West Main Associates v. City of Bellevue

720 P.2d 782, 106 Wash. 2d 47
CourtWashington Supreme Court
DecidedSeptember 11, 1986
Docket50913-1, 50914-0
StatusPublished
Cited by95 cases

This text of 720 P.2d 782 (West Main Associates v. City of Bellevue) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
West Main Associates v. City of Bellevue, 720 P.2d 782, 106 Wash. 2d 47 (Wash. 1986).

Opinion

Utter, J.

The City of Bellevue appeals from a trial court's orders granting partial summary judgment in favor of West Main Associates and summary judgment for Belle-vue Downtown Association. The trial court concluded that Bellevue ordinance 3359 unconstitutionally interfered with rights guaranteed by this court's vesting doctrine. We agree with the trial court.

In February 1981, the City of Bellevue enacted a set of ordinances to regulate and encourage downtown growth. That set of ordinances was the product of 6 years of study. Upon enactment of the ordinances, West Main Associates took its first steps toward development of Meydenbauer Place, a 22-story mixed-use retail and residential structure on a 1.1-acre tract in "Old Bellevue" at the southeastern edge of Bellevue's central business district. In August 1983, West Main Associates submitted its application for administrative design review of Meydenbauer Place. On October 11, 1983, it issued a draft environmental impact statement, on which a hearing was held November 10, 1983. West Main Associates continued to revise and refine its design plans.

In March 1984, the Bellevue City Council met in study session to discuss development within the central business district "transition area." The transition area is the portion of the business district immediately bordering the surrounding residential area, and includes the designated site for Meydenbauer Place. The council considered several proposals regarding development in the transition area, including a city-wide ordinance to establish the point at which rights to develop property vest.

West Main Associates completed and submitted revised *49 administrative design review materials on March 30, 1984. A few days later, on April 2, 1984, the City of Bellevue added two sections to its building code by enacting ordinance 3359. The ordinance prohibited the filing of a building permit application for any proposed project in Bellevue until all of the following procedures are complete: (1) administrative design review approval; (2) site plan review approval; (3) administrative conditional use approval; (4) modification of landscaping approval; (5) design review approval by the planning commission; (6) passage by the city council of any necessary ordinance approving a conditional use, shoreline conditional use, planned unit development or planned residential unit development; (7) approval by the board of adjustment of a variance or shoreline variance; and (8) issuance of a shorelines substantial development permit. The ordinance specifically provided that if any appeal were taken with respect to the first four of these approvals no building permit application would be accepted until the appeal was finally resolved. The ordinance also provided that filing of applications for any of these preliminary approvals would not vest rights; development rights would be vested only as of the time a building permit application was filed.

The ordinance established several hurdles for West Main to clear before it could vest its rights by filing for a building permit. West Main's investment on April 2 is not known. However, by July 13, 1984, West Main estimated expenditures of over $500,000 on design phase costs for Meyden-bauer Place.

After enactment of the ordinance, West Main Associates and Bellevue Downtown Association, a nonprofit corporation consisting of residents, business persons, and landowners in downtown Bellevue, filed separate suits against Bellevue. Each party sought, among other things, a declaratory judgment that the ordinance was unconstitutional and unenforceable. West Main also claimed monetary damages on three theories: (1) damages for a "taking" of its property without compensation in violation of the Fifth *50 Amendment; (2) damages as authorized by 42 U.S.C. § 1983 (1983) for the deprivation of constitutional rights by a state official acting under color of state authority; and (3) damages as authorized by RCW 64.40 for the interference with private property rights by a local government acting in knowing violation of constitutional rights.

Bellevue moved for summary judgment on the pleadings. After a hearing the trial court denied the motion, and entered an order granting summary judgment in favor of Bellevue Downtown Association and an order granting partial summary judgment in favor of West Main Associates. The trial court expressly directed entry of the latter judgment as a final judgment. In its letter opinion the court concluded that the ordinance improperly interfered with the vesting doctrine, and suggested that the ordinance violated due process requirements. 1

We agree with the trial court. We have recognized that " [although less than a fee interest, development rights are beyond question a valuable right in property." Louthan v. King Cy., 94 Wn.2d 422, 428, 617 P.2d 977 (1980), relying on Penn Cent. Transp. Co. v. New York, 438 U.S. 104, 57 L. Ed. 2d 631, 98 S. Ct. 2646, reh'g denied, 439 U.S. 883, 58 L. Ed. 2d 198, 99 S. Ct. 226 (1978). See also C. Siemon, W. Larsen & D. Porter, Vested Rights 61-68 (1982). Despite the expanding power over land use exerted by all levels of government, "[t]he basic rule in land use law is still that, absent more, an individual should be able to utilize his own land as he sees fit. U.S. Const. amends. 5, 14." Norco Constr., Inc. v. King Cy., 97 Wn.2d 680, 684, 649 P.2d 103 (1982).

One aspect of this court's protection of these rights is our vested rights doctrine. Under this doctrine, developers who file a timely and complete building permit application *51 obtain a vested right to have their application processed according to the zoning and building ordinances in effect at the time of the application. The Washington doctrine protects developers who file a building permit application that (1) is sufficiently complete, (2) complies with existing zoning ordinances and building codes, and (3) is filed during the effective period of the zoning ordinances under which the developer seeks to develop. See, e.g., Allenbach v. Tuk-wila, 101 Wn.2d 193, 676 P.2d 473 (1984). Once a developer complies with these requirements a city cannot frustrate the development by enacting new zoning regulations.

The purpose of the vesting doctrine is to allow developers to determine, or "fix," the rules that will govern their land development. See Comment, Washington's Zoning Vested Rights Doctrine, 57 Wash. L. Rev. 139, 147-50 (1981). The doctrine is supported by notions of fundamental fairness. As James Madison stressed, citizens should be protected from the "fluctuating policy" of the legislature. The Federalist No. 44, at 301 (J.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Arends v. State
Washington Supreme Court, 2025
Shadow Creek Investments, V. City Of Anacortes
Court of Appeals of Washington, 2024
Seven Hills, LLC v. Chelan County
Washington Supreme Court, 2021
Chong Yim v. City of Seattle
Washington Supreme Court, 2019
Snohomish County v. Pollution Control Hearings Board
386 P.3d 1064 (Washington Supreme Court, 2016)
Snohomish County v. Pollution Control Hearings Board
368 P.3d 194 (Court of Appeals of Washington, 2016)
Potala Village Kirkland, Llc v. City Of Kirkland
Court of Appeals of Washington, 2014
Town of Woodway v. Snohomish County
Washington Supreme Court, 2014
Lauer v. Pierce County
157 Wash. App. 693 (Court of Appeals of Washington, 2010)
Deer Creek Developers, LLC v. Spokane County
236 P.3d 906 (Court of Appeals of Washington, 2010)
GOAT HILL HOMEOWNERS ASS'N, INC. v. King County
686 F. Supp. 2d 1130 (W.D. Washington, 2010)
Abbey Road Group, LLC v. City of Bonney Lake
167 Wash. 2d 242 (Washington Supreme Court, 2009)
Biggers v. City of Bainbridge Island
162 Wash. 2d 683 (Washington Supreme Court, 2007)
Tiffany Family Trust Corp. v. City of Kent
119 P.3d 325 (Washington Supreme Court, 2005)
East County Reclamation Co. v. Bjornsen
105 P.3d 94 (Court of Appeals of Washington, 2005)
WCHS, Inc. v. City of Lynnwood
86 P.3d 1169 (Court of Appeals of Washington, 2004)
EDMONDS SHOPPING CENTER ASS'N v. City of Edmonds
71 P.3d 233 (Court of Appeals of Washington, 2003)
Edmonds Shopping Center Associates v. City of Edmonds
71 P.3d 233 (Court of Appeals of Washington, 2003)
Thornton Creek Legal Defense Fund v. City of Seattle
52 P.3d 522 (Court of Appeals of Washington, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
720 P.2d 782, 106 Wash. 2d 47, Counsel Stack Legal Research, https://law.counselstack.com/opinion/west-main-associates-v-city-of-bellevue-wash-1986.