SDF permitting. Plaintiffs Motion for Summary Judgment is granted, as the Court finds that requiring plaintiff to obtain a state SDF permit for the pre-construction, construction, and operation of its federally authorized gas pipeline conflicts with FERC’s orders certifying this project, and the permit requirement is therefore preempted by the federal NGA.

I. Factual Background

Plaintiff Islander East, a Delaware natural-gas company with its principal place of business in Houston, Texas, is authorized by the FERC to construct and operate a gas pipeline project running from Connecticut to New York to supply natural gas to customers on Long Island. In October 2001, plaintiff gave notice to CT DEP of its “core sampling” program in Long Island Sound needed to prepare construction plans for the project. Thereafter, the CT DEP wrote to the CT AG to advise that although “core sampling can be considered ‘work incidental thereto’ for purposes of the permitting authority of [the SDF statute],” 1 it decided “to not require an application from Islander East for this sampling work” based on the “determin[ation] that any sedimentation ... would be short-term in nature and would be expected to minimally impact only those shellfish in the immediate vicinity of the core.” (Nov. 5, 2001 CT DEP letter, Mulherr Aff. [Doc. # 33], Ex. C.) Plaintiffs sampling program commenced in October 2001 but was interrupted by the arrest of an Islander East employee on charges of criminal trespass by the Branford police; the charges were dismissed in November 2002. (Apr. 27, 2006 PL letter, Mulherr Aff., Ex. D.)

Although the CT DEP had not required plaintiff to obtain a SDF permit, plaintiff submitted an application to the agency on February 13, 2002 and . amended it in March 2003. (Jacobson Aff. [Doc. # 38-4] ¶¶ 3, 4.) In April 2003, the CT DEP informed plaintiff that the application processing fee would be $1.4 million. (Second Mulherr Aff. [Doc. # 40-2] ¶ 3.) Plaintiff disputed the amount of the fee, estimating that it should be only $41,865. (Apr. 28, 2003 PI. letter, Second Mulherr Aff., Ex. B.) The fee issue apparently was left unresolved, and the application process ceased. (Second Mulherr Aff. ¶ 6.)

Preliminary sampling was revived in 2006, when plaintiff advised the CT DEP in an April 27 letter that it was “now resuming the core sampling program, and offshore survey activities, and intends to take samples.” (Id.) On May 9, 2006, plaintiff updated the agency on its “intention to resume the offshore core sampling no sooner than the week of May 22, 2006. The [CT DEP] has already determined *292 that (1) the core sampling will have minimal impact, and (2) no permit is required for this activity under [the SDF statute].” (May 9, 2006 PL letter, Mulherr Aff., Ex. E.) Plaintiff stated that “[t]he impact of the core sampling that Islander East intends to resume will not materially differ from that previously reviewed by the Connecticut DEP in 2001.” (Id.) Two days later, the CT DEP wrote plaintiff of its determination that plaintiffs “currently proposed activities” were “quite different” from those proposed in October 2001, and that the agency therefore “determined that the activities which [plaintiff] [had] outlined in the April 27, 2006 and May 9, 2006 letters are regulated activities which require authorization in the form of a[SDF] permit.” (CT DEP May 11, 2006 letter, Mulherr Aff., Ex. F.)

CT DEP Commissioner Gina McCarthy brought a state court injunctive action dated May 15, 2006, seeking to enjoin Islander East from “conducting any drill, core sampling, invasive offshore survey and related activities in the waters of Long Island Sound ... along or in the vicinity of the route of the proposed Islander East pipeline,” which was removed to federal court. (See Compl. [Doc. # 1-3], McCarthy.) McCarthy’s application for a temporary injunction to enjoin plaintiff from undertaking its scheduled surveys without first obtaining a SDF permit was heard and denied on May 19, 2006. (See [Doc. # 20], McCarthy.) 2

FERC Proceedings

On December 21, 2001, after a hearing on non-environmental dimensions of the project, FERC issued a Preliminary Determination which “providefd] certainty concerning the economic aspects of Islander East’s ... proposals” and certified the project pending environmental review. Islander East Pipeline Co., 97 F.E.R.C. ¶ 61,363 (2001). On September 19, 2002, after environmental review was completed, FERC issued its “final decision on Islander East’s ... request for authorizations,” wherein FERC “determine[d] that the proposed facilities and services are required by public convenience and necessity.” Islander East Pipeline Co., 100 F.E.R.C. ¶ 61,276 (2002) (“Order”). The FERC Order was issued with reference to the Final Environmental Impact Statement (“FEIS”) prepared for the project pursuant to the National Environmental Policy Act (“NEPA”), 42 U.S.C. §§ 4432 et seq., 18 C.F.R. § 380.6. In the Order, FERC “note[s] that the NGA and the regulations promulgated by the Commission under that statute generally preempt state and local law,” but “encourages cooperation between interstate pipelines and local authorities. However, this does not mean that state and local agencies, through application of state or local laws, may prohibit or unreasonably delay the construction or operation of facilities approved by [FERC].” See 102 F.E.R.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Millennium Pipeline Co. v. Seggos
288 F. Supp. 3d 530 (N.D. New York, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
478 F. Supp. 2d 289, 167 Oil & Gas Rep. 253, 2007 U.S. Dist. LEXIS 20737, 2007 WL 861187, Counsel Stack Legal Research, https://law.counselstack.com/opinion/islander-east-pipeline-co-llc-v-blumenthal-ctd-2007.