Irvin Water District No. 6 v. Jackson Partnership

109 Wash. App. 113
CourtCourt of Appeals of Washington
DecidedNovember 15, 2001
DocketNo. 19244-0-III
StatusPublished
Cited by10 cases

This text of 109 Wash. App. 113 (Irvin Water District No. 6 v. Jackson Partnership) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Irvin Water District No. 6 v. Jackson Partnership, 109 Wash. App. 113 (Wash. Ct. App. 2001).

Opinion

Sweeney, J.

— This is a dispute between real estate developers and Irvin Water District No. 6 over connection fees. The District provided the developers with water for fire and construction purposes. Later it substantially increased the connection charges. It did so before the developers actually applied for service and tendered the connection fees. The primary question before us is whether the District was committed to the connection fees in place when [117]*117it first provided water to the developers. We have concluded that the District is not bound under any legal or equitable theory to supply water at the old, lower connection fees and that the appropriate fees were the fees in effect at the time the developers actually formally applied for and tendered the connection fees. We therefore reverse the trial court’s ruling to the contrary. We do, however, remand the case to the trial court for calculation of the appropriate connection fees set out in former RCW 57.08.010(3) (1994).

I. FACTS

A. Parties

Gunning and Lawson Investments (G&L) built an apartment complex. William Lawson and Stephen Schmautz, the Jackson Partnership, built a commercial building. Both projects are within the service boundaries of Irvin Water District No. 6. G&L and Jackson will be collectively referred to as the “Developers.”

B. Water Use for Construction

G&L talked to the District’s General Manager, George Shearer, about water service in January 1994. Mr. Shearer quoted an incorrect connection fee. But he did approve G&L’s proposed utilities plan on February 18, 1994. The utilities plan stated that the District had sufficient water to supply the Developers’ projects.

Sometime during the spring, Betty Skillingstad, the District’s Office Manager, reminded Mr. Lawson of the need to formally apply for water service and pay the connection fees.

Construction on G&L’s apartments began in late March 1994. The District provided water for fire protection and construction purposes at least by the end of April 1994. The Developers had installed several hundred feet of eight-inch water main as part of the project by the end of April. The water line became the District’s property upon completion of the project. At the same approximate time, G&L tapped into the District’s water service at four different locations. [118]*118Two additional taps were made into the new eight-inch main line. The District’s manager approved these connections. Water was not yet, however, available for domestic use because it had not been tested. The Developers used the water for construction and fire control only.

C. Connection Fee Adjustment

The District’s Board of Commissioners met in June 1994, and talked about new growth, its effect, and the need to adjust connection fees to reflect increased costs.

Ms. Skillingstad called Mr. Lawson after the June Board meeting and again reminded him of the need to file an application for service and the need to pay the connection fees. She also reported that the District was considering an increase in connection fees.

On July 12, 1994, the District’s Board adopted a new connection charge of “$1,000 per unit for multi-unit buildings.” Clerk’s Papers at 94. Fees for the apartment project under the new fee schedule rose from $19,000 to $140,000.

The Developers never applied for service or paid the connection fees requested by the District. Both steps are required by District regulations and bylaws to secure service.

The District told the Developers of the increased connection fees. The Developers then tried to tender the fees required under the old schedule. The District rejected the tender.

D. Court Proceedings

The District sued for a judicial declaration that the new connection fees were lawful and that they applied to the Developers.

Following a bench trial, the judge concluded that the new connection fees were properly adopted and lawful. But the judge also concluded that the Developers became “customers” of the District before adoption of the new charge. It therefore permitted the Developers to pay the fees in effect before adoption of the new increased connection fees.

[119]*119The District appeals, arguing that the new connection fee is applicable to the Developers. The Developers cross-appeal, arguing the new fee is really an invalid tax and that it was calculated incorrectly.

II. APPLICATION OF CONNECTION FEE

A. Standard of Review

“The standard of review for a trial court’s findings of fact and conclusions of law is a two-step process. First, we must determine if the trial court’s findings of fact were supported by substantial evidence in the record. If so, we must next decide whether those findings of fact support the trial court’s conclusions of law.” Landmark Dev., Inc. v. City of Roy, 138 Wn.2d 561, 573, 980 P.2d 1234 (1999).

B. Customer

The trial judge conferred the status of “customer” on the Developers and then ascribed legal consequences to that status, tantamount to “vesting.”1 But we find no statute, case, or rule that attaches legal consequences to the status of “customer” in this context.

The questions here are whether these new connection fees apply to the Developers and, of course, if they do, why?

The District argues that the Developers must pay the new connection fees because they neither applied for service nor paid the applicable fees before the Board adopted the new fees. The Developers respond that the new fees do not apply to them for a variety of reasons. First, they were “vested” under the old fees. Next, they had an implied contract with the District for the old fees. Or, finally, the District is either estopped or has waived its right to apply the new fees to them. We consider each of the arguments in order.

[120]*120C. Vesting

The Developers argue that they have a vested right to the connection fees in place on July 11, 1994, and rely on Landmark Development, Inc.2 The District responds that the Developers were not vested and rely on Lincoln Shiloh Associates v. Mukilteo Water District.3 Each party argues that its case is dispositive of the question here.

1. Lincoln Shiloh Associates v. Mukilteo Water District

In Lincoln Shiloh, the developer had planned a 208-unit apartment complex. The development fell within the Mukilteo Water District. Lincoln needed to extend a water main owned by the district in order to obtain service. Lincoln submitted plans for extending the water main in February 1981. The district approved the plans in March. Lincoln Shiloh Assocs. v. Mukilteo Water Dist., 45 Wn. App. 123, 125-26, 724 P.2d 1083, 742 P.2d 177 (1986).

Lincoln began building the water main in May 1981.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City Of Issaquah, V. Westridge-issaquah Ii Lp
500 P.3d 157 (Court of Appeals of Washington, 2021)
Albert And Margaret Figaro v. City Of Bellingham
Court of Appeals of Washington, 2016
Lane v. City of Seattle
164 Wash. 2d 875 (Washington Supreme Court, 2008)
In re Spiegel, Inc.
337 B.R. 821 (S.D. New York, 2006)
Harberd v. City of Kettle Falls
84 P.3d 1241 (Court of Appeals of Washington, 2004)
Sudden Valley Community Ass'n v. Whatcom County Water District No. 10
55 P.3d 653 (Court of Appeals of Washington, 2002)
IRVIN WATER DIST. v. Jackson Partnership
34 P.3d 840 (Court of Appeals of Washington, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
109 Wash. App. 113, Counsel Stack Legal Research, https://law.counselstack.com/opinion/irvin-water-district-no-6-v-jackson-partnership-washctapp-2001.