Iroquois Gas Transmission System, L.P. v. Federal Energy Regulatory Commission

145 F.3d 398, 330 U.S. App. D.C. 271, 28 Envtl. L. Rep. (Envtl. Law Inst.) 21497, 1998 U.S. App. LEXIS 16471, 1998 WL 403645
CourtCourt of Appeals for the D.C. Circuit
DecidedJuly 21, 1998
Docket97-1276 and 97-1533
StatusPublished
Cited by5 cases

This text of 145 F.3d 398 (Iroquois Gas Transmission System, L.P. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Iroquois Gas Transmission System, L.P. v. Federal Energy Regulatory Commission, 145 F.3d 398, 330 U.S. App. D.C. 271, 28 Envtl. L. Rep. (Envtl. Law Inst.) 21497, 1998 U.S. App. LEXIS 16471, 1998 WL 403645 (D.C. Cir. 1998).

Opinions

Opinion for the Court filed by Circuit Judge WILLIAMS.

Concurring opinion filed by Circuit Judge WALD.

WILLIAMS, Circuit Judge:

Iroquois Gas Transmission System, L.P., ran up substantial legal defense costs as a result of federal investigations into environmental violations committed in its construction of a natural gas pipeline. The Federal Energy Regulatory Commission issued orders excluding these legal costs from the rate base used to calculate Iroquois’s permissible charges, explaining that Iroquois had failed to carry the burden of proving that the costs were prudently incurred. Iroquois says the orders were grounded in an impermissible presumption of non-recoverability and asks us to set them aside, relying primarily on our decisions in Mountain States Telephone and Telegraph Co. v. FCC, 939 F.2d 1021 (D.C.Cir.1991) (“Mountain States I”) and Mountain States Telephone and Telegraph Co. v. FCC, 939 F.2d 1035 (D.C.Cir.1991) (“Mountain States II”). Because the Commission has failed to come to grips with the questions that Mountain States II said must be answered when addressing a utility’s recovery of legal expenses, we remand the ease for a more reasoned decision.

* Hs *

In November 1990 the Commission granted Iroquois, a certificate of public convenience and necessity under Section 7 of the [399]*399Natural Gas Act (the “Act”), authorizing the company to build and operate a new pipeline stretching from the Canadian border to Long Island. The pipeline went into full service in January 1992. Before long, however, Iroquois found itself in trouble for environmental violations. Around November 1991 the U.S. Attorney’s Office for the Northern District of New York, in conjunction with the FBI and the Environmental Protection Agency, began an investigation into whether Iroquois’s construction activities violated the Clean Water Act. The record suggests that the investigation focused on points where the pipeline crossed creeks and streams in upstate New York, allegedly discharging silt and sediment in violation of Iroquois’s Clean Water Act permit, and on Iroquois’s alleged failure to build so-called trench breakers, which control soil erosion and pipeline corrosion. An Army Corps of Engineers inspection report from early 1992 cited a potential overall penalty of more than $115,000,000. Civil investigations, presumably closely related, were also undertaken by the U.S. Attorney’s offices for the Northern, Eastern, and Southern Districts of New York. In addition, FERC’s own enforcement staff launched a separate investigation to determine whether Iroquois had violated the environment-related conditions of its Section 7 certificate. Ultimately an Iroquois affiliate and four of its employees entered into guilty pleas and a civil settlement costing $22 million in fines and penalties, and Iroquois consented to a settlement with the Commission admitting violations of environmental conditions in its certificate and agreeing not to pass the fines and penalties on to its ratepayers. Iroquois Gas Transmission System, L.P., 75 FERC ¶ 61,205 (1996).

In the course of resolving these disputes Iroquois ran up a legal bill of more than $15,000,000. While the various investigations were still under way, Iroquois filed with the Commission for a general rate increase to recover its pipeline construction costs. The rate proceeding culminated in a settlement between Iroquois and its customers resolving all issues except the rate and accounting treatment of the legal defense costs. Hearings on these reserved , issues were held before an administrative law judge, who determined that the legal costs were not unrecoverable per se, and observed that “[t]he participants have presented nothing to rebut Iroquois’s position that the legal costs were incurred as an appropriate and normal response to investigatory activities arising from the construction undertaken to provide service to the ratepayers.” Iroquois Gas Transmission System, L.P., 72 FERC ¶ 63,004, at 65,027 (1995).

The Commission reversed the ALJ’s initial decision and held' that Iroquois’s legal defense costs could not be included in its rate base. Iroquois Gas Transmission System, L.P., 77 FERC ¶ 61,288 (1996). “Allowing recovery of Iroquois’ litigation expenses,” the Commission concluded,

would fail to recognize the interests of Iroquois’ ratepayers, shared by the Commission, that emanate from Section 7 of the NGA. These, interests are to ensure that the pipeline is built in compliance with all applicable federal environmental and safety laws so as to prevént any future personal injuries or environmental damage.

Id. at 62,280. The Commission based its disallowance of recovery on Iroquois’s failure to demonstrate any. countervailing economic or non-economic benefit to ratepayers from the activities that gave rise to the investigations. The Commission denied Iroquois’s request for rehearing, Iroquois Gas Transmission System, L.P., 78 FERC ¶ 61,216 (1997), and later rejected similar claims in a second rate, ease filed by Iroquois. Iroquois Gas Transmission System, L.P., 77 FERC ¶ 61,352, at 62,538 (1996), rehearing denied, 80 FERC ¶ 61,199, at 61,797-98 (1997). Iroquois petitioned for review in this court.

At the outset the Commission concedes two propositions, one general and one specific to this case. First, the Commission admits that although the Act gives the natural gas company the burden of showing that a proposed rate increase is just and reasonable, 15 U.S.C. § 717c(e), as a matter of FERC practice “a natural gas company is ordinarily not required to show that all of its expenditures were prudent unless serious doubts are raised regarding the prudence of -those [400]*400costs.” FERC Br. at 24. See, e.g., Trans World Airlines, Inc. v. CAB, 385 F.2d 648, 657 (D.C.Cir.1967); Minnesota Power & Light Co., 11 FERC ¶ 61,312, at 61,645 (1980). Second, the Commission does not seriously contest that it effectively raised a presumption against recovery in this case, putting the burden on Iroquois to demonstrate that its expenditures were prudently incurred. See 78 FERC at 61,927 (“[S]ince [Iroquois] was seeking to recover the legal defense costs in its rates, it had the burden of proving that the costs were just- and reasonable.”). Indeed, at times the Commission seemed to erect something close to an irre-buttable presumption against recovery. See id. (“Iroquois placed itself in the untenable position of arguing that its illegal activities, supposedly taken to save time and money during construction, were in the interests of its ratepayers, ánd, therefore, just and reasonable.”) (emphasis added).

The Commission contends, however, that it adequately justified its decision to invert the normal presumption in this case, because Iroquois’s legal costs by their very nature raised a serious doubt as to prudence (i.e., because they grew out of civil and criminal violations).1 See FERC Br. at 24.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
145 F.3d 398, 330 U.S. App. D.C. 271, 28 Envtl. L. Rep. (Envtl. Law Inst.) 21497, 1998 U.S. App. LEXIS 16471, 1998 WL 403645, Counsel Stack Legal Research, https://law.counselstack.com/opinion/iroquois-gas-transmission-system-lp-v-federal-energy-regulatory-cadc-1998.